IN THE HIGH COURT OF DELHI AT NEW DELHI
Sanjeev Narula, J.
Orchid Infrastructure Developers (p). Ltd. - Appellant
Versus
Five Star Constructions Pvt. Ltd. - Respondent
O.M.P. (Comm) 124/2019 & I.A. 11506/2021.
Decided On : 19-07-2022
Arbitration and Conciliation Act - Construction Contract - Section 34 - 11(3) - The court set aside the arbitral award which allowed the respondent's claim in part and dismissed the petitioner's counter-claims. The court found that the award was arbitrary, erroneous, and against public policy as it lacked reasoning and was based on conjecture and surmises. The court held that the award was contrary to the statutory mandate of the Act and failed to provide any basis for accepting the claim. The impugned award was set aside to the extent it awarded Rs. 4,33,877/- and interest thereon.
Fact of the Case:
The petitioner awarded a construction contract to the respondent, but a dispute arose due to delays in completion of work. The respondent terminated the contract, and the parties invoked arbitration. The arbitral award allowed the respondent's claim in part and dismissed the petitioner's counter-claims.
Finding of the Court:
The court found that the arbitral award was arbitrary, erroneous, and against public policy. It lacked reasoning, was based on conjecture and surmises, and failed to fulfill the statutory mandate of the Act. The court set aside the award to the extent it awarded Rs. 4,33,877/- and interest thereon.
Issues: The issues included the validity of the arbitral award, the reasoning behind the award, and the statutory compliance under the Act.
Ratio Decidendi: The court held that the arbitral award was arbitrary, lacked reasoning, and failed to provide any basis for accepting the claim. It was set aside as it was contrary to the statutory mandate of the Act.
Final Decision: The court allowed the petition and set aside the impugned award to the extent it awarded Rs. 4,33,877/- and interest thereon.
JUDGMENT
Sanjeev Narula, J. - The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 [hereinafter, 'the Act'] impugns the arbitral award dated 10th September, 2018, whereby the Sole Arbitrator has dismissed Petitioner's counter-claim and allowed Respondent's claim in part - to the extent of Rs. 4,33,877/-.
BRIEF FACTS
2. Petitioner - Orchid Infrastructure Developers Pvt. Ltd. [hereinafter, 'ORCHID'] awarded a contract vide letter dated 28th December, 2012, for 'Construction of 21 Dwelling Units, ORCHID ISLAND at Gurugram on 7 plots bearing numbers 257 to 262 and 261-A' [hereinafter, 'Contract'] to Respondent - Five Star Constructions Pvt. Ltd. [hereinafter, 'FIVE STAR'] for a consideration of Rs. 2,21,01,162/-. The construction was tentatively to be completed within a period of twelve months i.e., on or before 31st December, 2011.
3. Dispute arose between the parties with regard to delays in completion of work under the Contract. ORCHID contends that it released a mobilisation advance of Rs. 11,05,058/- to FIVE STAR and routinely made payments in terms of the Contract. FIVE STAR repeatedly sought extensions, which were granted by ORCHID, without prejudice to its rights to raise claims. Thereafter, ORCHID issued a show-cause notice dated 1st November, 2012, to which, there was no satisfactory response from FIVE STAR. Ultimately, on 23rd May, 2013, FIVE STAR terminated the Contract. ORCHID then issued a final bill dated 20th November, 2013, which was responded by FIVE STAR asking ORCHID to depute a suitable person for joint verification of the work done. ORCHID contended that a substantial portion of work was still left to be completed, and the same was awarded to other contractors at the cost and risk of FIVE STAR. Further, ORCHID was also forced to pay a 'delay penalty' to its customers, on account of the delay in handing over possession of the dwelling units.
AT ARBITRATION
4. In the circumstances noted above, FIVE STAR invoked arbitration under Section 11 of the Act, which led to appointment of the Arbitral Tribunal by this Court vide order dated 27th May, 2016. FIVE STAR raised claims towards:
(i) Rs. 29,60,466/- (towards expenditure incurred on work done till 14th January, 2013);
(ii) interest; and
(iii) costs. ORCHID filed its counter-claim qua mobilization advance, liquidated damages due to FIVE STAR'S failure to complete work, cost for pending work commissioned by ORCHID from other contractors and costs.
5. The Arbitrator, vide impugned award dated 10th September, 2018, allowed FIVE STAR'S claim in part and directed ORCHID to pay a sum of Rs. 4,33,877/- along with post-award interest payable at 12% per annum. The remaining claims, as well as ORCHID's counter-claims, were dismissed.
CONTENTIONS OF THE PARTIES
ON BEHALF OF ORCHID
6. Although, ORCHID seeks setting-aside of the impugned award with respect to award of claim and dismissal of counter-claims; however, Mr. Manish Sharma, counsel for ORCHID, has addressed arguments only qua the award of claim of Rs. 4,33,877/-, and no serious challenge was raised qua dismissal of counter-claims. His submissions summarised as follows:
6.1. The impugned award is arbitrary, erroneous and against the public policy of India - as it gives no reasoning for award of the claim in favour of
FIVE STAR.
6.2. The impugned award is based on conjuncture and surmises and fails to fulfil the statutory mandate of Section 31(3) of the Act. The Arbitrator has erroneously and mistakenly held in paragraph no. 11.28 of the impugned award that ORCHID (in its Statement of Defence), has admitted to the pleadings qua interim relief, and on the basis of such 'deemed admission', ruled in favour of FIVE STAR. On the contrary, ORCHID had categorically refuted FIVE STAR's claim and had rather raised counter-claims of recovery of mobilisation advance, liquidated damages, etc.
6.3. Since the Arbitrator has rejected the main claim for Rs. 29,60,466/-, which included Rs. 4,33,877/- claimed as interim re
Associate Builders vs. Delhi Development Authority 2015 (3) SCC 49
Indian Oil Corporation Ltd. vs. Shri Ganesh Petroleum (2022) 4 SCC 463
The main legal point established in the judgment is that an arbitral award must provide reasoning and comply with the statutory mandate of the Arbitration and Conciliation Act. Arbitrary awards lacki....
Judicial review of arbitral awards is limited; courts should not interfere unless there is clear evidence of perversity or violation of public policy.
The court confirmed the validity of the Arbitrator's findings regarding excess work claims and the correct application of interest, highlighting that overlapping interest claims were erroneous.
Judicial interference with an arbitral award under Section 34 is limited to specific grounds. Courts cannot re-appreciate evidence or substitute their own view. Where parties are given adequate notic....
The Court emphasized the limited scope of jurisdiction under Section 34 of the Act and the need for evidence to support claims for loss of profit.
The limited grounds for interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, emphasize the concept of patent illegality and the criteria for setting asi....
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.