IN THE HIGH COURT OF GAUHATI
Devashis Baruah, J.
Bikash Chandra Pradhani - Appellant
Versus
State Of Assam And Others - Respondents
CRP/47/2020
Decided On : 30-06-2022
Delay Condonation - Civil Procedure - Limitation Act - Sections 115, 151 - The court dismissed the appeal as barred by limitation due to the delay of more than 18 years in filing the appeal. The delay condonation application was based on the grounds of lack of knowledge about the revival of execution proceedings and improper legal advice. The court found the explanations insufficient and dismissed the appeal.
Fact of the Case:
The petitioner filed an application challenging the order of the Civil Judge, Dhubri, which had condoned the delay of more than 18 years in filing an appeal against a judgment and decree dated 29.06.2001. The petitioner's suit sought declaration of land ownership, and the defendants, represented by the State of Assam, filed written statements denying the plaintiff's claim.
Finding of the Court:
The court found that the explanations provided for the delay in filing the appeal were insufficient and dismissed the appeal as barred by limitation.
Issues: The main issue was whether there was sufficient cause for condoning the delay of more than 18 years in filing the appeal.
Ratio Decidendi: The court held that the explanations provided for the delay were insufficient and did not constitute a sufficient cause for condonation. The court emphasized that the law of limitation is founded on public policy and must be applied with rigor. It also noted that the government departments are under a special obligation to ensure diligence and commitment in performing their duties.
Final Decision: The court dismissed the appeal as barred by limitation due to the delay of more than 18 years in filing the appeal.
JUDGMENT :
Devashis Baruah, J.
Heard Mr. D. Kalita, the learned counsel for the Petitioner and Mr. P.S. Deka, the learned Senior Government Advocate appearing on behalf of the State of Assam.
2. This is an application under Section 115 read with Section 151 of the Code of Civil Procedure, 1908 challenging the order dated 30.01.2020 passed by the Court of the Civil Judge, Dhubri, whereby the application being registered as Petition No. 1152 dated 04.09.2019 under Section 5 of the Limitation Act, 1963 was allowed thereby condoning the delay of more than 18 years in connection with Title Appeal No. 32/19.
3. The brief facts of the instant case is that the Petitioner herein as Plaintiff had filed the suit being Title Suit No. 331/1995 in the Court of the Munsiff No. 1, Dhubri seeking declaration that the land described in Schedule-C to the plaint has been wrongly recorded as Khas in Khas Khatian No. 1 and is a part and parcel of Dag No. 844 in Khatian No. 369 in village Dakhin Tokrarchera, Part-IV under P.S. Golakganj in the District of Dhubri; a decree for declaration that the plaintiff has got right, title and interest with a confirmation of possession over the Schedule-C land; a decree for declaration that the record in respect of the land specified in Schedule-C land so prepared by the defendant as khas is wrong and liable to be corrected in the name of the plaintiff under Dag No. 844 of Khatian No. 369 declaring the said to be the part of Schedule-A land; a decree for permanent injunction restraining the defendants from evicting and dispossessing the plaintiff from the Schedule-C land for cost and other reliefs. In the said suit, the defendants were at the State of Assam represented by the Collector Dhubri, and the Assistant Settlement Officer, Golakganj Circle, Golakganj.
4. The said defendants filed their written statement. In the said written statement, it was the specific stand of the defendants was that the plaintiff is an encroacher in the road side Govt. khas land and liable to be evicted. It was also the stand taken that the suit land neither belongs to settle land nor any part of the Khatiandar. The Khatian was continued as ejmali an area of 2 Bighas 12 Lechas in Patta No. 190 in Dag No. 844 in the name of Bhuban Chandra Prodhani.
5. On the basis of the said pleadings, as many as 7 issues were framed. The plaintiff examined 2 witnesses including himself and exhibited some documents. The defendants side however did not adduce any evidence nor exhibited any documents. In deciding the Issue No. 5 which pertains as to whether the plaintiff has right, title and interest and possession over the suit land, the Trial Court opined that the suit land is in continuous possession of the plaintiff and his predecessor in interest and as such the plaintiff has got right, title and interest over the suit land. On the basis of the findings, the Trial Court decreed the suit in favour of the plaintiff declaring the plaintiff's right, title, interest and possession over the Schedule-C land alongwith the decree of correction of records of rights. A permanent injunction was also granted restraining from eviction from the Schedule-C land. The said judgment and decree was passed on 29.06.2001.
6. Thereafter, the record reveals that an execution proceeding was initiated being Title Execution Case No. 35/2001. The Executing Court vide an order dated 18.10.2001 issued precept to the judgment debtors as per the decree. Subsequent thereto, on 20.03.2002, a petition was filed by the judgment debtors stating inter alia that the concerned authority in the meantime have been directed for correction of the records as per the precept issued in the case. It was therefore submitted that the Title Execution Case No. 35/2001 be closed on satisfaction of the decree. To the said Petition, a communication issued by the Additional Deputy Commissioner, Dhubri was enclosed dated 20.03.2002 wherein the Additional Deputy Commissioner had directed the Assistant Settlemen
Abdul Rehman Antulay v. R.S. Nayak
Arjun Singh Vs. Mohindra Kumar
Basawaraj Vs. Land Acquisition Officer
P. Ramachandra Rao v. State of Karnataka
Popat and Kotecha Property v. SBI Staff Assn.
Post Master General Vs. Living Media (India) Ltd.
Pundlik Jalam Patil v. Jalgaon Medium Project
State of Rajasthan Vs. Balkrishna Mathur
AI
The main legal point established in the judgment is that the explanations provided for the delay in filing the appeal were insufficient and did not constitute a sufficient cause for condonation. The ....
The court held that bureaucratic inefficiencies do not constitute sufficient cause for condoning delays in appeals, emphasizing accountability in litigation processes.
Court reiterated the need for sufficient cause in condoning delay, emphasizing that inordinate delays without justifiable reasons will not be entertained.
The main legal point established in the judgment is that the law of limitation has to be applied with rigor, and a satisfactory explanation is required for condonation of delay.
Limitation - Condonation of delay - Law of limitation may harshly affect a particular party but it has to be applied with all its rigour when statute so prescribe and Courts have no power to extend p....
Condonation of delay under the Limitation Act requires substantial justification, and the State is treated no differently than private litigants in these matters.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.