IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. Anand Venkatesh, J.
M/s.Muthu Construction – Salem - Petitioner
Versus
Union of India, rep.by its Principal Chief Engineer - Respondent
Arbitration O.P.(Com.Div.) No.603 of 2022
Decided On : 20-01-2026
Certainly. Based on the provided legal document, here are the key points:
The case involves a challenge to an arbitral award on the grounds of bias among arbitrators and alleged patent illegality in interpretation of contractual terms (!) (!) .
The petitioner contended that bias within the arbitral tribunal compromised its impartiality, violating principles of natural justice and statutory provisions, warranting the setting aside of the award (!) (!) (!) .
The arbitral tribunal's interpretation of the measurement unit "per track metre" was found to be unreasonable, deviating from the clear contractual terms, and thus suffering from patent illegality (!) (!) (!) .
The tribunal replaced explicit contractual language with an alleged mutual understanding, which was deemed a patent illegality because it disregarded the unambiguous contractual provisions (!) (!) .
The award was also challenged due to the involvement of arbitrators who participated in other related proceedings, raising concerns about bias and premeditation, especially since two members of the tribunal had served in similar cases concurrently (!) (!) .
The court emphasized that bias of even a single arbitrator taints the entire award, especially when bias is alleged and supported by evidence of preconceived notions or lack of impartial discussion (!) (!) (!) (!) .
The principles of natural justice, including the requirement for impartiality and the prohibition against bias, are fundamental and their violation justifies setting aside arbitral awards (!) (!) (!) .
The court found that the involvement of arbitrators with a predisposition or bias, particularly those who had acted in other related cases, compromised the integrity of the tribunal and rendered the award liable to be annulled (!) (!) .
Ultimately, the court held that the award was tainted by bias and premeditation, violating statutory provisions and principles of natural justice, leading to its annulment (!) (!) .
The court ordered the award to be set aside and awarded costs to the petitioner, reinforcing the importance of impartiality and adherence to contractual and legal principles in arbitration proceedings (!) .
Please let me know if you need further analysis or assistance.
ORDER :
N. Anand Venkatesh, J.
In this petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short, the Act), the petitioner assails the award dated 22.1.2022 passed by the Arbitral Tribunal.
2. Heard both.
3. The facts leading to filing of this case are as follows:
(i) The petitioner is a proprietary concern, which entered into a contract with the respondent titled as repairs to the existing dily changing corroded fittings over points and crossings/SEJs/bridges/ curves, boxing and tidying of ballast, painting of boards, etc. Two contracts were entered into namely SA/279 and SA/280. This case pertains to SA/279.
(ii) The petitioner participated in the tender that was floated by the respondent and was declared as the successful bidder, pursuant to which, they were awarded the contract. The letter of acceptance 28.11.2018 for a value of Rs.1,55,15,697/- was also issued.
(iii) The claims made by the petitioner before the Arbitral Tribunal pertained to earnest money deposit, security deposit, final bill amount and payment for the difference as per the unit of measurement of “track metre”. It was an admitted case that the only issue, which became the subject matter of adjudication before the Arbitral Tribunal, was with regard to the last component namely payment for the difference as per the unit of measurement of “track metre”
(iv) Ultimately, the Arbitral Tribunal came to the conclusion that the claim made by the petitioner under this head was found to be untenable and hence, it came to be rejected. Aggrieved by that, the above petition has been filed before this Court.
4. The learned counsel for the petitioner questioned the award mainly on two grounds and they are:
(a) that it is vitiated by bias, that it violates Section 18 of the Act and the principles of natural justice and that therefore, it is liable to be interfered under Section 34(2)(i)(b) of the Act; and
(b) that the interpretation given by the Arbitral Tribunal to deny the claim made by the petitioner suffers from patent illegality and hence, it is liable to be interfered under Section 34(2A) of the Act.
5. Per contra, the learned Senior Central Government Standing Counsel appearing for the respondent submitted that the dissenting note of one of the Arbitrators rendered in the other award in respect of the same parties cannot automatically result in attributing bias as against the unanimous award passed by the Arbitral Tribunal, that the Arbitral Tribunal has rightly interpreted the relevant clause in the agreement, that it is a possible view taken by the Arbitral Tribunal and that it cannot be interfered by this Court while exercising its jurisdiction under Section 34 of the Act.
6. This Court has carefully considered the submissions of the learned counsel on either side and perused the materials available on record and more particularly the impugned award.
7. This Court will first deal with the second issue raised with respect to the interpretation of the expression “per track metre” and test as to whether the view taken by the Arbitral Tribunal is a possible view.
8. The sum and substance of the contention raised on the side of the petitioner is that Schedule B in the agreement consisted of six categories of works, which used the expression “per track metre” as the unit of measurement. Except with respect to item Nos.1 and 2, for all the other items, the measurements were taken separately for each track whereas in so far as item Nos.1 and 2 were concerned, they were treated differently and the measurements were recorded by clubbing two tracks (up and down) and it has been questioned by the petitioner on the ground that these two items could not be treated/ measured differently especially when the unit of measurement was one and the same.
9. For proper appreciation, item Nos.1 and 2 in Schedule B are extracted as hereunder:
| S.No | Description of Work | Quantity | Unit | Rate | Amount |
| 1 | Boxing and tidying of ballast duly cleaning and uprooting bushes all vegetation availa | ||||
State of Chhattisgarh Vs. SAL Udyog (P) Ltd.
Delhi Airport Metro Express (P) Ltd. Vs. Delhi Metro Rail Corporation Ltd.
Central Organization for Railway Electrification Vs. ECI SPIC SMO MCML (JV)
Bias among arbitrators undermines impartiality and can lead to annulment of the award under arbitration law.
The court ruled that arbitrators must adhere to contractual terms, and any deviation without justification constitutes patent illegality warranting interference.
The court confirmed the validity of the Arbitrator's findings regarding excess work claims and the correct application of interest, highlighting that overlapping interest claims were erroneous.
The court affirmed that limited judicial review under Section 34 of the Arbitration Act does not allow for re-evaluation of arbitration awards unless they are demonstrably perverse, illegal, or devoi....
Arbitral awards may be composite if the issues relate closely, but interest must adhere to contractual terms.
The timely objections to an arbitrator's impartiality are essential; delays in raising such objections or challenges on grounds of bias and limitation render subsequent claims unenforceable under the....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.