SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Mad) 573

IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. Anand Venkatesh, J.
M/s.Muthu Construction – Salem - Petitioner
Versus
Union of India, rep.by its Principal Chief Engineer, Southern Railway - Respondent
Arbitration O.P.(Com.Div.) No.602 of 2022
Decided On : 20-01-2026

Advocates Appeared:
For the Petitioner: Mr. Sharath Chandran
For the Respondent: Mrs. V.J. Latha, SCGSC

The court ruled that arbitrators must adhere to contractual terms, and any deviation without justification constitutes patent illegality warranting interference.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to majority arbitral award - Petitioner assailed award related to unit measurement - Grounds included bias, violation of natural justice, and patent illegality. (Paras 1-3, 4-6, 18-20)

(B) Legal Principles - A tribunal's construction of contractual terms should respect the clear language of the contract; deviations without justification constitute patent illegality. (Paras 10-14)

(C) Bias - Allegations of bias and predetermined conclusions among arbitrators necessitate scrutiny under principles of natural justice. (Paras 16-20)

Facts of the case:
The petitioner challenged a majority award on grounds of bias and improper interpretation of contract terms regarding measurement of work, which was contested per the agreement.

Findings of Court:
The majority award was found to be tainted by bias and hence set aside.

Issues: The court addressed whether the majority arbitrators showed bias and if their interpretation of contract terms was legally sound.

Ratio Decidendi: The majority's construction of contract terms was flawed, leading to findings that lacked evidential support and violated principles of natural justice, warranting judicial intervention.

Result: The majority award is set aside and the original petition is allowed with costs.

Table of Content
1. contractual terms and claims overview. (Para 3)
2. counsel's arguments on bias and legal interpretation. (Para 4 , 5)
3. analysis of arbitral interpretation and clarity. (Para 6 , 7 , 10 , 11 , 14 , 15)
4. patently illegal grounds for challenge. (Para 12 , 13 , 19)
5. conclusion on bias and annulment of award. (Para 20 , 21 , 22)

ORDER :

N. Anand Venkatesh, J.

In this petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short, the Act), the petitioner assails the majority award dated 25.2.2022 passed by the Arbitral Tribunal.

2. Heard both.

3. The facts leading to filing of this case are as follows:

(i) The petitioner is a proprietary concern, which entered into a contract with the respondent titled as repairs to the existing dily changing corroded fittings over points and crossings/SEJs/bridges/ curves, boxing and tidying of ballast, painting of boards, etc. Two contracts were entered into namely SA/279 and SA/280. This case pertains to SA/280.

(ii) The petitioner participated in the tender that was floated by the respondent and was declared as the successful bidder, pursuant to which, they were awarded the contract. The letter of acceptance 27.11.2018 for a value of Rs.2,76,83,452/- was also issued to them.

(iii) The claims made by the petitioner before the Arbitral Tribunal pertained to earnest money deposit, security deposit, final bill amount and payment for the difference as per the unit of measurement of “track metre”. It was an admitted case that the only issue, which became the subject matter of adjudication before the Arbitral Tribunal, was with regard to the last component namely payment for the difference as per the unit of measurement of “track metre”

(iv) Ultimately, the majority of the Arbitral Tribunal came to the conclusion that the claim made by the petitioner under this head was found to be untenable and hence, it came to be rejected. Aggrieved by the majority award, the above petition has been filed before this Court.

4. The learned counsel for the petitioner questioned the majority award mainly on two grounds and they are:

(a) that it is vitiated by bias, that it violates Section 18 of the Act and the principles of natural justice and that therefore, it is liable to be interfered under Section 34(2)(i)(b) of the Act; and

(b) that the interpretation given by the majority of the Arbitral Tribunal to deny the claim made by the petitioner suffers from patent illegality and hence, it is liable to be interfered under Section 34(2A) of the Act.

5. Per contra, the learned Senior Central Government Standing Counsel appearing for the respondent submitted that the dissenting note of one of the Arbitrators cannot automatically result in attributing bias as against the remaining members of the Arbitral Tribunal, that the majority of the Arbitral Tribunal has rightly interpreted the relevant clause in the agreement, that it is a possible view taken by the Arbitral Tribunal and that it cannot be interfered by this Court while exercising its jurisdiction under Section 34 of the Act.

6. This Court has carefully considered the submissions of the learned counsel on either side and perused the materials available on record and more particularly the impugned award.

7. This Court will first deal with the second issue raised with respect to the interpretation of the expression “per track metre” and test as to whether the view taken by the majority of the Arbitral Tribunal is a possible view.

8. The sum and substance of the contention raised on the side of the petitioner is that Schedule B in the agreement consisted of six categories of works, which used the expression “per track metre” as the unit of measurement. Except with respect to item Nos.1 and 2, for all the other items, the measurements were taken separately for each track whereas in so far as item Nos.1 and 2 were concerned, they were treated differently and the measurements were recorded by clubbing two tracks (up and down) and it has been

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top