IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Jaiprakash Associates Limited - Appellant
Versus
NHPC Limited - Respondent
OMP (ENF.) (COMM.) 33 of 2020 & EX.Appl.(OS) 407 of 2021
Decided On : 22-09-2021
| Table of Content |
|---|
| 1. arbitral award enforcement context. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10) |
| 2. court's analysis of nhpc's objections. (Para 11 , 12 , 13 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36) |
| 3. arguments against enforcing the decree. (Para 14 , 15 , 16 , 17) |
| 4. final directive for payment by nhpc. (Para 37 , 38 , 39) |
JUDGMENT
Vibhu Bakhru, J. (Oral)--The Decree Holder (hereafter `JAL') has filed the present petition seeking enforcement of an Arbitral Award dated 19.02.2018, which was made a rule of the court by a judgment dated 08.04.2019 in CS(COMM.) 907/2018 captioned "M/s Jaiprakash Associates Limited v. NHPC Limited".
2. JAL and the Judgment Debtor (hereafter `NHPC') had entered into a contract on 27.05.1986 for construction of the main concrete dam and coffer dam at Chamera Hydroelectric Projects at Dalhousie, District Chamba, Himachal Pradesh. The disputes between the parties, essentially, relate to JAL's claim for payment of 25% mark up on the market rate of material utilised in execution of extra and deviated items of work under the contract in question. The petitioner claimed a sum of Rs.6,47,00,648.87/- as mark-up on materials, which was not accepted by NHPC. NHPC contended that in terms of the contract between the parties, a mark-up would apply only to material supplied by the contractor and not by NHPC. JAL's claim for markup was finally rejected by NHPC by a letter dated 13.09.1993.
3. In view of the disputes, JAL invoked the Arbitration Clause by a letter dated 28.10.1993. NHPC appointed Justice (Retired) Hari Swarup as the Sole Arbitrator. And, on 03.11.1993, JAL referred its claim to the Arbitral Tribunal.
4. The Arbitral Tribunal delivered the arbitral award on 21.12.1996. JAL filed objections under Sections 30 and 33 of the ARBITRATION ACT , 1940 against the said award before this Court.
5. The said objections were accepted; this Court set aside the aforementioned arbitral award by a judgment dated 11.02.2010 and remanded the matter to the Arbitral Tribunal. NHPC appealed against the said judgment dated 11.02.2010 before the Division Bench of this Court. NHPC's appeal was rejected by an order dated 04.11.2011 and the learned Single Judge's interpretation of Clause 11.8(iii) of the Contract between the parties was upheld.
6. NHPC challenged the judgments passed by this Court (Judgment dated 11.02.2010 passed by the Single Judge and the Judgment dated 04.11.2011 passed by the Division Bench) before the Supreme Court by filing a Special Leave Petition. The said SLP was dismissed by the Supreme Court by an order dated 18.11.2014.
7. In the meantime, the learned Sole Arbitrator (Justice Hari Swarup) had expired. Consequently, on 25.04.2015, NHPC appointed another Arbitrator to fill the vacancy caused by Justice Hari Swarup's demise. And, the arbitral proceedings recommenced. JAL pursued its claim before the Arbitral Tribunal in view of the relevant clauses as interpreted by this Court.
8. The arbitral proceedings culminated in the Arbitral Award dated 19.02.2018 (`the Arbitral Award'). In terms of the Arbitral Award, JAL was awarded a sum of Rs.6,23,39,157/- along with interest at the rate of 14% per annum from the date of reference till realization.
9. Thereafter, NHPC filed an application, inter alia, for rectification of the Arbitral Award as according to NHPC, there was calculation error in computing the quantum of mark-up claimed by JAL. The said application was accepted and the Arbitral Award was rectified to award a sum of Rs.5,90,40,294/- in favour of JAL instead of
Rs.6,23,39,157/-.
10. NHPC filed its objection under Sections 30 and 33 of the ARBITRATION ACT , 1940 against the Arbitral Award as rectified in terms of the order dated 28.03.2018.
11. One of the issues raised before this Court was regarding payment of interest as awarded by the Arbitral Tribunal. NHPC claimed that the interest was not payable in terms of Clause 49.
The court ruled that an unsubstantiated claim for set off cannot affect the enforceability of an arbitral award, and interest on decreed amounts runs from the date the claim arose.
Execution of the works was delayed and the respondent sought Extension of Time for completion of the works on successive occasions, which were approved by NHAI.
NHAI is contractually obliged to pay 90% of the Debt Due to lenders irrespective of defaults by the concessionaire, with no deductions permitted.
Arbitration - Application for setting aside arbitral award – Enforcement of – Amounts awarded in different currencies – Execution of award - it necessary to clarify that the calculations for discharg....
The main legal point established in the judgment is the interpretation and application of Section 34 of the arbitration and Conciliation act, 1996 to an international commercial arbitration, and the ....
Future interest on an arbitral award must be calculated on the total sum directed to be paid, including both principal and interest components. Liability for such interest accrues starting from the d....
Arbitration - Application for setting aside of arbitral Award - Award of interest at rate of 18% per annum from date of award is not in consonance with observations made by Arbitral Tribunal, which r....
The inapplicability of the ground of patent illegality to international commercial arbitration and the importance of interpreting specific contractual clauses in determining the validity of claims an....
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.