IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
NTPC Vidyut Vyapar Nigam Ltd. - Appellant
Versus
Newton Solar Pvt. Ltd. - Respondent
O.M.P.(COMM.) 271 of 2020 & I.A. 1559 of 2020 and O.M.P. (COMM). 375 of 2020 & I.A. 2369 of 2020
Decided On : 06-07-2022
| Table of Content |
|---|
| 1. parties impugning an arbitral award (Para 1 , 2) |
| 2. disputes regarding delays and damages (Para 3 , 4 , 5) |
| 3. guidelines for solar power project selection (Para 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15) |
| 4. criteria for liquidated damages under the agreement (Para 40 , 61) |
| 5. arguments on interpretation of the agreement (Para 41 , 42) |
| 6. court's interpretation of commissioning date (Para 45 , 46 , 47 , 48) |
| 7. tribunal's decision on compensation claims (Para 63 , 64) |
| 8. conclusion and order disposing of petitions (Para 65 , 66 , 67 , 68) |
JUDGMENT
Vibhu Bakhru, J.
INTRODUCTION
1. The parties have filed the present petitions under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter `the A&C Act') impugning an arbitral award dated 21.10.2019 (hereinafter `the impugned award') delivered by an Arbitral Tribunal comprising of Justice (Retd.) G.N. Ray, Justice (Retd.) Usha Mehra, and Justice (Retd.) G.B. Patnaik as the Presiding Arbitrator (hereinafter `the Arbitral Tribunal').
2. The impugned award was rendered in the context of disputes that have arisen between the parties in connection with a Power Purchase Agreement dated 08.01.2011(hereinafter `the Agreement').
THE CONTROVERSY
3. The controversy in the present petition relates to the question whether there was any delay on the part of Newton Solar Power Private Limited (hereinafter `NSPPL') in complying with its obligations under the Agreement and whether it was liable to pay liquidated damages for the said delay, if any. In addition, NTPC Vidyut Vyapar Nigam Limited (hereinafter `NVVNL') had also claimed compensation for shortfall in supply of solar power, which was disputed by NSPPL.
4. The Arbitral Tribunal found that there was a delay of four days in commissioning the solar project and NSPPL was liable to pay liquidated damages quantified at 20% of the aggregate amount of the performance bank guarantees. The Arbitral Tribunal further found that NSPPL was not liable to pay any compensation for any shortfall in supply of energy.
5. Both the parties are aggrieved by the finding of the Arbitral Tribunal regarding the delay in commissioning of the solar power project and the consequent decision regarding levy of liquidated damages. According to NVVNL, the delay is in excess of one month and NSPPL is liable to pay an additional 40% of the aggregate amount of the Performance Bank Guarantees as liquidated damages. According to NSPPL, there is no delay in commissioning the solar project in question and therefore, it is also aggrieved by the impugned award. In addition, NVVNL is aggrieved by the decision of the Arbitral Tribunal in absolving NSPPL of any liability on account of shortfall in supply of solar power. Thus, both the parties have assailed the impugned award to the extent that they are aggrieved.
FACTUAL CONTEXT
6. In the month of July 2010, the Ministry of New & Renewable Energy, Government of India (hereinafter `MNRE') issued certain guidelines for the selection of new grid connected solar power projects. NVVNL was selected as a nodal agency for arranging and purchasing solar power from Solar Power Developers (hereinafter `SPD' in singular and `SPDs' in plural).
7. On 18.08.2010, NVVNL issued a request for selection (hereafter `RFS'), which was followed by a request for proposal (hereafter `RFP') on 29.10.2010.
8. Pursuant to the said RFP, NSPPL (a SPD) submitted its bid for establishing a solar power project and supplying power. NSPPL's bid was accepted and NVVNL issued a Letter of Intent dated 11.12.2010 (hereinafter `the LoI') accepting NSPPL's proposal to set up the power project at Village Askandra, Tehsil Nachna in District Jaisalmer, Rajasthan.
9. Thereafter, on 08.01.2011, the parties entered into the Agreement. In terms of the Agreement, NSPPL agreed to set up a "Solar Power Project based on Advanced Technology of 5 MW capacity" (hereinafter `the Power Project') and supply power for a period of twenty-five years co
The main legal point established in the judgment is the determination of the date of commissioning of the Power Project and the liability for liquidated damages. The court interpreted the relevant pr....
Point of Law : Arbitration - Application for setting aside of Arbitral Award - Courts would not interfere “unless Court comes to a conclusion that perversity of award goes to root of matter without t....
The court upheld the Arbitral Tribunal's finding that a contractor is not liable for damages unless the claimant proves actual loss, emphasizing limited scope for judicial review of arbitral awards.
The court clarified that in public utility projects, liquidated damages may be claimed without proof of actual loss, reinforcing the importance of agreed contractual terms.
Interpretation of Agreement – Duty of Court is not to delve deep into intricacies of human mind to explore undisclosed intention, but only to take meaning of words used (expressed intentions). In see....
The court upheld the arbitral tribunal's decision that the contract mandated construction power be supplied at 400/440 V, recognizing the claimant's entitlement to additional expenses due to unmet co....
Arbitral tribunals have discretion over fact-finding, and courts should not re-evaluate evidence unless decisions violate public policy or involve patent illegality.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.