IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
Chief Engineer IV, Delhi State Industrial and Infrastructure Devlp. Corp. Ltd. - Appellant
Versus
Well Protect Manpower Services Pv - Respondent
O.M.P. (COMM) 309 of 2021 and & I.A. 13047 of 2021, 13048 of 2021, 13049 of 2021 and 13052 of 2021
Decided On : 30-03-2022
Important Points
Subject
Arbitration - Enforcement of Arbitral Awards
Headnote
(B) Scope of Judicial Review - Scope under Section 34 is limited; interference only if the award is patently illegal or conflicts with public policy. (Paras 30, 34)
Facts of the case:
DSIIDC contracted WPMS for watch and ward services under an agreement. WPMS claims payment for services rendered post-agreement expiry, while DSIIDC contests this. WPMS's service continued without formal extension. DSIIDC and WPMS dispute obligations and payments owed.
Findings of Court:
Tribunal found WPMS performed obligations satisfactorily and DSIIDC failed to contest the claims effectively; awarded interest and reimbursement of performance guarantee.
Issues: Whether WPMS performed according to agreement; entitlement to payments after 08.04.2018; sufficiency of documents submitted; grounds for setting aside the award.
Ratio Decidendi: The Tribunal did not find any misconduct in WPMS's performance and evidence supported its claims; courts should not reconsider arbitrators’ conclusions unless patently illegal.
Result: Petition dismissed; award upheld.
| Table of Content |
|---|
| 1. arbitration initiation and agreement details. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14) |
| 2. summary of claims and defenses in arbitration. (Para 15 , 16 , 17) |
| 3. findings and awards of the arbitral tribunal. (Para 18 , 19 , 20 , 21 , 22) |
| 4. grounds for dsiidc's appeal against the award. (Para 24 , 25) |
| 5. court's evaluation of claims and award validity. (Para 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34) |
| 6. dismissal of the petition. (Para 35) |
JUDGMENT
Vibhu Bakhru, J. The petitioner (hereinafter `DSIIDC') has filed the present petition under section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the `A&C Act') impugning an arbitral award (hereinafter the `impugned award') dated 11.12.2020 delivered by the Arbitral Tribunal consisting of Justice (retd.) Swatanter Kumar as the Sole Arbitrator (hereinafter the `Arbitral Tribunal').
2. The impugned award was rendered in the context of disputes that have arisen between the parties in connection with the Agreement dated 23.11.2016 (hereafter the `Agreement').
Factual Context
3. On 27.06.2016, DSIIDC issued a notice inviting tender for providing watch and ward services for various housing projects completed by it at different locations in Delhi (hereafter the `Services').
4. The respondent (hereinafter `WPMS'), submitted its bid and by a Letter of Acceptance (hereinafter `LOA') dated 19.10.2016, DSIIDC awarded the contract for providing the Services to WPMS.
5. Thereafter, on 20.10.2016, prior to the commencement of the Services, WPMS furnished a performance bank guarantee for 5% of the tendered value, which amounted to a sum of Rs.16,76,830/-.
6. Thereafter, on 23.11.2016, the parties entered into the Agreement. The Agreement was for an initial period of three-hundred and sixty-five days, which commenced from 09.11.2016; that is upto 08.11.2017. The parties agreed that it could be extended further by mutual consent.
7. By a letter dated 02.11.2017, WPMS requested DSIIDC to extend the Agreement. DSIIDC agreed to do so and by a letter dated 04.11.2017 extended the Agreement upto 08.04.2018.
8. WPMS claims that on oral instructions, it continued to provide the Services even after the 08.04.2018. It called upon the concerned officers of DSIIDC to take over the charge of security. However, no alternative arrangement was made and WPMS was requested to continue providing Services. The invoices raised by WPMS remained outstanding. WPMS claims that it continued to provide Services till 1.12.2018 but thereafter, was constrained to lock up the gates and withdraw its security staff.
9. DSIIDC claims that no further extensions were granted and the Agreement stood terminated on 08.04.2018. Notwithstanding the same, a bill dated 15.01.2019 for a sum of Rs.3,32,05,013/- was raised by WPMS for the period of 28.10.2017 to 30.11.2018, which was not accurate. Further, the same was not compliant with the procedures as specified in the Special Conditions of Contract, which were a part of the Agreement. DSIIDC further claims that none of the other two bills dated 30.06.2017 and 06.11.2017 submitted by WPMS were of the right amount or in accordance with the procedure agreed under the Special Conditions of Contract.
10. WPMS, issued a legal notice dated 18.10.2018 calling upon DSIIDC to pay the entire due amount, a sum of approximately Rs.5 crores, along with interest at the rate of 18% per annum from the date the amount became due till its realization. Further, DSIIDC was also asked to issue a formal letter of extension with effect from 18.11.2017 and to pay damages quantified at Rs.10,00,000/-.
11. On 19.03.2019, DSIIDC sent a letter to WPMS whereby, WPMS was called upon to submit the correct bills along with the relevant supporting documents in accordance with the terms and conditions stipulated in the Agreement.
12. In response to the legal notice dated 18.10.2018, DSIIDC sent a letter dated 06.04.2019, alleging that WPMS had blatant