IN THE HIGH COURT OF DELHI AT NEW DELHI
CHANDRA DHARI SINGH, J.
FLOWMORE LIMITED – Petitioner
Versus
M/S SKIPPER LIMITED – Respondent
O.M.P. (COMM) No. 391 of 2022
Decided On : 02-02-2023
Arbitration and Conciliation Act, 1996 – Section 9, 34 – Sale of Goods Act, 1930 –Section 41 – Manufacturing Clearance – Contrary to fundamental policy of Indian Law – Fundamental Policy of Indian Law – Ground of patent illegality – Instant petition under section 34 of Arbitration and Conciliation Act, 1996 has been filed on behalf of the petitioner seeking reliefs – Held, Court is of the view that on the application of the rule of contra proferentem, the Purchase Order was fittingly interpreted by the Learned Arbitrator, leaving no scope for interference of this Court on the Award – Learned Arbitrator rightfully found Petitioner to be guilty of breach of contract, which resulted in Respondent incurring losses and hence validates award of a sum to Respondent – Court disagrees with Petitioner's submission that Respondent had shown no proof of any loss caused to it and that Respondent was attempting to make unjust gains from Petitioner – Learned Arbitrator has accurately considered documents on record to conclude that Respondent has indeed incurred loss due to Petitioner's actions and hence is liable to be compensated – In view of above discussion of facts and law, Court finds no reason to set aside Impugned Arbitral Award – Petition dismissed.
JUDGMENT :
CHANDRA DHARI SINGH, J.
1. The instant petition under section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter “The Act, 1996”) has been filed on behalf of the petitioner seeking the following reliefs:
(B) Allow and accordingly grant Counter Claim as prayed for by the Petitioner in Arbitration Case Ref. No. 05/02/2020.
(C) Award costs in favour of the Petitioner and against the Respondent.
(D) Grant any other relief which this Hon'ble Court may deem fit and proper in the facts and circumstances of the case in favour of the Petitioner.”
FACTUAL MATRIX
2. The facts necessary for the disposal of the present petition are that the Petitioner is a Public Limited Company that primarily deals in the area of large speciated application pumps and has diversified into the power sector. Flowmore Jagabandhu JV, the Petitioner's joint venture with Jagabandhu Enterprises Ltd. was awarded a contract for the Design, Engineering, Supply, Erection, Testing, and Commissioning of a 132/33 KV, 2 x 50 MVA grid sub-station including the construction of Control Room Building & approach road as well as other civil works for 8 transmission lines by Jharkhand Urja Sancharan Nigam Ltd. (hereinafter “JUSNL”).
3. The Respondent was engaged by the Petitioner as the manufacturer and supplier of customized towers and other ancillary goods as per the specifications and other details provided the respondent for transmission lines to be erected for its client JUSNL, in various districts vide the Contract/Purchase Order dated 02.03.2019.Prior to this, the respondent vide an e-mail dated 20.02.2019, sent a purchase enquiry to the claimant for the manufacture and supply of structural material for 122/132 KV Sub-Station for JUSNL Tender NIT. No. 244 to 249.Pursuant to negotiation and discussion, Purchase Order no. Ref. FL/Skipperj-JUSML-PKG-244-249/60 dated 02.03.2019 was issued by the Petitioner in favour of the Respondent, for the supply of fabricated and galvanized HDG tower parts, stubs, cleats (for both mild steel and HT steel), MS templates, earthing of tower materials, and fasteners for the project.
4. According to the Respondent, as per the contract, the Petitioner was to provide structural drawings, shop sketches, BOM of items to the Respondent. Based on these, the Respondent was to arrange sketches and BOM for approval before mass production. The Respondent was to get all drawings/documents approved directly from JUSNL.
5. According to the Petitioners, as per the mutual agreement between the parties dated 8th March 2019, it was evidently clear that the approvals and drawings were to come from the Respondent.
6. The Supplier was to start manufacturing material only after getting a written Manufacturing Clearance (hereinafter “MC”) from the buyer. The quantity cleared in MC only was to be manufactured by the supplier. Any material manufactured without getting the MC from the buyer was to be rejected. Hence, the Respondent had to provide a prototype-type to the Petitioner to conduct an inspection, subsequent to which an advance payment was to be made.
7. The transaction between the parties lasted for a brief duration of 3 months, after which it was prematurely terminated by the Petitioner on 25th July 2019 based on the alleged delay and breach of contractual obligations by the Respondent. Further, the Petitioner engaged with RR Ispat as its supplier on the same day the contract with the Respondent was terminated.
8. In January 2020, an application under Section 9 of the Act, 1996, bearing O.M.P. (I) (COMM.) No. 3/2020 came to be filed by the Respondent before this Court. By way of consent, vide order dated 27th January, 2020, the learned Sole Arbitrator was appointed by the this Court in O.M.P. (I) (COMM.) No. 3/2020 titled Skipper Ltd. vs. Flowmore Ltd.
9. Thereafter, the learned Sole Arbitrator rendered its Award on 05.07.2022 and awa
Champsey Bhara Company vs. The Jivraj Balloo Spinning and Weaving Company Ltd. AIR 1923 PC 66
Delhi Airport Metro Express Pvt. Ltd. vs. Delhi Metro Rail Corporation
Nabha Power Ltd. vs. Punjab State Power Corporation Ltd. (2018) 11 SCC 508
ONGC Ltd. vs. Western Geco International Ltd. 2014 (9) SCC 263
ONGC Ltd. vs. Saw Pipes Ltd. (2003) 5 SCC 705
Patel Engg. Ltd. vs. North Eastern Electric Power Corporation Ltd. (2020) 7 SCC 167
Satya Jain vs. Anis Ahmed Rushdie
Ssangyong Engg. and Construction Co. Ltd. vs. NHAI
State of Jharkhand vs. HSS Integrated SDN
Saw Pipes Ltd. (2003) 5 SCC 705
Trollope and Colls Ltd. vs. North West Metropolitan Regl. Hospital Board
Union of India vs. D.N. Revri and Co. (1976) 4 SCC 147
United India Insurance Co. Ltd. vs. Manubhai Dharmasinhbhai Gajera
Western Geco International Ltd. (2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12
Limited intervention of the Courts in arbitral proceedings is intended by the legislature. An Arbitral Award may only be set aside if it is patently illegal, against the public policy of India, based....
Limited grounds for setting aside an arbitral award under Section 34 of the Arbitration Act and the Court's reluctance to re-adjudicate disputes on their merits.
The limited scope of intervention by Courts in arbitral awards under Section 34 of the Arbitration and Conciliation Act, emphasizing the need to satisfy specific grounds for setting aside an arbitral....
The Court held that the learned Arbitrator had erred in decreeing the award with respect to the rate of interest, and hence, the Award qua issue no. 20 with regards to the rate of interest is liable ....
The main legal point established in the judgment is the requirement for the Arbitrator's conclusions to be based on evidence and not to ignore vital evidence, failing which the Award may be set aside....
The court affirmed that limited judicial review under Section 34 of the Arbitration Act does not allow for re-evaluation of arbitration awards unless they are demonstrably perverse, illegal, or devoi....
The limited grounds for interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, emphasize the concept of patent illegality and the criteria for setting asi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.