SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Del) 477

IN THE HIGH COURT OF DELHI AT NEW DELHI
Anil Kshetarpal, Harish Vaidyanathan Shankar, JJ.
Pankaj Mittal - Appellant
Versus
Union Of India - Respondent
FAO(OS) 60 of 2019
Decided On : 27-08-2025

Advocates Appeared:
For the Appellant :Mr. Bhupesh Narula, Mr. H.L Narula, Mrs. Rinku Narula, Mr. Anugrah Ekka, Mr. Kanishk Taneja, Advocates
For the Respondent:Ms. Pratima N. Lakra, CGSC with Mr. Shailendra Kumar Mishra and Mr. Chandan Prajapati, Advocates

Judicial intervention under the Arbitration Act is limited to reviewing arbitral awards for irrationality or unreasonableness, affirming the arbitrator's authority to award post-award interest and damages due to breaches without prior notice.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37 - Appeal against Arbitral Award - Jurisdictional limits defined under Section 34 - Interference in arbitral awards is restricted to grounds under Section 34, from which Courts should not deviate unless established as perverse or unreasonable. (Paras 20, 21, 22)

(B) Counter-Claim - Award of interest - The arbitrator may award post-award interest to ensure compliance with the award, irrespective of prior absence of specific demand. (Paras 13, 20)

Facts of the case:
The appellant's claims against an arbitral award regarding penalty for delay and interest on counter-claims were addressed. The arbitral tribunal held that the appellant abandoned the work, leading to legitimate claims against it. The appellant argued for a limit on damages and the necessity of notice prior to claims.

Findings of Court:
The judgment upheld the award, citing that failure to submit performance guarantees as per contractual obligations justified the penalties and claims for damages, which were assessed based on public importance.

Issues: The court examined the relevance of Clause 17B of the General Conditions of Contract for damages awarded and the necessity of issuing notices for claims.

Ratio Decidendi: The court affirmed that the clauses regarding penalties and damages must be viewed in the context of contract abandonment, and that no notice was required for damage claims following a breach.

Result: Appeal dismissed.

Table of Content
1. applicability of arbitration and conciliation act (Para 1 , 2)
2. appellant's contentions against the award (Para 3 , 4 , 5)
3. court's reasoning on damages and contract breaches (Para 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13)
4. limits of judicial intervention in arbitral decisions (Para 19 , 20)
5. dismissal of appeal with no interference (Para 23 , 24)

JUDGMENT :

HARISH VAIDYANATHAN SHANKAR, J.

1. The present Appeal under Section 37 of the Arbitration and Conciliation Act, 1996, [A&C Act] read with Section 10 of the Delhi High Court Act, 1966, has been preferred challenging the Judgment dated 05.12.2018, [Impugned Judgment] passed by the learned Single Judge of this Court in O.M.P. No. 691/2012, which was filed under Section 34 of the A&C Act. The Appellant seeks to set aside the Impugned Judgment as well as the Arbitral Award dated 22.03.2012, [Award] rendered by the learned Arbitrator, in respect of Claim No. 1 and Counter Claim No. 1.

2. At the outset, it needs to be stated that the learned Single Judge has affirmed the Award passed in favour of the Respondent, meaning thereby that this is an Appeal against two concurrent findings in favour of the Respondent.

CONTENTIONS OF THE APPELLANT:

3. Learned counsel for the Appellant would challenge the Award on the following points:

(a). The learned counsel for the Appellant would contend that no interest was claimed in the counter-claim and, while referring to the prayers as sought therein, would urge that the Award of interest, having not been specifically sought for, ought not to have been granted by the learned Arbitrator; and that the learned Single Judge, in exercise of his jurisdiction under Section 34 of the Act, has further exacerbated the position by failing to reverse the same.

(b). He would further contend that the learned Arbitrator has erred in allowing the counter-claim of the Respondent towards penalty. He would contend that in terms of Clause 17B of theGeneral Conditions of Contract, [GCC.], the maximum liquidated damages for a contract of a value of more than Rs. 2 lacs is 10% of the first Rs. 2 lacs and 5% of the balance amount. The Arbitrator, however, has awarded a penalty of 10% on the total contract value, thereby acting in ignorance of the contractual condition.

(c). It is his contention that the learned Arbitrator has awarded a total sum of Rs.5,38,015/- against what was the maximum allowable, which is a sum of Rs.2,39,007/-.

(d). He also states that the learned Arbitrator erred in permitting the earnest money to be forfeited.

(e). He would further contend that the Respondent had not issued any notice before claiming damages from the Appellant.

4. Learned counsel for the Appellant would specifically contend that the letters dated 17.04.2008, 21.09.2008, 23.10.2008 and 17.11.2008 were not considered and reading of these letters would make it evident that the necessary documents had not been provided by the Respondent, resulting in the Appellant being rendered unable to form its part of the Agreement.

CONTENTIONS OF THE RESPONDENT:

5. Per contra, learned counsel for the Respondent submits that the Impugned Judgment as well as the Award suffers from no infirmity. She would further state that both the fora below have concurrently ruled in favour of the Respondent, and having regard to the narrow scope of interference permissible under Section 37 of the A&C Act, no ground for intervention is made out in the present matter.

ANALYSIS:

6. At the outset, we consider it appropriate to extract the relevant portion of the impugned Judgement, which reads as follows:

5. I have considered the submissions made by the counsel for the petitioner, however, I find no merit in the same. As noticed by theArbitrator, upon issuance of the Letter of Acceptance in favour of the petitioner and in terms of paragraph 5.2 (a) and (b) of the Special Tender Conditions and instructions to tenderers, it was the obligation of the petitioner to submit a Performance Guarantee within 15 days of the

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top