SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Raj) 1922

IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JAIPUR
SANJEEV PRAKASH SHARMA, CHANDRA PRAKASH SHRIMALI, JJ.
Continental Engineering Corporation Limited - Appellant
Versus
Jaipur Metro Rail Corporation - Respondent
D.B. Special Appeal (Civil) No. 4 of 2022, S.B. Arbitration Application No. 117 of 2018
Decided On : 21-08-2025

Advocates Appeared:
For the Appellants : Anil Kher, Anant Kasliwal, Shashank Kasliwal, Raghav Krishnatri, Diwakar Kholdwa
For the Respondents: Rajendra Prasad, Sandeep Pathak, Harshita Thakral, Dhriti Laddha, Tanay Goyal

A wrong heading on an application does not negate its purpose; the court must consider the contents for adjudication purposes. Delay due to pursuing an incorrect forum may be condoned under applicable legal principles.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Commercial Court Act, 2015 - Section 10(1) - Special Appeal against dismissal of application for setting aside arbitral award - The appellant's application was dismissed on grounds of maintainability and delay. The Single Judge failed to recognize the merits of the application and disregarded the time spent in pursuing the wrong forum, failing to allow for delay condonation under Section 14 of the Limitation Act, establishing that a wrong heading on an application does not defeat the cause of justice. (Paras 19-21)

(B) Delay - The principle of prosecuting with due diligence applies; the time spent by the appellant in seeking resolution in the incorrect forum should be ignored, facilitating a fair hearing on the merits. (Paras 21)

Facts of the case:
The appellant, a company, sought to challenge an arbitral award through an application dismissed by the Single Judge. The initial application was filed improperly. The Commercial Court had declared it was outside its jurisdiction, resulting in procedural complications.

Findings of Court:
The court noted that the Single Judge erroneously held that no application under Section 34 was filed and should have considered the merits. The appeal is allowed, and the matter is remanded for evaluation of the application on its merits.

Issues: The main issues included whether an application under Section 34 was filed and if the delay could be condoned.

Ratio Decidendi: The court stated that a wrong heading on the application does not defeat justice and emphasized the need to consider the contents of the application, thus allowing the appeal for appropriate remedy.

Result: Appeal allowed; order set aside and remanded for consideration on merits.

Table of Content
1. background of arbitration proceedings and initial court involvement. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7)
2. arguments regarding maintainability and procedural delays. (Para 9 , 10 , 11 , 12 , 13 , 14)
3. legal provisions governing arbitration and appeals. (Para 15 , 16 , 17)
4. court's analysis of the application under section 34 and delay considerations. (Para 18 , 19 , 20 , 21)
5. final judgment remanding the case back for merits determination. (Para 22 , 23 , 24 , 25)

JUDGMENT :

SANJEEV PRAKASH SHARMA, J.

1. By way of this Special Appeal (Civil), preferred under Section 37 (1)(c) of the Arbitration and Conciliation Act, 1996 (for brevity, "the Act of 1996”) read with Section 13(1A) of the Commercial Court Act, 2015, (for short "the Act of 2015"), the appellant has challenged the order passed by the learned Single Judge dated 02.03.2022 whereby S.B. Arbitration Application No.117/2018 preferred by it under Section 34 of the Act of 1996 read with Section 10(1) of the Act of 2015 was dismissed by holding that there is no application under Section 34 of the Act of 1996 before him and the application moved under Section 10(1) of the Act of 2015 was not maintainable.

I. Factual Aspects:

2. The appellant is a company incorporated under the laws of Taiwan engaged in the business of civil construction, building construction and related works in various countries including India. On arising of a dispute between the appellant and the respondent Jaipur Metro Rail Corporation (for short, "JMRC"), arbitration proceedings were taken up by the Arbitral Tribunal comprising of Hon’ble Mr. Justice Vikramajit Sen (Retd.), Hon’ble Mr. Justice Mukul Mudgal (Retd.) and Mr. Pradeep K. Deb, IAS (Retd.). The Arbitral Tribunal by 2:1 majority turned down the claim of the appellant vide its Award dated 20.12.2017.

3. The appellant challenged the Award vide their petition under Section 34 of the Act of 1996 on 16.03.2018 before the Rajasthan State Commercial Court (District Level), Jaipur (hereinafter referred to as “the Commercial Court”). The respondent entered appearance and raised a preliminary objection by filing an application, primarily on the ground of jurisdiction of the Commercial Court as the dispute was covered under the international commercial arbitration. The Commercial Court, after hearing arguments of both the sides, vide order dated 22.11.2018 proceeded to hold that as per Section 10(1) of the Act of 2015, the application or appeal would lie before the High Court where there is an international commercial dispute and therefore, the petition filed by the appellant was returned to be filed before the competent court of jurisdiction in terms of Order 7 Rule 10 CPC.

4. Having received the application under Section 34 of the Act of 1996 filed in original on 06.12.2018, the appellant filed it before the Registry of this court on 06.12.2018 itself. However, the Registry refused to accept the petition in its existing form stating that the petition under Section 34 of the Act of 1996 cannot be directly filed. The appellant thereafter filed the application under Section 10(1) of the Act of 2015 in order to remove the defects pointed out by the Registry. The said application was listed before the Division Bench of this court and the petition was registered under Section 34 of the Act of 1996, numbered as D.B. Arbitration Application No.117/2018.

5. Again the respondent raised a preliminary issue regarding maintainability of the petition under Section 34 of the Act of 1996 in the given form with following objections:

“a) No application under Section 34 of the Act has been filed before the High Court;

b) Order passed by Commercial Court is incorrect as the application of Appellant under Section 34 should have been rejected and not transferred under Order 7 Rule 10 of CPC.

c) Under sub-clause (a) of Rule 4 of the Rajasthan Arbitration Rules, 2003 a signed application has to be filed, verification of which is mandatory. The Respondent alleged t

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top