SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(All) 1063

IN THE HIGH COURT OF ALLAHABAD
HON'BLE ARUN BHANSALI, CHIEF JUSTICE, HON'BLE JASPREET SINGH, J.
M/S Shyam Lalit Dubey And Another - Appellants
Versus
Union of India, Thru. General Manager Northern Railway Baroda House, New Delhi And Another - Respondents
Appeal Under Section 37 of Arbitration and Conciliation Act 1996 No. 66 of 2023
Decided On : 15-07-2024

Advocates Appeared:
For the Appellant : Pritish Kumar, Shantanu Gupta.
For the Respondent: Deepanshu Dass, Varun Pandey.

IMPORTANT POINT
The court established that an arbitral award can only be set aside in part if some claims are valid and arbitrable, and that claims arising from work not included in the original contract are not subject to arbitration under the Arbitration and Conciliation Act, 1996.

Headnote:

ARBITRATION - Arbitration and Conciliation Act, 1996; Contract Act, 1872 - Sections 34, 31(7), 70 - The court discussed the provisions of the Arbitration and Conciliation Act, 1996, particularly Section 34 regarding the setting aside of arbitral awards, and Section 31(7) concerning interest on awards. It interpreted that the entire award could not be set aside if part of it was valid, as per the proviso to Section 34(2)(a)(iv). The court also examined Section 70 of the Contract Act, 1872, which addresses compensation for non-gratuitous acts, concluding that the claim for epoxy grouting was not arbitrable as it was not part of the original contract. This legal framework influenced the decision to partially uphold the arbitral award while setting aside the portion related to epoxy grouting and interest.

Fact of the Case:

The appellants submitted a tender for rebuilding a bridge, which was accepted, and a contract was formed. The appellants claimed that the work could not proceed due to the respondents' failure to provide necessary drawings. They performed additional work (epoxy grouting) on other bridges at the request of the respondents but were not compensated. An arbitration was initiated, resulting in an award in favor of the appellants, which was later set aside by the Commercial Court under Section 34 of the Arbitration and Conciliation Act, 1996.

Finding of the Court:

The Commercial Court found that the award regarding mobilization of resources was justified, but the claim for epoxy grouting was not arbitrable. It ruled that the award suffered from patent illegality and set it aside in its entirety, which the appellants contested.

Issues: 1. Whether the entire arbitral award could be set aside when part of it was justified. 2. Whether the claim for epoxy grouting was arbitrable under the contract. 3. Whether the award of interest was justified under Section 31(7) of the Act, 1996.

Ratio Decidendi: The court held that under Section 34(2)(a)(iv) of the Arbitration and Conciliation Act, 1996, only the parts of the award that dealt with non-arbitrable disputes could be set aside. The claim for epoxy grouting was found to be outside the scope of the arbitration clause, thus not arbitrable. The court emphasized that the principle of quantum meruit under Section 70 of the Contract Act, 1872, does not automatically render a non-contractual claim arbitrable.

Final Decision: The appeal was partly allowed. The judgment of the Commercial Court was set aside to the extent that it invalidated the award related to mobilization of resources, while the claims for epoxy grouting and interest were upheld as non-arbitrable and thus set aside.

JUDGMENT :

Arun Bhansali, C.J.

1. This appeal is directed against the judgement dated 28.06.2023 passed by the Commercial Court, Lucknow whereby the petition filed by the respondents under Section 34 of the Arbitration and Conciliation Act, 1996 (for short the ‘Act, 1996’) has been allowed and the arbitral award dated 6.11.2020 has been set aside.

2. Tender offer of the appellants for the work of rebuilding of Bridge No. 70 at Km 34/13-14 between Lalgopalganj (LGO) and Bhadri (BHDR) Station on ARC Section under ADEM/PRG of Lucknow Divison was submitted in pursuance of the tender notice dated 21.12.2016, which was accepted by the competent authority at the offered rates. The total cost of assigned work was Rs.2,50,86,758.87P.

3. Pursuant to the said acceptance, Letter of Acceptance (LoA) dated 01.05.2017 was issued. Pursuant to the terms of the contract, earnest money deposited by the appellants with the tender documents was retained and balance security deposit was to be recovered from the progressive bills @ 10% till full security amount was recovered. A performance guarantee of Rs.12,54,340/- was required to be submitted, which was submitted in the shape of FDRs by the appellants. A formal agreement was entered into between the parties to which the general conditions of Railways contract (‘GCC’) were applicable. Under the agreement, the appellants were required to complete the work within eight months from the date of issue of LoA i.e. by 31.12.2017 in conformity with the approved drawing.

4. It was claimed by the appellants that it arranged the entire paraphernalia and infrastructure including labour, staff, tools and materials at the site to execute the awarded contract. However, the contract could not be carried out between the period 01.05.2017 to 31.12.2017 in terms of the agreement as the respondents failed to provide approved drawing to construct the bridge, though it was provided that the same would be supplied at the time of execution of the agreement. The contract period was extended without penalty from 01.01.2018 to 31.07.2018. However, even during the extended period the approved drawing was not supplied.

5. It is claimed that in June, 2018, the appellants were directed by the Senior Divisional Engineer-IV to perform epoxy grouting work on Bridges No. 4, 6, 8, 12, 110, 115, 119, 96, 151, 148, 146, 146A, 147, 144, 140, 120, 116, 105A, 105, 117, 104A, 104, 127, 123, 109 & 131A. It is further claimed that though the said work was not provided in the contract, keeping in view the long standing association of the appellants with the Railways and emergent and urgent nature of the work, the same was performed whereby the appellants expended about Rs.65 Lakhs. The said epoxy grouting work was approved and verified by the competent Railway Authorities. However, the payment was not made.

6. Since the approved drawing was not provided to the appellants within time to complete the work awarded to them under the contract and on account of non payment of their dues for epoxy grouting, the respondents were requested to appoint an Arbitrator under clause 64 of the GCC. However, when the Arbitrator was not appointed, the appellants approached the High Court, which appointed a sole Arbitrator by its order dated 06.01.2020.

7. The Arbitrator passed the arbitral award dated 06.11.2020 and awarded the following amounts along with 12% pendente lite interest :

A.

Amount under earnest money

Rs.2,72,500.00

B.

Amount under the performance guarantee

Rs.12,54,340.00

C.

Amount of epoxy grouting work

Rs.61,24,732.79

D.

Amounts under mobilization of resources

Rs.34,13,437.50

E.

Amount under 10% loss of profit

Rs.25,08,675.89

F.

Fee and Expenses (Rs.360937.50 + 172000.00)

Rs.5,32,937.50

 

Total

Rs.1,41,06,623.68

8. Feeling aggrieved, the petition under Section 34 of the Act, 1996 was filed by the respondents.

9. After hearing the partie

              Click Here to Read the rest of this document
              1
              2
              3
              4
              5
              6
              7
              8
              9
              10
              11
              SupremeToday Portrait Ad
              supreme today icon
              logo-black

              An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

              Please visit our Training & Support
              Center or Contact Us for assistance

              qr

              Scan Me!

              India’s Legal research and Law Firm App, Download now!

              For Daily Legal Updates, Join us on :

              whatsapp-icon Back to top