IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ALOK ARADHE, CJ, SANDEEP V. MARNE, J.
Larsen & Tourbo Limited - Appellant
Versus
Hindustan Petroleum Corporation Ltd. and Another - Respondents
Appeal Nos. 14, 26 of 2006, Arbitration Petition No. 449 of 2003
Decided On : 08-08-2025
| Table of Content |
|---|
| 1. challenges to arbitration awards (Para 1) |
| 2. facts about the tender and arbitration (Para 2 , 3 , 4) |
| 3. previous appeals and supreme court directives (Para 5 , 6 , 7 , 8) |
| 4. case law regarding arbitral awards (Para 9) |
| 5. arguments of l&t and hpcl regarding claims (Para 10 , 11 , 12 , 13) |
| 6. court's reasoning on various claims (Para 15 , 16 , 18 , 19) |
| 7. final observations reiterated the court's obligation to uphold judicial decisions absent clear error. (Para 17) |
| 8. final conclusions aligned with judicial precedent on evidence in arbitration. (Para 56) |
| 9. final conclusion of appeals (Para 57 , 62) |
JUDGMENT :
SANDEEP V. MARNE, J.
The Challenge
1. These are cross appeals filed under provisions of Section 37 of the Arbitration and Conciliation Act, 1996 (the Act) challenging the judgment and order dated 16 November 2005 passed by learned Single Judge of this Court in Arbitration Petition No. 449 of 2003. Arbitration Petition No. 449 of 2003 was filed by Hindustan Petroleum Corporation Limited (HPCL) challenging the award made by the Arbitral Tribunal on 4 July 2003 by which, various claims raised by the original claimant-Larsen and Turbo Limited (L&T) were granted. By the impugned order dated 16 November 2005, the learned Single Judge has set aside the award qua Claim Nos. 1, 2, 4, 9, 15, 16, 21(1), 21(3) and 21(4) awarded by the Arbitral Tribunal. The learned Single Judge has retained the award only to the extent of Claim No. 19. Accordingly, original Claimant-L&T has filed Appeal No. 26 of 2006 to the extent of setting aside the award qua Claim Nos. 1, 2, 4, 9, 15, 16, 21(1), 21(3) and 21(4) whereas the original Respondent-HPCL has filed Appeal No. 14 of 2006 to the extent of the learned Single Judge maintaining the award qua Claim No. 19.
Facts
2. A tender was floated by HPCL for executing the work of laying, testing, pre-commissioning and commissioning of 18 inch diameter and 350 kilometers pipeline from Vishakhapatnam to Vijaywada, including temporary cathodic protection and optical fiber cable work (Work). L&T submitted its bid in pursuance of the tender on 23 April 1996. HPCL issued Letter of Intent, followed by Letter of Allotment, in favour of L&T for execution of the work at a contract price of Rs. 53,64,39,858/- on 25 November 1996. The contractual date for commencement of work was 10 December 1996 and the completion date was 25 November 1997. Engineers India Limited was appointed as Engineer-in-Charge in respect of the work. On 23 September 1997, L&T applied for further extension up to 31 March 1998. The Engineer-in-Charge extended the period for completion of work up to 30 April 1998 with the consent of HPCL. L&T could not complete the work by 30 April 1998 and hence sought further extension up to 30 June 1998. The Engineer-in-Charge, however, refused to grant an extension beyond 30 April 1998. According to L&T, it released the entire pipeline from Vishakhapatnam to Vijaywada for water filling (Hydrotesting) on 10 May 1998. It is claimed by L&T that on 11 May 1998, HPCL pumped water/project through pipeline. Work Completion Certificate was issued on 20 August 1998 by HPCL.
3. In the above background, disputes arose between HPCL and L&T and L&T invoked the arbitration clause on 22 August 2000 and called upon the Marketing Director of HPCL to nominate an Arbitrator. HPCL appointed its General Manager to act as the sole arbitrator on 21 September 2000. Both the parties agreed that no oral evidence would led and that they would be represented by their functional department officers and/or law officers. The Arbitrator made the award on 4 July 2003. Out of total 30 Claims of Rs. 27,82,74,107/-, only 16 Claims were allowed for an aggregate amount of Rs. 7,43,66,444/-.
Proceedings under Section 34
4. Aggrieved by the award of the Arbitral Tribunal dated 4 July 2003, HPCL filed Arbitration Petition No. 449 of 2003 before the learned Single Judge of this Court, challenging the award under the provisions of Section 34 of t
Municipal Corporation of Delhi vs. Jagan Nath Ashok Kumar and another
Jagdish Chander vs. Hindustan Vegetable Oils Corporation and another
State of Orissa vs. Dandasi Sahu
U.P. Hotels and others v. U.P. State Electricity Board
Builders vs. Delhi Development Authority
Santa Sila Devi and another vs. Dhirendra Nath Sen and others
Bijendra Nath Srivastava (Dead) through LRs. vs. Mayank Srivastava and others
Venkatesh Construction Company vs. Karnataka Vidyuth Karkhane Limited (Kavika)
M/s. Larsen Air Conditioning and Refrigration Company v. Union of Indian and Ors.
Mcdermott International Inc. vs. Burn Standard Co. Ltd. and Ors.
Court's intervention under Section 34 is valid when arbitral award lacks evidence or deviates from contractual terms, while retention of claims based on clear factual findings is upheld.
Point of law: Arbitral Tribunal is not bound by the Code of Civil Procedure or the Indian Evidence Act.
The judiciary's role in arbitration is to ensure courts do not reassess merits but identify manifest errors and whether vital evidence was overlooked by the arbitral tribunal.
The appeal was allowed, reinstating the arbitrator's award which concluded that the termination of the contract was illegal due to failure in fulfilling mutual obligations concerning site availabilit....
The court confirmed the validity of the Arbitrator's findings regarding excess work claims and the correct application of interest, highlighting that overlapping interest claims were erroneous.
The scope of interference with an Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996 is fairly limited and narrow. The Courts shall not sit in an appeal while adjudicating ....
The court affirmed that arbitral awards challenging under Sections 34 and 37 are limited in scope, requiring clear evidence of illegality or perversion; otherwise, the Arbitrator's decision stands.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.