SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
NTPC Vidyut Vyapar Nigam Ltd. - Appellant
Versus
Newton Solar Pvt. Ltd. - Respondent
O.M.P.(COMM.) 271 of 2020 & I.A. 1559 of 2020 and O.M.P. (COMM). 375 of 2020 & I.A. 2369 of 2020
Decided On : 06-07-2022




Commissioning of a power project occurs when power is first injected into the grid, influencing liquidated damages as stipulated under the agreement.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Disputes arising from a Power Purchase Agreement - Delay in commissioning of solar project and liquidated damages - Tribunal found four days' delay and imposed 20% liquidated damages; parties aggrieved by findings on delays and shortfall compensation - The tribunal's ruling on the commissioning date as the date power injected into grid is determinative of delays and damages. (Paras 4, 34, 66)

(B) Liquidated damages - The applicability of liquidated damages under Clause 4.6.1 was upheld, with the court affirming the requirement of timely power supply and performance bank guarantees. (Paras 44, 46)

(C) Shortfall in power - Tribunal found NSPPL not solely responsible for supply shortfalls and denied compensation, emphasizing NVVNL's obligations. (Paras 62, 64)

Facts of the case:
Disputes arose between NVVNL and NSPPL regarding the commissioning dates and associated liquidated damages as per their Agreement dated 08.01.2011, with claims from both sides under the Arbitration and Conciliation Act.

Findings of Court:
The tribunal's determination that NSPPL commissioned power on 11.01.2012 was upheld, along with the legality of liquidated damages. NVVNL's claims for additional damages and shortfall compensation were addressed, resulting in mixed outcomes.

Issues: The court addressed whether there was a delay in commissioning and the implications for liquidated damages, as well as accountability for supply shortfalls under the Agreement.

Ratio Decidendi: The court held that the date of commissioning is when power was first injected into the grid, and highlighted the contractual obligations related to delays and compensation.

Result: NVVNL's challenge partially succeeded; tribunal's determination of delay modified.

Table of Content
1. parties impugning an arbitral award (Para 1 , 2)
2. disputes regarding delays and damages (Para 3 , 4 , 5)
3. guidelines for solar power project selection (Para 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15)
4. criteria for liquidated damages under the agreement (Para 40 , 61)
5. arguments on interpretation of the agreement (Para 41 , 42)
6. court's interpretation of commissioning date (Para 45 , 46 , 47 , 48)
7. tribunal's decision on compensation claims (Para 63 , 64)
8. conclusion and order disposing of petitions (Para 65 , 66 , 67 , 68)

JUDGMENT

Vibhu Bakhru, J.

INTRODUCTION

1. The parties have filed the present petitions under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter `the A&C Act') impugning an arbitral award dated 21.10.2019 (hereinafter `the impugned award') delivered by an Arbitral Tribunal comprising of Justice (Retd.) G.N. Ray, Justice (Retd.) Usha Mehra, and Justice (Retd.) G.B. Patnaik as the Presiding Arbitrator (hereinafter `the Arbitral Tribunal').

2. The impugned award was rendered in the context of disputes that have arisen between the parties in connection with a Power Purchase Agreement dated 08.01.2011(hereinafter `the Agreement').

THE CONTROVERSY

3. The controversy in the present petition relates to the question whether there was any delay on the part of Newton Solar Power Private Limited (hereinafter `NSPPL') in complying with its obligations under the Agreement and whether it was liable to pay liquidated damages for the said delay, if any. In addition, NTPC Vidyut Vyapar Nigam Limited (hereinafter `NVVNL') had also claimed compensation for shortfall in supply of solar power, which was disputed by NSPPL.

4. The Arbitral Tribunal found that there was a delay of four days in commissioning the solar project and NSPPL was liable to pay liquidated damages quantified at 20% of the aggregate amount of the performance bank guarantees. The Arbitral Tribunal further found that NSPPL was not liable to pay any compensation for any shortfall in supply of energy.

5. Both the parties are aggrieved by the finding of the Arbitral Tribunal regarding the delay in commissioning of the solar power project and the consequent decision regarding levy of liquidated damages. According to NVVNL, the delay is in excess of one month and NSPPL is liable to pay an additional 40% of the aggregate amount of the Performance Bank Guarantees as liquidated damages. According to NSPPL, there is no delay in commissioning the solar project in question and therefore, it is also aggrieved by the impugned award. In addition, NVVNL is aggrieved by the decision of the Arbitral Tribunal in absolving NSPPL of any liability on account of shortfall in supply of solar power. Thus, both the parties have assailed the impugned award to the extent that they are aggrieved.

FACTUAL CONTEXT

6. In the month of July 2010, the Ministry of New & Renewable Energy, Government of India (hereinafter `MNRE') issued certain guidelines for the selection of new grid connected solar power projects. NVVNL was selected as a nodal agency for arranging and purchasing solar power from Solar Power Developers (hereinafter `SPD' in singular and `SPDs' in plural).

7. On 18.08.2010, NVVNL issued a request for selection (hereafter `RFS'), which was followed by a request for proposal (hereafter `RFP') on 29.10.2010.

8. Pursuant to the said RFP, NSPPL (a SPD) submitted its bid for establishing a solar power project and supplying power. NSPPL's bid was accepted and NVVNL issued a Letter of Intent dated 11.12.2010 (hereinafter `the LoI') accepting NSPPL's proposal to set up the power project at Village Askandra, Tehsil Nachna in District Jaisalmer, Rajasthan.

9. Thereafter, on 08.01.2011, the parties entered into the Agreement. In terms of the Agreement, NSPPL agreed to set up a "Solar Power Project based on Advanced Technology of 5 MW capacity" (hereinafter `the Power Project') and supply power for a period of twenty-five years co

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top