SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Raj) 1562

IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR
Manindra Mohan Shrivastava, C.J., Ashutosh Kumar, J.
Rajasthan Vidyut Vitran Nigam Limited and ors.- Appellants
Versus
Somi Conveyors Beltings Limited and ors. - Respondents
D.B. Special Appeal Writ No. 493/2024
Decided On : 19-11-2024

Advocates:
Advocate Appeared:
For the Appellant : Mr. Kartik Seth with Mr. Darsh Pareek & Mr. Keshav Parashar
For the Respondent: Mr. Sushil Daga with Mr. Anurag Kalawatia with Mr. Chitransh Mathur & Ms. Parul Singhal, Mr. Sumeer Sodhi for Mr. Punit Singhvi

IMPORTANT POINT
The court ruled that ex-parte interim orders in public procurement should be avoided to prevent disruption of essential services, emphasizing timely decision-making in such matters.

Headnote:

(A) The Electricity Act, 2003 - Section 41 - Interim orders in public procurement - The court emphasized that ex-parte interim orders should not be granted lightly in public projects, as they can disrupt essential services. The appellants argued that timely procurement of conveyor belts is crucial for electricity production. The learned Vacation Judge's order was challenged on grounds of lack of hearing and urgency. (Paras 1, 10, 12)

(B) Judicial Review - Scope - The court reiterated that the scope of judicial review in tender matters is limited and should not interfere with the decision-making process unless there is manifest arbitrariness. (Paras 3, 11)

Facts of the case:

The appeal arose from an ex-parte interim order restraining the appellants from awarding a contract for conveyor belts, essential for thermal power production. The appellants contended that the decision to award the contract was based on fiscal prudence and performance records of the lowest bidder.

Findings of Court:

The court found that the interim order was improperly granted without hearing the appellants and emphasized the need for timely procurement to avoid disruption in electricity supply.

Issues: The main issues included the maintainability of the appeal against the interim order and the appropriateness of the ex-parte order.

Ratio Decidendi: The court ruled that ex-parte interim orders in public procurement cases should be avoided, and applications for vacating such orders must be decided expeditiously.

Result: The appeal was partly allowed, and the interim order was extended for one month pending the final decision on the writ petition.

JUDGMENT :

Manindra Mohan Shrivastava, C.J.

1. This appeal is directed against the interim order dated 25.06.2024 passed by the learned Vacation Judge, by which an ex-parte interim order has been passed in favour of respondent No.1 (writ petitioner) restraining appellants (official respondents in the writ petition) to issue work order to respondent No.2 herein (respondent No.5 in the writ petition) in pursuant to letter of intent dated 10.06.2024 and NIT dated 07.12.2023.

2. Learned counsel for the appellants would submit that the learned Vacation Judge passed an ex-parte interim order even without hearing the appellants and without material facts brought to its notice. The appellants applied for vacating stay by filing an application for vacation of stay on 10.07.2024 on various substantial grounds but the application remained pending despite several prayers made for expeditious disposal. Therefore, the said interim order was challenged by filing an appeal, which was disposed off on 06.08.2024 with a request to the learned Single Judge to hear the application for vacating stay at the earliest preferably within a period of one week. However, the application was not considered despite repeated prayers made. Therefore, the appellant had approached this Court by filing an application seeking restoration of the appeal and consideration of the same on merits and vide order dated 21.09.2024, this prayer was allowed and the appeal stood restored to its original number.

3. On merits, it is submitted that the present is a case pertaining to award of work for supply of conveyor belts, which is extremely essential for transportation of coal to boiler in the thermal plants and failure in the procurement of conveyor belts in time would lead to serious complexities resulting in stoppage of thermal power production and obstruction in supply of electricity in the State. It is argued that the learned Single Judge failed to appreciate that the learned Vacation Judge ought not to have passed the ex-parte interim order without hearing the appellants.

It is next submitted that the appellants proceeded to award contract and issued letter of intent in favour of respondent No.3. He being L-1, the decision to award contract to respondent No.3 as lowest bidder was premised on fiscal prudence after taking into consideration entire aspect of the matter, particularly taking into consideration that during the period of alleged debarment, in fact, respondent No.3 was granted supply orders by the NTPC itself taking into consideration the performance of the lowest bidder/respondent No.3. Therefore, the decision making process did not suffer from any manifest arbitrariness so as to warrant interference. The scope of judicial review in tender matters is extremely limited. The learned Single Judge did not appreciate that only on technical ground made out, procurement ought not to be stayed. He further placed reliance upon various decisions including the decision of Hon’ble Supreme Court in N.G. Projects Ltd. vs. Vinod Kumar Jain & Ors. [2022(6) SCC 127]. It is submitted that Hon’ble Supreme Court has time and again reiterated that in the matters of public projects, injunction should not be lightly granted. He would submit that even after filing an application for vacating stay, his application has not been heard till date and therefore, the appellant, which is a public functionary, was left with no option but to challenge the ex-parte interim order by way of this appeal. He would submit that interim order needs to be urgently vacated as procurement of conveyor belts despite issuance of letter of intent way back in the month of June 2024 has remained stayed. Referring to documents on record, he would submit that various power projects are in dire need of conveyor belts and if it is not supplied to them in time, serious complexity may arise which would adversely affect production of electricity and would be contrary to public interest. He would further submit that the

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top