IN THE HIGH COURT OF ALLAHABAD
SAUMITRA DAYAL SINGH, J.
Tata Projects Ltd. – Appellant
Versus
Central Organization for Railway Electrification – Respondent
Arbitration and Conciliation Application U/s 11(4) No. 68 of 2019
Decided On : 02-02-2021
Arbitration and Conciliation Act, 1996 - Section 11 - Prayer to Appoint an Independent Arbitrator - To Adjudicate Disputes - Application filed under Section 11 of Act, 1996 - Application filed with a prayer to appoint an independent arbitrator, to adjudicate the disputes that have arisen between parties under a written contract entered into between applicant and Chief Project Manager, Railway Electrification for the work “Design, Supply, Erection, Testing and Commissioning of 25 KV, AC, 50 Hz, Single Phase, Traction Overhead Equipments, Switching Stations, Booster Transformer Stations, LT Supply Transformer Stations and All Ancillary Equipments Madurai –
Finding of the Court:
Observation made by the Supreme Court in Central Organization for Railway Electrification (supra), in the first place, observation of Supreme Court has been made while deciding the issue whether the General Manager himself being ineligible by operation of law to appoint an arbitrator was eligible to nominate the arbitrator - That issue does not arise in the facts of the present case as in response to notice opposite party did not appoint of any arbitrator and did not offer for appointment any panel of arbitrators to the applicant - In fact, opposite party refused arbitration - Inasmuch as the opposite party failed to appoint an arbitrator, the applicant was within its rights to approach this Court for appointment of an independent arbitrator - That matter is engaging the attention of the Supreme Court - objection raised by Sri. Tripathi is found to be lacking in force. Neither on ground of legality nor of propriety learned proposed arbitrator is inconvenienced –
Result: Application disposed of.
JUDGMENT :
SAUMITRA DAYAL SINGH, J.
1. Heard Sri. Rahul Agarwal, learned counsel for the applicant and Sri. Navneet Chandra Tripathi, learned counsel for the opposite party.
2. Present is an application filed under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act’). The application was filed on 12.07.2019 with a prayer to appoint an independent arbitrator, to adjudicate the disputes that have arisen between the parties under a written contract dated 01.03.2010 entered into between the applicant and the Chief Project Manager, Railway Electrification for the work “Design, Supply, Erection, Testing and Commissioning of 25 KV, AC, 50 Hz, Single Phase, Traction Overhead Equipments, Switching Stations, Booster Transformer Stations, LT Supply Transformer Stations and All Ancillary Equipments Madurai (Excl.)-Tuticorin- Vanchimaniyanchi-Nagercoil (Excl.) of Southern Railway” valued at Rs. 24,97,54,357/- (Rupees Twenty Four Crores Ninety Seven Lakhs Fifty Four Thousand Three Hundred Fifty Seven only).
3. Before approaching this Court, the applicant had issued the statutory notice dated 31.12.2018, invoking arbitration. Referring to Section 12(5) of the Act (as enforced w.e.f. 23.10.2015), the applicant expressed its desire for appointment of an independent arbitral tribunal and for that purpose nominated a retired Judge of this Court. It required the opposite party to nominate an arbitrator of its choice so that the two arbitrators (thus appointed), may nominate a third arbitrator. The three arbitrators together were to constitute the arbitral tribunal.
4. In response to the above notice, on 21.01.2019, the opposite party denied the request for arbitration. It stated, under Clause 1.2.54(b)(i), the arbitration could be sought only after 120 days and before completion of 180 days from the date of presentation of the final bill. Since, the final bill payment was made on 13.06.2016, the request for arbitration first made on 31.12.2018, was outside the said period. Therefore, it was stated to be lacking in locus-standi. Second, it was stated that the ‘No Claim Certificate’ issued by the applicant while obtaining the final payment contained an undertaking to the following effect:
2. It shall be also noted that you have submitted a “No Claim Certificate” under Signature and seal of firm, in which it states “should any claim be raised by us in future under this agreement, the same shall be nullified by virtue of this indenture.”
3. Similarly, your attention is invited to Clause No. 17 of the “Preamble” (Page No. 8 of the tender paper) which states that General Conditions of Contract of concerned Railway as amended for advance correction slips issued up to date shall be part of the contract. The clause no. 63 of latest GCC provides that no such notice of dispute shall be served later than 30 days after the date of issue of completion certificate by the Engineer. The Completion Certificate was issued on 15.03.2015. Hence, it is regretted to inform you that Railway is not in a position to entertain your demand for arbitration at this farthest date as the same is not admissible at this juncture.”
Third, referring to Clause 17 of the Preamble to the agreement and thereby invoking Clause 63 of the General Conditions of Contract (herei
Build India Construction System vs. Union of India
Brahmani River Pellets Ltd. vs. Kamachi Industries Ltd. AIR 2019 SC 3658
Bharat Broadband Network Ltd. vs. United Telecoms Ltd. (2019) 5 SCC 755
2020 Rules which came into force from the date of their publication in the Official Gazette, i.e. 12.02.2020, cannot be given retrospective effect. The intention of Government of India to make the 20....
The court affirmed that the claimant must secure the necessary Airport Entry Permits and upheld the arbitration award, ruling no breach by the respondent; consent regarding the arbitrator's appointme....
The main legal principle established in the judgment is the procedure for appointing arbitrators under the amended Act and the modified Clause 64 of the GCC, emphasizing the ineligibility of certain ....
The appointment of an arbitrator must comply with the Arbitration and Conciliation Act, particularly Section 12(5), which disqualifies certain individuals from serving as arbitrators.
An employee of the respondent or even a retired employee would be ineligible to be appointed as an arbitrator. The panel of arbitrators should be broad-based and should include persons with diverse b....
The court established that the modified provisions of the General and Special Conditions of Contract (GCC) regarding the constitution of the Arbitral Tribunal were applicable in railway contracts, an....
The main legal point established in the judgment is the importance of impartiality and independence of arbitrators, as well as the need for a balanced approach to arbitration, as emphasized by the in....
The court reinforced that impartiality and independence of arbitrators is essential, disqualifying those with vested interests under Section 12(5) of the Arbitration and Conciliation Act, 1996.
Arbitration - Merely because the panel of arbitrators are the retired employees who have worked in the Railways, it does not make them ineligible to act as the arbitrators.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.