SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 1144

IN THE HIGH COURT OF JUDICATURE AT BOMBAY 
Alok Aradhe, CJ., Sandeep V. Marne, J.
Gammon India Limited - Appellant
Versus
Konkan Railway Corporation Ltd. - Respondent
Appeal No. 255 of 2007 In Arbitration Petition No.327 of 2006
Decided On : 22-07-2025

Advocates:
Advocate Appeared:
For the Appellant : Mr. Amrut Joshi with Mr. Yazad Udwadia and Mr. Aditya Mhatre i/b Mr. Akshay Zantye
For the Respondent: Mr. Tushad Kakalia with Mr. D. J. Kakalia, Mr. Paresh Patkar and Mr. Ayan, Zariwalla i/b Mulla & Mulla & Craigie Blunt & Caroe

The judiciary's role in arbitration is to ensure courts do not reassess merits but identify manifest errors and whether vital evidence was overlooked by the arbitral tribunal.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 and Section 37 - Appeal against setting aside of Arbitral Award - Jurisdiction of courts under Section 34 limited to manifest errors and not to reassess merits - Court found that Arbitral Tribunal did not consider vital evidence pertaining to claims for electricity charges, price variation due to minimum wage increase, and extra excavation costs - Learned Single Judge's interference justified as it did not exceed jurisdiction by addressing the material evidence ignored by the Tribunal. (Paras 1-36)

(B) Awarding claims - The learned Single Judge acted within his scope when setting aside claims under laws and contractual obligations that were either ignored or misinterpreted by the Arbitral Tribunal, confirming that courts do not act as first Appellate Courts in arbitration matters. (Paras 4, 6, 29, 30, 36)

Facts of the case:
A construction company challenged the setting aside of arbitral awards concerning claims for unpaid charges and increases in costs incurred during the tunneling project. The arbitral tribunal had awarded certain claims but some were overturned by the learned Single Judge under Section 34, leading to this appeal.

Findings of Court:
The learned Single Judge found that crucial correspondence and contractual clauses were ignored by the Arbitral Tribunal, affirming the dismissal of the original awards for certain claims.

Issues: Determining if the learned Single Judge exceeded his jurisdiction in setting aside the Arbitral Tribunal's awards regarding claims for electricity charges, wage increases, and excavation costs.

Ratio Decidendi: Court clarified that jurisdiction under Section 34 is restricted to checking for errors and whether vital evidence was considered; the learned Judge acted correctly in setting aside awards that ignored essential material.

Result: Appeal dismissed.

Table of Content
1. outline of appeal and factual background (Para 1 , 2 , 3)
2. appellant's contention on the excess of jurisdiction by the single judge (Para 4 , 5 , 6 , 7 , 9)
3. response to interference on jurisdiction under section 34 (Para 8 , 10 , 11)
4. judicial scrutiny of arbitral decisions is limited to legal framework. (Para 12)
5. recognition of the arbitral tribunal's authority within explicit statutory limits. (Para 18 , 34)
6. analysis of claim 5 regarding electricity charges (Para 21 , 22 , 23)
7. assessment of claim 6 and claim 8 (Para 29 , 30 , 31)
8. final ruling and dismissal of appeal (Para 35 , 36)

JUDGMENT :

Sandeep V. Marne, J.

1. This is an Appeal filed under the provisions of Section 37 of the Arbitration and Conciliation Act, 1996 (the Act) challenging the order dated 16 November 2006 passed by the learned Single Judge of this Court in Arbitration Petition No.327/2006, in which Award passed by the Arbitral Tribunal was challenged under Section 34 of the Act. By the impugned order dated 16 November 2006, the learned Single Judge has allowed Arbitration Petition No.327/2006 and has set aside the Arbitral Award, by which three claims of the Appellant towards electricity charges, price variation on account of increase in minimum wages and extra cost of excavation were allowed by the Arbitral Tribunal.

2. Brief facts leading to filing of the present petition are that Konkan Railways Corporation Ltd. (KRCL) a public utility undertaking of the Government of India invited tenders for construction of B.G. Single Line Tunnel (Tunnel No.20 – Karbude Tunnel) in Ratnagiri (North). The Appellant was a successful bidder and was issued Letter of Acceptance dated 25 June 1991. Agreement dated 9 July 1991 was executed for construction of the tunnel walls. The work was completed after grant of several extensions. On 14 September 1998, Appellant submitted the final bill and on 22 May 2001, a further amended final bill was submitted. The Appellant invoked arbitration clause raising disputes for total 25 claims totaling to Rs.15,62,29,315/-. The Arbitral Tribunal was constituted on 16 May 2003. Appellant- Claimant filed Statement of Claim, which was resisted by Respondent by filing its Written Statement. After considering the documentary and oral evidence, the Tribunal made an Award on 14 January 2006 awarding sum of Rs.4,39,38,389/- in favour of the Appellant by fully accepting some of the claims, partly accepting some claims and rejecting some claims.

3. Respondent accepted the Arbitral Award in respect of Claim Nos.1, 2, 7, 10, 19, 21 and 22 and decided to challenge the Award only in respect of the Award of Claim Nos.5, 6 and 8. Accordingly, Respondent filed Arbitration Petition No. 327/2006 in this Court challenging the Award dated 14 January 2006 to the limited extent of award of Claim No.5 (Refund of recoveries towards electricity charges), Claim No.6 (Reimbursement of difference between price variation on account of increase in minimum wages) and Claim No.8 (Extra cost in excavation of soft strata of Tunnel from Bhoke Portal side). By the impugned order dated 16 November 2006, the learned Single Judge has allowed Arbitration Petition No. 327/2006 and has set aside the arbitral award only to the extent of Claim Nos. 5, 6 and 8. Aggrieved by the order dated 16 November 2006, the Appellant-Claimant has filed the present Appeal under the provisions of Section 37 of the Act.

4. Mr. Amrut Joshi, the learned counsel appearing for the Appellant would submit that the learned Single Judge has exceeded the jurisdiction under Section 34 of the Act while interfering with the Arbitral Award. That the decision of the Arbitral Tribunal was based on judicial approach and does not suffer from the vice of perversity or irrationality and in support, he would place reliance on judgment of the Apex Court in Associate Builders Versus. Delhi Development Authority , [ (2015) 3 SCC 49 ] He would further submit that the scope of appeal under Section 37

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top