IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. Anand Venkatesh, J.
M/s.Muthu Construction – Salem - Petitioner
Versus
Union of India, rep.by its Principal Chief Engineer, Southern Railway - Respondent
Arbitration O.P.(Com.Div.) No.602 of 2022
Decided On : 20-01-2026
| Table of Content |
|---|
| 1. contractual terms and claims overview. (Para 3) |
| 2. counsel's arguments on bias and legal interpretation. (Para 4 , 5) |
| 3. analysis of arbitral interpretation and clarity. (Para 6 , 7 , 10 , 11 , 14 , 15) |
| 4. patently illegal grounds for challenge. (Para 12 , 13 , 19) |
| 5. conclusion on bias and annulment of award. (Para 20 , 21 , 22) |
ORDER :
N. Anand Venkatesh, J.
In this petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short, the Act), the petitioner assails the majority award dated 25.2.2022 passed by the Arbitral Tribunal.
2. Heard both.
3. The facts leading to filing of this case are as follows:
(i) The petitioner is a proprietary concern, which entered into a contract with the respondent titled as repairs to the existing dily changing corroded fittings over points and crossings/SEJs/bridges/ curves, boxing and tidying of ballast, painting of boards, etc. Two contracts were entered into namely SA/279 and SA/280. This case pertains to SA/280.
(ii) The petitioner participated in the tender that was floated by the respondent and was declared as the successful bidder, pursuant to which, they were awarded the contract. The letter of acceptance 27.11.2018 for a value of Rs.2,76,83,452/- was also issued to them.
(iii) The claims made by the petitioner before the Arbitral Tribunal pertained to earnest money deposit, security deposit, final bill amount and payment for the difference as per the unit of measurement of “track metre”. It was an admitted case that the only issue, which became the subject matter of adjudication before the Arbitral Tribunal, was with regard to the last component namely payment for the difference as per the unit of measurement of “track metre”
(iv) Ultimately, the majority of the Arbitral Tribunal came to the conclusion that the claim made by the petitioner under this head was found to be untenable and hence, it came to be rejected. Aggrieved by the majority award, the above petition has been filed before this Court.
4. The learned counsel for the petitioner questioned the majority award mainly on two grounds and they are:
(a) that it is vitiated by bias, that it violates Section 18 of the Act and the principles of natural justice and that therefore, it is liable to be interfered under Section 34(2)(i)(b) of the Act; and
(b) that the interpretation given by the majority of the Arbitral Tribunal to deny the claim made by the petitioner suffers from patent illegality and hence, it is liable to be interfered under Section 34(2A) of the Act.
5. Per contra, the learned Senior Central Government Standing Counsel appearing for the respondent submitted that the dissenting note of one of the Arbitrators cannot automatically result in attributing bias as against the remaining members of the Arbitral Tribunal, that the majority of the Arbitral Tribunal has rightly interpreted the relevant clause in the agreement, that it is a possible view taken by the Arbitral Tribunal and that it cannot be interfered by this Court while exercising its jurisdiction under Section 34 of the Act.
6. This Court has carefully considered the submissions of the learned counsel on either side and perused the materials available on record and more particularly the impugned award.
7. This Court will first deal with the second issue raised with respect to the interpretation of the expression “per track metre” and test as to whether the view taken by the majority of the Arbitral Tribunal is a possible view.
8. The sum and substance of the contention raised on the side of the petitioner is that Schedule B in the agreement consisted of six categories of works, which used the expression “per track metre” as the unit of measurement. Except with respect to item Nos.1 and 2, for all the other items, the measurements were taken separately for each track whereas in so far as item Nos.1 and 2 were concerned, they were treated differently and the measurements were recorded by clubbing two tracks (up and down) and it has been
State of Chhattisgarh Vs. SAL Udyog (P) Ltd.
Delhi Airport Metro Express (P) Ltd. Vs. Delhi Metro Rail Corporation Ltd.
Central Organization for Railway Electrification Vs. ECI SPIC SMO MCML (JV)
The court ruled that arbitrators must adhere to contractual terms, and any deviation without justification constitutes patent illegality warranting interference.
Bias among arbitrators undermines impartiality and can lead to annulment of the award under arbitration law.
The court confirmed the validity of the Arbitrator's findings regarding excess work claims and the correct application of interest, highlighting that overlapping interest claims were erroneous.
The court affirmed the limited scope of review under Section 34 of the Arbitration and Conciliation Act, emphasizing respect for arbitral awards unless stark violations of public policy or procedural....
The court affirmed that limited judicial review under Section 34 of the Arbitration Act does not allow for re-evaluation of arbitration awards unless they are demonstrably perverse, illegal, or devoi....
Arbitration - If the Arbitrator so appointed resigns his appointment or vacates his office or is unable or unwilling to act due to any reason whatsoever, the authority appointing him may appoint a ne....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.