IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
ALOK ARADHE, C.J.
Archon Powerinfra India Private Limited – Petitioner
Versus
M/s. Chabbras Associates – Respondent
Arbitration Application No. 108 of 2024
Decided On : 13-09-2024
(A) Arbitration and Conciliation Act, 1996 – Section 11(6) – Appointment of arbitrator – Dispute arising from Memorandum of Understanding (MoU) dated 25.01.2019 – The applicant sought arbitration for claims against the respondent, which was not denied – The court found the MoU contained an arbitration clause and the dispute was arbitrable. (Paras 2, 15, 17)
(B) Jurisdiction of Arbitral Tribunal – The doctrine of kompetenz-kompetenz allows the tribunal to rule on its own jurisdiction, including objections regarding the existence of the arbitration agreement. (Paras 13, 14)
Facts of the case: The applicant and respondent entered into an MoU for project support, leading to disputes over contract execution and bank guarantees. The applicant invoked arbitration after the respondent denied claims.
Findings of Court: The court confirmed the existence of an arbitration agreement in the MoU and appointed a sole arbitrator to resolve the dispute.
Issues: Whether the MoU constituted a valid arbitration agreement and if the dispute was arbitrable.
Ratio Decidendi: The court ruled that the MoU contained an arbitration clause, and disputes arising from it were subject to arbitration, emphasizing the principle of kompetenz-kompetenz.
Result: Arbitration Application allowed.
ORDER :
1. Mr. Lomesh Kiran N. learned counsel representing Mr. Emil Joseph, learned counsel for the applicant. Mr. P.U. Bhaskara Rao, learned counsel for the respondent.
2. This application under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”) has been filed to seek appointment of an arbitrator to adjudicate the claims and disputes between the parties as envisaged under Clause 32 of Memorandum of Understanding (hereinafter referred to as “MoU”) dated 25.01.2019.
3. Facts leading to filing of this application briefly stated are that the applicant is a company incorporated on 18.09.2017 in Ahmedabad. The respondent is also a company situated in Hyderabad. The applicant and respondent entered into an MoU on 25.01.2019 whereunder the respondent agreed to render complete support to the applicant to participate in the tenders as mentioned in the MoU dated 25.01.2019. Sometime in the month of January, 2019, the respondent participated in Tender Ref: HCC/LPG-32/Pt-171/ 2018-19 (hereinafter referred to as ‘the Tender”) for a bid titled “Construction of Plant Buildings, Non-Plant Buildings, ground improvement and allied works at grass root LPG bottling facility at Motihari, Bihar” (hereinafter referred to as ‘the Project”) raised by the Indian Oil Corporation Limited (IOCL). The respondent was awarded the contract on 28.03.2019 and a letter of acceptance was issued to it.
4. Thereafter on 29.04.2019, a Work Order was issued in favour of the applicant to execute the work under the Project. The respondent by a communication dated 02.01.2020 made an additional demand to the applicant for a bank guarantee for the escrow account. The additional bank guarantee was not a part of the MoU dated 25.01.2019. However, the applicant submitted a bank guarantee worth Rs.35,00,000.00, which was encashed by the respondent sometime in the month of April, 2020.
5. On 01.04.2020, the respondent issued an e-mail in which the status of the applicant was acknowledged as “MoU holder” and the respondent requested the applicant to share all information regarding value of work conducted on the Project site and dues receivable from IOCL in order to furnish the information to IOCL so that further payments may be disbursed to the applicant.
6. The applicant issued a notice on 29.09.2021 to the respondent, in which the various breaches committed by the respondent under the MoU dated 25.01.2019 were highlighted. The respondent sent a reply on 19.10.2021, in which the claims made by the applicant were denied. Thereafter, the applicant issued an e-mail on 14.07.2023 invoking arbitration under Clause 32 of the MoU dated 25.01.2019. The aforesaid e-mail was responded to by the respondent on 24.07.2023. Thereafter, this petition has been filed seeking appointment of an Arbitrator.
7. Learned counsel for the applicant submitted that neither the execution of the MoU dated 25.01.2019 nor the existence of the arbitration clause has been denied on behalf of the respondent. Attention of this Court has also been invited to by Clause 16.1 and Clause 27 of the Memorandum of Understanding dated 25.01.2019 and it has been submitted that the respondent is at liberty to urge all such contentions before the Arbitrator. In support of his submission, reliance has been placed on decision of Supreme Court In Re: Interplay between Arbitration Agreements under the Arbitration and Conciliation Act, 1996 and the Indian Stamp Act, 1899, 2023 SCC Online SC 1666.
8. On the other hand, learned counsel for the respondent submits that the MoU dated 25.01.2019 is only a pre-tender MoU and thereafter no back to back agreement has been executed between the parties. It is further submitted that the MoU is not in existence. It is also contended that there is neither an agreement nor an arbitration clause under which the dispute raised by the applicant can be referred for adjudication. It is further submitted that the applicant has been debarred by IOCL from part
AI
The court affirmed that disputes arising from a Memorandum of Understanding containing an arbitration clause are subject to arbitration under the Arbitration and Conciliation Act, 1996.
The arbitration clause survives the expiration of the main contract, and issues of limitation must be decided by the Arbitral Tribunal.
The existence of an arbitration agreement under Section 11 requires clear indication of a binding contract, which was absent in this case; the Letter of Intent was merely a precursor to an actual con....
The sufficiency of stamp duty payment rendered the document admissible, and the named arbitrator was disqualified, leading to the appointment of Hon’ble Shri Justice K. K. Lahoti as Arbitrator.
Arbitration - Undisputedly both the parties had intended to refer the disputes to the arbitration and had accordingly agreed for the same. Hence, there being existence of arbitration agreement, and t....
Appointment of Arbitrator - Existence of arbitration agreement - Plea of agreement being unstamped also does not prevent this court in appointing an arbitrator while exercising jurisdiction under sec....
The court's authority under Section 11 of the Arbitration Act restricts to determining the existence of an arbitration agreement, deferring substantive disputes to the arbitrator.
The main legal point established in the judgment is the principle of minimal judicial intervention in the arbitral process, emphasizing the competence of the arbitrator to decide all preliminary issu....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.