IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
UJJAL BHUYAN, C.V.BHASKAR REDDY, JJ.
M/s. S.R.Technologies (Unit-II) – Appellant
Versus
Micro and Small Enterprises Facilitation Council – Respondent
Writ Appeal No.734 of 2022
Decided on : 21-03-2023
Constitution of India,1950 - Article 226 - Micro Small and Medium Enterprises Development Act, 2006 - Section 18(1) - Letters Patent - Clause 15 - Small scale industrial unit - Amounts claimed - Registration certificate - Appellant before us is M/s. S.R. Technologies (Unit-II) (referred to hereinafter as, “claimant”, “supplier” or “appellant” as the case may be). Claimant is a small scale industrial unit bearing registration certificate dated issued by District Industries Centre, Ranga Reddy, under the small manufacturing enterprises category - Claimant made a reference under Section 18(1) of Micro Small and Medium Enterprises Development Act, 2006 to Facilitation Council for acting as Conciliator and Arbitrator in respect of amount claimed against M/s. India Glycols Limited (respondent No.2 herein) - Amounts claimed by the claimant against respondent No.2 - Reference was registered and admitted by Facilitation Council - According to claimant, respondent No.2 had raised purchase order dated for supply of HVAC, doors, windows, false ceiling etc., including installation and commissioning at M/s. IGL site for their NHPS Dehradun Project for an amount - Whether arbitration proceedings were preceded by conciliation is a jurisdictional issue - Whether he had perused record which led to passing of the award dated 20.02.2016 which had clearly mentioned that there was conciliation but it had ended in failure - Before the Facilitation Council both claimant and respondent No.2 were present. However, process of conciliation failed. Therefore, Facilitation Council took up the case for arbitration. (Para 4.4)
Finding of Court :
Learned Single Judge also held that there was no consideration of the counter claim of respondent No.2 by the Facilitation Council while passing award though directed by this Court vide order dated 16.06.2016 passed in W.P.No.15230 of 2016 - On this ground also award was faulted. Learned Single Judge failed to note that aspect was considered and decided by Facilitation Council under issue No.3 by holding that Facilitation Council has the mandate only to decide a matter referred to it under Section 17 of MSME Act which does not include a counter claim of the buyer - Thus for aforesaid reasons, Court are of the unhesitant view that learned Single Judge fell in error in not only entertaining the writ petition but also in allowing same by setting aside award dated 28.10.2021 passed by Facilitation Council.
Result: Writ appeal is accordingly allowed.
JUDGMENT :
Ujjal Bhuyan, J.
Heard Mr. Suresh Dhole, learned counsel representing Mr. Gollakota Satya Jagannath, learned counsel for the appellant and Mr. C.V.Mohan Reddy, learned Senior Counsel for respondents No.2 and 3.
2. This intra-court appeal under Clause 15 of the Letters Patent has been filed against the judgment and order dated 14.09.2022 passed by the learned Single Judge allowing W.P.No.16918 of 2022 filed by respondents No.2 and 3 as the writ petitioners.
3. It may be mentioned that respondents No.2 and 3 had filed the related writ petition assailing the legality and validity of the award dated 28.10.2021 passed by the Micro and Small Enterprises Facilitation Council (briefly, “the Facilitation Council” hereinafter). By the judgment and order dated 14.09.2022, learned Single Judge set aside the award dated 28.10.2021 by invoking jurisdiction under Article 226 of the Constitution of India.
4. Appellant before us is M/s. S.R. Technologies (Unit-II) (referred to hereinafter as, “claimant”, “supplier” or “appellant” as the case may be). Claimant is a small scale industrial unit bearing registration certificate dated 19.01.2007 issued by the District Industries Centre, Ranga Reddy, under the small manufacturing enterprises category. Claimant made a reference on 28.10.2015 under Section 18(1) of the Micro Small and Medium Enterprises Development Act, 2006 (briefly, “the MSME Act” hereinafter) to the Facilitation Council for acting as Conciliator and Arbitrator in respect of the amount claimed against M/s. India Glycols Limited (respondent No.2 herein). The amounts claimed by the claimant against respondent No.2 were as follows: Principal: Rs. 40,29,862.00 and Interest: Rs. 80,89,605.00 (as on the date of filing the reference). The reference was registered and admitted by the Facilitation Council on 28.10.2015.
4.1. According to the claimant, respondent No.2 had raised purchase order dated 17.03.2008 for supply of HVAC, doors, windows, false ceiling etc., including installation and commissioning at M/s. IGL site for their NHPS Dehradun Project for an amount of Rs.2,01,00,000.00 plus excise duty etc., with the terms and conditions of payment as under:
b) 10% against submission of drawings;
c) 50% payment as per the break up approved by M/s.IGL and on submission of dispatch documents on prorate basis;
d) 10% payment will be released after mechanical completion at site to be certified by M/s.IGL representative;
e) 10% payment shall be paid on submission of performance bank guarantee of equivalent amount as per IGL format valid for a period of 24 months from the date of successful commissioning;
4.2. According to the claimant, respondent No.2 had released 20% of the order value as advance on 08.05.2008 and further 10% of the order value as advance against submission of drawings on 31.05.2008. Thereafter, claimant started supply of goods from 04.06.2008 onwards and deputed erection team to the site. It submitted bill for supply/services on 21.03.2009. Respondent No.2 released 50% of the bills and retained balance amount. Claimant and respondent No.2 continued mechanical erection and submitted inspection report on 24.03.2009 whereafter claimant requested respondent No.2 to release 10% of the order value but the same was not responded to by respondent No.2 though respondent No.2 did not deny the fact that it owed 20% of the amount to the claimant. According to the claimant, it had deputed personnel for carrying out the necessary modifications as requested by respondent No.2 from time to time besides recording minutes of the meetings held on 14/15th October, 2009, 20th May, 2011 and 20th April, 2013, duly signed by both the parties.
4.3. Despite request by the claimant for release of the balance 20% of the purchase order amount, respondent No.2 had maintained silence without any payment. A series of correspondences were exchanged between the parties. Ultimately, claimant issued a legal not
Balasaria Construction (P) Ltd. v. Hanuman Seva Trust
Bharat Sewa Sansthan v. U.P.Electronics Corporation (AIR 2007 SC 2961)
Deep Industries Limited v. Oil and Natural Gas Corporation Limited
Dhanrajamal Gobindram v. Shamji Kalidas and Co.
Gujarat Urja Vikas Nigam Ltd. v. Essar Power Ltd.
Indur District Cooperative Marketing Society Ltd. v. Microplex (India), Hyderabad
K. Prabhakaran v. P. Jayarajan ((2005) 1 SCC 754)
M/s. Indu Projects Limited v. Telangana Micro & Small Enterprises Facilitation Council
Punjab State Electricity Board, Mahilpur v. Guru Nanak Cold Storage & Ice Factory, Mahilpur
M/s. Sterling Industries v. Jayprakash Associates Ltd.
National Highways Authority of India v. Sayedabad Tea Company Limited
Ramesh B. Desai v. Bipin Vadilal Mehta
State of Gujarat through Chief Scretary v. Amber Builders
SBP and Co. v. Patel Engineering Ltd.
Savitra Khandu Beradi v. Nagar Agricultural Sale and Purchase Cooperative Society Ltd., Ahmednagar
T.N. Generation & Distribution Corpn. Ltd. v. PPN Power Generating Co. (P) Ltd.
Point of Law : Court are of the unhesitant view that learned Single Judge fell in error in not only entertaining the writ petition but also in allowing the same by setting aside the award dated 28.10....
The main legal point established in the judgment is that the Facilitation Council has the jurisdiction to act as an Arbitrator after the failure of conciliation proceedings under the MSME Act. The ri....
The High Court cannot entertain writ petitions challenging awards of the Micro and Small Enterprises Facilitation Council without the mandatory deposit of 75% of the awarded amount as per Section 19 ....
The mandatory pre-deposit requirement under Section 19 of the MSMED Act, 2006 for challenging an award and the overriding effect of the MSMED Act, 2006 over the Arbitration Act, 1996 in specific disp....
Section 34 of the Arbitration Act arises as is evident from sub Section (6) of Section 16 of the Arbitration Act, which inter alia provides that the parties aggrieved by such an arbitral award may ma....
The court ruled that a party to a dispute cannot waive the mandatory conciliation requirement under Section 18(2) of the MSMED Act, validating subsequent arbitration proceedings.
Writ petition against arbitral award is maintainable; petitioner must follow remedies under Arbitration Act.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.