SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Del) 1428

IN THE HIGH COURT OF DELHI AT NEW DELHI
Chandra Dhari Singh, J.
Shiga Energy Pvt. Ltd. – Appellant
Versus
GE Power India Ltd. – Respondent
O.M.P. (COMM) 50 of 2021 & I.A. 1863 of 2021
Decided On : 08-05-2023

Advocates appeared:
Appearance not given, for the Petitioner.
Mr. Anish Kapur and Ms. Nikhita K. Suri, Advocates, for the Respondent.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Petition to set aside arbitral award - The petitioner sought to challenge an award regarding the liability of the respondent to reimburse excise duty and central sales tax (CST) on Bought Out Products (BOP) as per previously established contract terms - The arbitrators interpreted the contract to obligate the respondent for all applicable taxes, including those on BOP. (Paras 6 and 47)

(B) Contract Interpretation - Contractual obligation pertains to reimbursement of applicable taxes and does not distinguish between taxes on manufactured goods and those from subcontractors - The court emphasized that the findings of the arbitral tribunal are not to be disturbed unless there is a clear violation of law or public policy. (Paras 34 and 54)

Facts of the case:
The petitioner engaged the respondent for a hydroelectric project, resulting in a dispute over unpaid duties on subcontracted items. The arbitration confirmed the respondent's liability.

Findings of Court:
The court upheld the tribunal's interpretation that all relevant taxes—including on BOP items—were to be reimbursed by the respondent, affirming findings that the amounts involved were based on invoices and evidence presented.

Issues: Whether the respondent is liable to reimburse taxes for BOP items as per the contract.

Ratio Decidendi: The court adhered to the limit of judicial review under Section 34, affirming arbitration awards unless a clear breach of public policy or law is identified.

Result: Petition dismissed; the award is upheld.

Table of Content
1. factual background of the case. (Para 2 , 3 , 4 , 5)
2. petitioner's arguments on contractual obligations. (Para 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17)
3. respondent's counterarguments against petitioner's claims. (Para 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29)
4. court's analysis on scope of interference with arbitral awards. (Para 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40)
5. final analysis regarding the arbitral tribunal's interpretation. (Para 47 , 48 , 49 , 50 , 51)

JUDGMENT

Chandra Dhari Singh, J.

1. The instant petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter "the Act") has been filed on behalf of the petitioner seeking the following reliefs:

    "(i) Set aside the Award dated 14th October, 2020 passed by the Hon'ble Arbitral Tribunal comprising of Justice (Retd.) A. K. Sikri (Presiding Arbitrator), Justice(Retd.) Usha Mehra (Co-Arbitrator) and Mr. Gopal Jain (Co-Arbitrator) in the matter of arbitration GE Power India Ltd and Shiga Energy Pvt. Ltd.

    (ii) Grant a Stay on the operation/execution/enforcement of the impugned arbitral award.

    (iii) Pass such other/further order(s) as this Hon'ble Court may deem fit and proper in the facts and circumstances of the present case."

FACTUAL MATRIX

2. The petitioner, Shiga Energy is a private limited company incorporated under the laws of India, having its Registered Office at 207, Chiranjeev Tower, 43 Nehru Place, New Delhi. The petitioner operates as hydro energy generating company. The company specializes in the generation, distribution, management, construction and transmission of hydro-electric power project. The respondent, GE Power (erstwhile Alstom Projects India Ltd. and thereafter Alstom India Ltd.), is a Limited Company, inter alia, engaged in the business of manufacture and supply of Hydro Turbines, Generator, Electro-Mechanical equipment and parts thereof and has its manufacturing unit situated at ERDA Road, Maneja,Vadodara 13, Gujarat. The respondent regularly bids for various power projects in India as well as outside India for supply of plants, equipment, parts, etc. for such projects.

3. The petitioner is a Special Purpose Vehicle for the implementation of Tashiding Hydro Electric Power Project (THEP) located in West Sikkim. The petitioner, after floating tender and inviting bids from various contractors, in which respondent had also participated and succeeded, awarded the contract to the respondent. Accordingly, the Contract Agreement dated 21st May, 2010 was entered into between the parties whereby respondent was engaged for supply of plants, equipment and mandatory spares from abroad on C.I.F.-Indian Port Entry basis and from Ex-Works (India) basis for Electro-Mechanical Package for Tashiding Hydro Electric Project, Sikkim, India.

4. The contract has been duly executed and there are no disputes in respect thereof. The dispute, however, which has arisen between the parties pertains to the payment on account of Excise Duty and Central Sales Tax (CST). The contract stipulated that all applicable taxes and duties will be paid/reimbursed by the respondent to the claimant at actual.

5. The petitioner, in order to execute the aforesaid contract, had manufactured certain items/components of plants, equipments etc. of its own and some such equipments were got manufactured from third parties/sub-contractors, which the claimant was authorised to do as per the contract. The petitioner had reimbursed the respondent's Excise Duty and CST which had been paid by the respondent on the goods manufactured by it and supplied to the petitioner. However, for the goods which were got manufactured from the third parties, known as Bought Out Products (BOP) i.e., materials, parts and equipments, etc. procured for the project by the claimant from the approved sub-contractors, the petitioner refused to reimburse the Excise Duty and CST on the ground that in terms of the contract, the petitioner was under obligation to reimburse t















Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top