2017 Supreme(Raj) 509
IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
VIJAY BISHNOI, J.
Narayan Ram, son of Shri Lichman Ram - Petitioner
Versus
The State of Rajasthan – Respondent
S.B. Civil Writ Petition No. 14641 of 2013, S.B. Civil Writ Petition Nos. 5374, 5376, 5382-5384, 5386-5388, 5980, 5981, 5984, 5995, 5996 of 2015, S.B. Civil Writ Petition Nos.2222-2229, 2312-2314, 2316, 2334-2336, 2758, 2759, 7933, 8008 of 2016
Decided on : 08-09-2017
Advocate Appeared:
For the Petitioners: Mr M.S.Singhvi, Sr. Counsel assisted by Mr Sunil Beniwal, Mr Akhilesh Rajpurohit, Mr Vivek Aggarwal, Mr Anupam Vyas
For the Respondents: Mr P.R.Singh-AAG, Mr Dinesh Ojha, Mr Sanjeet Purohit, Mr Rajat Arora
Headnote:
Land Acquisition Act, 1894 - Section 4 and 5A - Constitution of India,1950 - Article 226 - Extension of industrial area - Impugned notification issue – Claim of compensation - Writ petitions are filed on behalf of petitioners with a prayer for quashing of notification petitioners have also challenged publication of notice of Land Acquisition Act for said land and final award passed - All petitioners are affected persons whose land comes impugned notification - impugned notification was issued It is also not in dispute that for same land notified in impugned notification earlier also a notification of Land Acquisition Act was issued in year however said acquisition proceedings lapsed as same could not be finalized by issuing award within a period of two years from date of issuance of declaration Land Acquisition Act - Held, This Court acquisition proceedings initiated by respondents are vitiated as inquiry conducted by LAO of Land Acquisition Act was farce and mere empty formality and, therefore acquisition proceedings are liable to be quashed - Contention of counsels for respondents that all petitioners have not filed objections of Land Acquisition Act is vehemently opposed by counsel for the petitioners and they have urged that all the petitioners have filed their objections before the LAO - It is noticed that the respondent-State has filed reply only in SBCWP No.14641/2013, whereas the RIICO has filed its reply in all writ petitions however no specific objection is raised by respondents that petitioner/petitioners in those writ petitions have not filed any objections of Land Acquisition Act before LAO - In such contention of counsels for respondents to effect that writ petitions are liable to be dismissed on ground that petitioners had not filed their objections before LAO is bereft of any merit and is liable to be dismissed – Petition disposed of
1. These writ petitions under Article 226 of the Constitution of India are filed on behalf of the petitioners with a prayer for quashing of the notification dated 12.08.2010 issued by the State Government under section 4 of the Land Acquisition Act, 1894 (hereinafter to be referred as ‘the Land Acquisition Act’) for acquisition of 3151 Bighas, 4 Biswas and 12 Biswansi of land of villages Salawas, Boranada and Heerkhera of Tehsil Luni, District Jodhpur for extension of industrial area of Boranada. The petitioners have also challenged the publication of notice under section 6 of the Land Acquisition Act for the said land and the final award passed. All the petitioners are affected persons, whose land comes under the impugned notification.
2. The facts, which are not in dispute, are that the impugned notification was issued on 12.08.2010. Sub- Divisional Officer, Luni was appointed as Land Acquisition Officer (hereinafter to be referred as ‘LAO’). Final notification under section 6 of the Land Acquisition Act was published on 26.09.2011 and the award is passed by the LAO on 24.09.2013.
3. It is also not in dispute that for the same land notified in the impugned notification, earlier also a notification under section 4 of the Land Acquisition Act was issued in the year 2005, however, the said acquisition proceedings lapsed as the same could not be finalized by issuing the award within a period of two years from the date of issuance of the declaration under section 6 of the Land Acquisition Act. The petitioners have challenged the impugned notification and the acquisition proceedings mainly on the following grounds:
(A) Mandatory procedure laid down under section 5A of the Land Acquisition Act has not been followed by the LAO.
(B) Final award issued by the LAO on 24.09.2013 is incomplete.
(C) The land sought to be acquired vide impugned notification falls within periphery control belt as per the master plan of Jodhpur City for the year 2002 to 2023 and, therefore, without making essential changes in the master plan, industrial area cannot be set up. The land sought to be acquired is adjoining to Jodhpur, situated in South-West side and as per the master plan of Jodhpur City, the land sought to be acquired cannot be used for industrial purpose.
(D) The set up of industrial area on the land sought to be acquired is in violation of norms fixed by the Ministry of Urban Development, Government of India with suggestion that industrial area should be located 50 kms. away from the urban limits.
The challenge of the petitioners to the impugned notification and the subsequent acquisition proceedings are countered by the respondent-State and Rajasthan State Industrial Development and Investment Corporation Limited (hereinafter to be referred as ‘RIICO’) by raising the following contentions:
(I) All the writ petitions have been filed after passing of the final award. Hence, they are liable to be dismissed on the ground of delay and laches.
(II) The LAO has decided the objections raised by some of the Khatedars under section 5A of the Land Acquisition Act after following due procedure and after application of mind.
(III) Award dated 24.09.2013 is complete in all respects and cannot be said to be incomplete.
(IV) Even if the land falls within periphery control belt as per the master plan of Jodhpur City, the same can be used for industrial purpose.
4. Learned Senior Counsel Mr M.S.Singhvi assisted by Mr Sunil Beniwal has argued that the acquisition proceedings initiated vide impugned notification are vitiated as the LAO has not followed the procedure laid down under section 5A of the Land Acquisition Act. It is argued that the provisions of section 5A of the Land Acquisition Act are mandatory in nature and non-compliance of the said provisions vitiates the acquisition proceedings. It is further argued that the LAO is duty bound to objectively consider the objections raised by any objector and thereafter can make recommendations by detailing