IN THE HIGH COURT OF DELHI AT NEW DELHI
Chandra Dhari Singh, J.
Nhpc Limited – Appellant
Versus
Jaiprakash Associates Ltd. – Respondent
O.M.P. (COMM) 482 of 2020
Decided On : 26-05-2023
The petitioner filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, objecting to the Award dated 7th October 2019, corrected on 18th December 2019, which granted additional costs to the respondent. The controversy arose from a Hydro Electric Project in Jammu and Kashmir. The petitioner objected to the Award on grounds of manifest disregard of the binding terms of the Contract, violation of statutory provisions, and public policy of India. The petitioner argued that the Award was patently illegal, lacked evidence and reasoning, and was barred by limitation. The respondent opposed the petition, claiming that the delay and additional costs were due to adverse geological conditions and law and order situation in Jammu & Kashmir. The Arbitral Tribunal granted the additional costs to the respondent, which the petitioner challenged in the petition.
Issues: The issues before the Court were: I. Whether the findings of the Arbitral Tribunal regarding additional costs were based on no evidence or no reasons. II. Whether the Arbitral Tribunal was barred from passing the Award on the basis of equity and good conscience.
Ratio Decidendi: The Court held that the Arbitral Tribunal failed to provide reasons for granting the additional costs and acted beyond the mandate of law by passing the Award on the basis of equity without express authorization from the parties. The Court set aside the findings in the impugned Award regarding the additional costs granted to the respondent.
Final Decision: The Court allowed the petition and set aside the findings in the impugned Award regarding the additional costs of Rs. 60 Crores granted in favor of the respondent. The pending applications, if any, were disposed of.
JUDGMENT
Chandra Dhari Singh, J.
1. The instant petition has been filed on behalf of the petitioner under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter "the Act") raising objections to the Award dated 7th October 2019, corrected on 18th December 2019, (hereinafter "the impugned Award"). The petitioner has prayed for the following reliefs:
"Set aside the Impugned Majority Award passed by (Retd.) Justice B. P. Jeevan Reddy and Sh. K.K. Madan ("Ld. Majority Tribunal") to the extent that it allows the claims of the Respondent and rejected Counter-Claims No. 1,2,10,13,14,16 and 17;
(b) Set aside the Impugned Minority Award passed by the V. K. Tyagi ("Ld. Minority Tribunal");"
FACTUAL MATRIX
2. The following course of events has led to the controversy and disputes between the parties which are before this Court:
a. The petitioner proposed a Hydro Electric Project on river Chenab at Kishtwar, Jammu and Kashmir (hereinafter "the work"). On 10th April 1995, the petitioner invited fresh bids for the work, after the same was abandoned by a previous awardee of the work, namely Dumaz-Sogea Borie SAE and was continued by the petitioner on its own between 1992 to 1995.
b. In the second phase, the work was divided into two packages, an Upstream Area Work and a Downstream Area Work. The Joint Venture of M/s Jaiprakash Industries Limited and M/s Statkraft Anlegg AS, subsequently amalgamated with M/s Jaypee Cement Limited and came to be known as M/s Jaiprakash Associates Limited, the respondent herein, also submitted its bid to the tender floated by the petitioner on 19th August 1995 and were awarded the work for the two packages on 3rd March 1997.
c. Accordingly, on 9th April 1997, the parties entered into a Contract, wherein the scope of work awarded was delineated including the time for completion of the work. However, due to certain hindrances, the respondent was not able to complete the work within the stipulated term of 33 months. Time extensions were also granted to the respondent to complete the work and hence, the project which was to be completed till the year 2000 was extended till 2007.
d. On 11th May 2007, the certificate of completion was issued to the respondent. Accordingly, the final bill for the two packages was also furnished by the respondent.
e. In the said bills produced by the respondent, there were additional costs which were said to have been incurred by the respondent. The respondent claimed a total amount of Rs. 360.56 Crores, which was rejected by the petitioner vide letter dated 25th January 2010 on the grounds that, first, the extension granted were as per the General Conditions of Contract entered into between the parties, second, the claim was not maintainable since it was put forth by M/s Jaiprakash Association Limited, whereas it was not an entity when the Contract was executed, and third, the respondent herein had submitted no claim undertaking as demanded by the petitioner. The respondent objected to the ground taken by the petitioner.
f. In the background of the aforesaid discrepancies, the respondent herein invoked Clause 39.2 of the Contract and invoked dispute resolution mechanism of arbitration to resolve and amicably settle the issues between the parties.
g. Accordingly, an Arbitral Tribunal was constituted comprising of three Arbitrators, including a Presiding Arbitrator, and arbitration proceedings were initiated between the parties.
h. Upon completion of pleadings and conclusion of arguments, the learned Tribunal passed the Minority and Majority Award dated 7th October 2019, which came to be corrected on 18th December 2019.
i. The petitioner, being aggrieved of both the Minority and Majority Award has approached this Court by way of the instant petition.
SUBMISSIONS
3. The learned counsel appearing on behalf of the parties were heard at length on the instant petition. Both the sides have also filed their written submissions, which are on record. A joint consideration of the arguments ad
Anand Brothers (P) Ltd. vs. Union of India & Ors.
Mcdermott International Inc. v. Burn Standard Co. Ltd
P. Radhakrishna Murthy v. National Buildings Construction Corp. Ltd.
Som Datt Builders Ltd. vs. State of Kerala
State of Rajasthan & Ors. v. Ferro Concrete Construction Pvt. Ltd.
The Arbitral Tribunal must provide reasons for its award, and it cannot pass an award on the basis of equity without express authorization from the parties.
An arbitral award must be supported by reasoning and evidence; a Minority Award is merely an opinion and cannot prevail over a Majority Award; the Court cannot modify an arbitral award.
The scope of interference with an Arbitral Award under Section 34 of the Arbitration and Conciliation Act, 1996 is fairly limited and narrow. The Courts shall not sit in an appeal while adjudicating ....
The Court held that the learned Arbitrator had erred in decreeing the award with respect to the rate of interest, and hence, the Award qua issue no. 20 with regards to the rate of interest is liable ....
Clauses in contracts that prohibit claims for damages are against public policy and void under Section 23 of the Indian Contract Act, 1872, as they undermine the sanctity of contracts.
Limited scope of interference and intervention by a Court in an Arbitral Award.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.