2012 Supreme(Del) 930

High Court of Delhi
S. MURALIDHAR, J.
Vale Australia Pvt. Limited & Others
Versus
Steel Authority of India Limited & Another
O.M.P. Nos.414 OF 2011, 415 OF 2011, 451 OF 2011
Decided on : 30-03-2012

Act Referred

ARBITRATION AND CONCILIATION ACT : S.34
CONSTITUTION OF INDIA : Art.14
CONTRACT ACT : S.23, S.55, S.63

Headnote

The Court upheld the arbitral award in favor of SAIL and dismissed the petitions filed by Vale and AMCI challenging the award. The Court found that Vale and AMCI were in breach of the LTA by failing to deliver the contracted quantity of hard coking coal during the First Delivery Period (FDP). The Court also held that SAIL was entitled to claim damages for the breach, including the difference in price between the contracted price and the price at which it effected risk purchase, and that SAIL had not waived its right to seek risk purchase damages. The Court further held that the Tribunal did not err in awarding interest on the damages from the date of the request for arbitration until the date of the award.

Fact of the Case:

SAIL entered into a Long Term Agreement (LTA) with Vale and AMCI for the supply of hard coking coal. Vale and AMCI failed to deliver the contracted quantity of coal during the First Delivery Period (FDP). SAIL claimed damages for the breach, including the difference in price between the contracted price and the price at which it effected risk purchase. Vale and AMCI challenged the arbitral award in favor of SAIL.

Finding of the Court:

The Court found that Vale and AMCI were in breach of the LTA by failing to deliver the contracted quantity of hard coking coal during the FDP. The Court also held that SAIL was entitled to claim damages for the breach, including the difference in price between the contracted price and the price at which it effected risk purchase, and that SAIL had not waived its right to seek risk purchase damages. The Court further held that the Tribunal did not err in awarding interest on the damages from the date of the request for arbitration until the date of the award.

Issues: 1. Whether Vale and AMCI were in breach of the LTA? 2. Whether SAIL was entitled to claim damages for the breach? 3. Whether SAIL had waived its right to seek risk purchase damages? 4. Whether the Tribunal erred in awarding interest on the damages?

Ratio Decidendi: 1. The Court found that Vale and AMCI were in breach of the LTA by failing to deliver the contracted quantity of hard coking coal during the FDP. The Court noted that Vale and AMCI had admitted their inability to make the balance supplies under the LTA and that they had advised SAIL to consider other sourcing options. 2. The Court held that SAIL was entitled to claim damages for the breach, including the difference in price between the contracted price and the price at which it effected risk purchase. The Court noted that the risk purchase clause in the LTA permitted SAIL to take such action at the cost of the defaulting seller. 3. The Court held that SAIL had not waived its right to seek risk purchase damages. The Court noted that the letter from Vale and AMCI to SAIL, in which they stated that they were unable to deliver the contracted quantity of coal, did not amount to a waiver of their liability for damages. 4. The Court held that the Tribunal did not err in awarding interest on the damages from the date of the request for arbitration until the date of the award. The Court noted that the Tribunal had awarded interest at a reasonable rate and that the award was in accordance with the law.

Final Decision: The Court upheld the arbitral award in favor of SAIL and dismissed the petitions filed by Vale and AMCI challenging the award.

Advocates Appeared:
For the Petitioners:Arvind Nigam, Senior Advocate with Amit Sibal, Anirudh Das, and Ms. Smarika Singh, Rajiv Nayar, Senior Advocate with Dhirendra Negi, Dheeraj Nair,and Shidharth Sethi, Advocates.
For the Respondents:R-1, A.K. Ganguli and Sanjay Jain, Senior Advocates with Sharat Kapoor, Sunil K. Jain, Aneesh Mittal, Parmatma Singh, Ms. Reeta Chaudhary, Mayank Jain and Sachin Sharma , R-2, Rajiv Nayar, Senior Advocate with Dhirendra Negi, Dheeraj Nair and Shidharth Sethi, Arvind Nigam, Senior Advocate with Amit Sibal, Anirudh Das, and Ms. Smarika Singh, Advocates.

Judgment

1. These are three petitions under Section 34 of the Arbitration and Conciliation Act, 1996 (‘Act’) arising out of the proceedings in which a final Award dated 10th March 2011 was passed by the Arbitral Tribunal (‘Tribunal’) constituted under the Rules of Arbitration of the ICC International Court of Arbitration.

2. OMP No.414 of 2011 is by Vale Australia Pty Ltd. (‘Vale’) formerly known as CVRD Australia Pty Ltd. and OMP No.415 of 2011 is by AMCI Pty Ltd. (‘AMCI’). Both petitions

challenge the final Award dated 10th March 2011 whereby the Tribunal allowed the claim of Respondent No.1 - Steel Authority of India Ltd. (‘SAIL’) for damages and held that Vale and AMCI were liable to pay SAIL damages equivalent to US Dollar (‘USD’) 152,270,789.10, simple interest on the said sum at the rate of 2.335364% per annum pendente lite from 2nd April 2009 till the date of the Award aggregating to USD 6,897,815.48, 80% of the SAIL’s legal costs and expenses in the sum of USD 320,000 and a sum of USD 160,000 being the advance on costs paid by the SAIL to ICC.

3. After the final Award was passed, both Vale and AMCI filed separate applications on 7th April 2011 under Section 33 of the Act praying for an additional award on the issue of interest for the post-Award period. These applications were rejected by the Tribunal on 16th May 2011 clarifying that the Tribunal had “consciously omitted to make any direction on post-Award interest in the final Award”. AMCI has filed a separate petition being OMP No.451 of 2011 under Section 34 of the Act challenging the aforementioned Order dated 16th May 2011. Background Facts

4. Vale is a company incorporated in Australia having its registered office at Brisbane. It was formerly known as AMCI Australia Pty. Ltd. It was renamed as CVRD Australia Pty. Ltd. and thereafter as Vale after the CVRD Group acquired the shares of AMCI Holding Australia Pty. Ltd., the parent Company of AMCI Australia Pty Ltd. pursuant to an agreement executed on 24th February 2007. AMCI Australia Pty. Ltd. was acting both as the coal producer and seller in terms of the earlier agreements executed between AMCI Australia Pty Ltd. and SAIL as well as under the Long Term Agreement (‘LTA’) dated 23rd April 2007 (LTA 217/2007) between the parties which forms the subject matter of the present dispute. After the acquisition by the CVRD Group of Vale, Vale acted as the producer under the Agreement and AMCI Pty. Ltd. (AMCI) which was the newly formed subsidiary of AMCI Australia Pty. Ltd. was to act as the seller. In other words, under the present arrangement, Vale was the producer of coal and AMCI was the seller.

5. By an Agreement dated 22nd June 2004 and by a subsequent Agreement dated 12th April 2005 Vale, then known as AMCI Australia Pty Ltd., had completed supplies of coking coal to SAIL. Under the LTA in question dated 23rd April 2007, Vale and AMCI agreed to supply SAIL 750,000 Metric Tonnes (‘MT’) of Broad-Borough medium volatile hard coking coal. Pursuant to an amendment dated 7th June 2007, Vale and AMCI were jointly responsible to supply the contracted hard coking coal, with Vale acting as the producer and AMCI the seller.

6. In terms of Clauses 1.1, 1.2, and 1.3 of the LTA 750,000 MT plus/minus 10%, plus 250,000 MT at SAIL’s option, was to be supplied by Vale and AMCI to SAIL within the delivery period from July 2007 to June 2008 [hereinafter referred to as ‘the First Delivery Period’ (FDP)] at a price of USD 96.45 per MT (‘PMT’) FOB. In terms of Clause 2, the price for the later delivery periods was to be mutually fixed prior to the commencement of the delivery period. Clause 1 of the LTA specified that Broad-Borough Medium Volatile hard coking coal was to be a blend of 50% Carborough Downs hard coking coal and 50% Broadlea hard coking coal.

7. On 26th March 2007, SAIL exercised its option for purchase of an additional quantity of 250,000 MT Broad-Borough hard coking coal for supply during the FDP. Vale and AMCI suppli



















































































































































1
2
3
4
5
6
7
8
9
10
11