ARBITRATION AND CONCILIATION AMENDMENT ACT, 2015
(1) This Act may be called the Arbitration and Conciliation (Amendment) Act, 2015.
(2) It shall be deemed to have come into force on the 23rd October, 2015.
The Arbitration and Conciliation Amendment Act, 2015, represents a significant reform in India's arbitration landscape, aimed at enhancing the efficiency and effectiveness of arbitration proceedings. Section 1 of the Act outlines its applicability and commencement, setting the stage for the subsequent provisions that govern arbitration in India.
Section 1 of the Arbitration and Conciliation Amendment Act, 2015, specifies the short title of the Act and its commencement date. It states that the Act may be cited as the Arbitration and Conciliation (Amendment) Act, 2015, and it came into force on October 23, 2015.
The scope of Section 1 is primarily administrative, establishing the legal framework within which the amendments to the Arbitration and Conciliation Act, 1996, will operate. It indicates that the provisions of the Amendment Act apply to all arbitration proceedings initiated after its commencement.
Section 1 does not prescribe any punishments or penalties. Its focus is on the formal introduction and commencement of the Act rather than on enforcement mechanisms.
In the Arbitration and Conciliation Act, 1996 (26 of 1996) (hereinafter referred to as the principal Act), in section 2,--
(I) in sub-section (1),--
(A) for clause (e), the following clause shall be substituted, namely:--
'(e) "Court" means--
(i) in the case of an arbitration other than international commercial arbitration, the principal Civil Court of original jurisdiction in a district, and includes the High Court in exercise of its ordinary original civil jurisdiction, having jurisdiction to decide the questions forming the subject-matter of the arbitration if the same had been the subject-matter of a suit, but does not include any Civil Court of a grade inferior to such principal Civil Court, or any Court of Small Causes;
&n
Legal Comments- Section 2 - Definition of "Court" (amended) - The Amendment Act 2015 redefines "Court" for international and domestic arbitrations, restricting jural reach and aligning interim measures with intended forum, with prospective application. [EMAAR MGF LAND LIMITED VS AFTAB SINGH]- Section 2 - Prospective application (Section 26) - The Act states that amendments apply to arbitral proceedings commenced on/after the date of commencement unless parties agree otherwise; pending proceedings often governed by pre-2015 regime. [Subramaniyan N. N. VS Anwar. C. K. ]- Section 34 - Public policy and patent illegality (amendments) - Post-2015, grounds include patent illegality and limits on merits review; Explanation 1/2 clarify scope of “fundamental policy” and narrow “most basic notions of morality/justice.” [Silver Resorts Hotel India Pvt. Ltd. VS Wimberly Allison Tong & Goo (UK)]- Section 34(2A) - Patent illegality (non-international) - Introduced to allow setting aside for patent illegality in non-international arbitrations; restricted by proviso not to permit mere re-appraisal of evidence. [Silver Resorts Hotel India Pvt. Ltd. VS Wimberly Allison Tong & Goo (UK)]- Section 34(2)(b)(ii) - Public policy test (amended) - Explanations broaden: fraud, fundamental policy, or most basic notions of morality; Explanation 2 bars merits review of fundamental policy, clarifying constraints. [Silver Resorts Hotel India Pvt. Ltd. VS Wimberly Allison Tong & Goo (UK)]- Section 36(2)/(3) - Stay of enforcement (post-2015/2016 amendments) - Automatic stays are not guaranteed; courts may impose conditions for stay, including partial monetary deposits; discretionary framework clarified by Board of Control for Cricket v. Kochi Cricket (SC). [Jaipur Municipal Corporation VS Shilpa Construction]- Section 11(6) - Appointment of arbitrators - Post-2015, jurisdiction focuses on existence of arbitration agreement; court’s role is to appoint an arbitrator if agreement exists, with inbuilt inbuilt procedures; prior cases emphasize party autonomy and inbuilt contractual appointment mechanisms. [M S. Kalicharan Pandey And Company vs Union Of India]- Section 26 - Clarifications on pending proceedings - Applies to proceedings commenced after 23 Oct 2015; pending matters governed by unamended provisions unless parties agree otherwise; important for section 11/12 challenges. [Subramaniyan N. N. VS Anwar. C. K. ]- Section 9 - Interim measures (amendment) - Section 9 extended to international arbitrations under proviso; interim relief available where-seat outside India, subject to agreements; interpretation consistent with BALCO/Bhatia lineage. [GALATEA LTD. VS SHREE KRISHNA EXPORTS]- Section 12(5) - Challenge to arbitrator - Amendment clarified that challenge to appointment before the arbitrator is via Section 11(6) and intra-arbitral mechanisms; pre‑amendment rule retained in some contracts unless amended. [Abb India Limited VS Bharat Heavy Electricals Limited]- Public policy scope post-amendments - The public policy ground is now narrowly construed; the “fundamental policy” doctrine is invoked only in exceptional cases; merits review is generally restricted. [Gillanders arbuthnot and co. Limited VS Steel Authority Of India Limited]- International arbitration framework - Section 2(2) proviso extends certain Part I protections to international arbitrations, even if seated abroad, unless parties agree otherwise; this is a landmark shift in the territorial approach. [Pasl Wind Solutions Private Limited VS Ge Power Conversion India Private Limited]- Interim relief and jurisdiction conflicts - BALCO/ARB decisions guide, but 2015 amendments shift emphasis to arbitration-centric remedies, limiting court interventions in merits. [Sterling and Wilson International Fze vs Sunshakti Solar Power Projects Private Limited]- Arbitration & Conciliation (Amendment) Ordinance 2015 - Transitional understanding preserved in subsequent Act; Section 37 remains, enabling appeals for certain orders, including reviewability of awards and interim measures. [Ascot Estates Pvt. Ltd. VS Bon Vivant Life Style Pvt. Ltd. ]- Stay of award in pre/post amendment contexts - Courts have rejected automatic stays under Section 34 objections; discretionary stays with conditions uphold the objective of timely enforcement. [Jaipur Municipal Corporation VS Shilpa Construction]- Enforceability of foreign awards - Section 48 remains, with explanations clarifying grounds to refuse enforcement and limiting merits review; post-amendments emphasize lawfulness of enforcement under New York Convention. [Integrated Sales Services Limited VS Arun Dev s/o Govindvishnu Uppadhyaya]- Appointment versus selection of arbitrators in government contracts - Courts uphold that internal appointment by government bodies is permissible if not contravening Section 12(5) and related provisions; emphasis on inbuilt dispute resolution mechanisms. [SP SINGLA CONSTRUCTIONS PVT. LTD. VS STATE OF HIMACHAL PRADESH]- Arbitration continuity after amendment - Where amendment applies, proceedings may continue under amended regime if parties intended; otherwise, unamended regime may govern pending actions. [Valliyara Trading And Services (Pvt. ) Ltd. VS Kotak Mahindra Bank Ltd. ]- Grounds for setting aside foreign awards - Section 48 explores grounds; post-2015 explanations narrow the scope for challenging foreign awards, focusing on jurisdictional and procedural integrity rather than merits. [Integrated Sales Services Limited VS Arun Dev s/o Govindvishnu Uppadhyaya]- Fast-track/arbitral timeframes (Section 29A) - Time-bound awards with potential extension via court, where applicable, subject to jurisdictional interpretation of “court” under amended Section 29A(4)/(5). [Subramaniyan N. N. VS Anwar. C. K. ]- Practical import for practitioners - Counsel should identify whether arbitration was commenced before 23/10/2015; determine applicability of 2015 amendments; consider Section 26 savings and Section 34 grounds accordingly. [Shilpa Construction VS Jaipur Municipal Corporation, Jaipur Through Chief Executive Officer]- Jurisdictional cover in mixed-seat arbitrations - Amendments ensure Indian courts retain limited but structured authority for interim measures in international arbitrations seated abroad, aligning with BALCO reforms. [Pasl Wind Solutions Private Limited VS Ge Power Conversion India Private Limited]- Public policy and “fundamental notions” - Explanations provide narrow, controlled use of public policy-based challenges to awards, reducing interference into arbitral merits. [Hll Lifecare Limited (hll) VS Employees State Insurance Corporation (esic)]- Enforcement posture post-amendments - The amended regime supports enforceability of awards as decrees under CPC, with Section 50/II appellate pathways preserved, subject to Section 48 grounds. [Integrated Sales Services Limited VS Arun Dev s/o Govindvishnu Uppadhyaya]
In section 7 of the principal Act, in sub-section (4), in clause (b), after the words "or other means of telecommunication", the words "including communication through electronic means" shall be inserted.
In section 8 of the principal Act,--
(i) for sub-section (1), the following sub-section shall be substituted, namely:--
"(1) A judicial authority, before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party to the arbitration agreement or any person claiming through or under him, so applies not later than the date of submitting his first statement on the substance of the dispute, then, notwithstanding any judgment, decree or order of the Supreme Court or any Court, refer the parties to arbitration unless it finds that prima facie no valid arbitration agreement exists.";
(ii) in sub-section (2), the following proviso shall be inserted, namely:--
"Provided that where the original arbitration agreeme
Legal Comments
"Scope of Section 4" - Section 4 of the Arbitration and Conciliation Act, 1996, as amended by the 2015 Act, narrows judicial intervention at the pre-arbitral stage, mandating reference to arbitration where a valid agreement exists and allowing court intervention only to determine existence/validity of arbitration agreement; post-2015, Section 11(6A) further confines pre-referral inquiry to existence of an arbitration agreement. - [IN RE: INTERPLAY BETWEEN ARBITRATION AGREEMENTS UNDER THE ARBITRATION AND CONCILIATION ACT 1996 AND THE INDIAN STAMP ACT 1899 VS . ]
"Seeded reform - purpose of amendment" - The 2015 amendments were designed to curb judicial interference and expedite arbitral processes by restricting court scrutiny to existence of arbitration agreement (Section 11(6A)) and by revising Section 8 to require timely initiation of references; this aligns with Law Commission recommendations. - [IN RE: INTERPLAY BETWEEN ARBITRATION AGREEMENTS UNDER THE ARBITRATION AND CONCILIATION ACT 1996 AND THE INDIAN STAMP ACT 1899 VS . ]
"Unilateral arbitrator appointment – Section 12(5) import" - Section 12(5), added in 2015, prohibits appointments of arbitrators who fall within Seventh Schedule relationships; this promotes neutrality and independence, with waivers possible only by express post-dispute written agreement. - [Duro Felguera, S. A. VS Gangavaram Port Limited]
"Section 29A timing and extension" - Section 29A(4) creates a 12-month initial mandate for arbitral proceedings, with extensions up to 6 months by consent and further extensions possible; post-2015 jurisprudence clarifies these timelines are not absolute rights of parties but time-bound objectives subject to extension by court or consent. - [P. K. Construction Co VS Shimla Municipal Corporation]
"Interpretation of 'court' post-2015" - Following ARBITRATION & CONCILIATION (Amendment) Act 2015, the term "court" in Section 29(4) is contextually interpreted as Supreme Court for international arbitrations and High Courts for domestic arbitrations; this allows lib erties in timely extensions of proceedings through the appropriate courts. - [Lots Shipping Company Limited VS Cochin Port Trust Board Of Trustees, Willingdon Island]
"Section 8(1) time frame change" - The amended Section 8(1) uses "not later than the date of submitting his first statement on the substance of the dispute," coupled with CPC/commercial court reforms, to tighten the window for invoking Section 8; failure to comply results in forfeiture of the right to refer. - [SPML Infra Ltd. vs Trisquare Switchgears Pvt. Ltd.]
"Section 11(6A) narrowens pre-referral inquiry" - Post-2015, Section 11(6A) restricts the referral court to examining only the existence of an arbitration agreement; questions of non-arbitrability or merits are reserved for the arbitral tribunal and subsequent court challenge under Section 34. - [Vimlesh Baregama S/o Shri Khyali Lal Brregama VS Manglam Cement Ltd. ]
"Duro Felguera and subsequent jurisprudence" - The Supreme Court in Duro Felguera, and later decisions, clarifies that Section 11(6A) confines pre-referral inquiry to validity/existence of arbitration agreement; non-arbitrability questions are for the tribunal (subject to limited pre-referral screening). - [Vimlesh Baregama S/o Shri Khyali Lal Brregama VS Manglam Cement Ltd. ]
"Neutrality of arbitrators – Section 12(5) Seventh Schedule" - Amended Section 12(5) disqualifies certain relationships (Seventh Schedule) to ensure independence; government contracts emphasize neutrality; non-compliance may render appointment invalid. - [Victory Oil Gram Udyog Association VS Managing Director]
"Interplay of Section 8, 11 and 6A in practice" - Post-amendment law requires courts to refer to arbitration if prima facie an arbitration agreement exists, but not to entertain filings that contradict the revised scope (e.g., stamping issues or ineligible arbitrators); the balance aims to reduce judicial interference while preserving enforceability. - [Shyamjee Prepaid Services VS Top Steels And Mrs. Renu Devi]
"Impact on stay and interim relief" - Post-2015 amendments, securing a stay of arbitral awards and interim relief follow updated frameworks (Section 36(2)/(3) and Order 41 CPC) with discretionary stays and conditions; automatic stay on objection under Section 34 is no longer guaranteed. - [Jaipur Municipal Corporation VS Shilpa Construction]
"Remedies for challenged arbitrator appointments" - The Act provides an integrated remedy framework: challenges to arbitrator appointments proceed under Section 12/13, with avenues to challenge and potentially set aside awards under Section 34; the Act discourages external judicial interference in the arbitral process. - [Ramgopalsomani Station Road VS Union of India Acting Through Chief Electrical Engineer (Construction), South East Central Railway]
"Non-signatory impleadment issue" - Arbitral Tribunal can be asked to implead non-signatories only in light of evolving principles (Group of Companies doctrine) and in accordance with amended Section 8 and 12; courts emphasize careful reading of arbitration clauses and documents. - [Abhibus Services India Pvt. Limited, Hyderabad VS Pallavan Transport Consultancies Services Ltd. , Represented by its Managing Director, Chennai]
"Role of tribunals as first reference point" - Post-amendment jurisprudence consistently emphasizes that the arbitral tribunal remains the primary forum for non-arbitrability, admissibility, and enforcement questions; courts intervene primarily to enforce or stay awards and to ensure validity of arbitration agreements. - [Aarohi Construction VS Manglam Build Developers Pvt. Ltd. ]
"Stamping and enforceability of arbitration agreements" - The legality and stamping of arbitration agreements are prerequisites for Section 11 references; courts have held that unstamped or insufficiently stamped agreements render applications under Section 11/8 not maintainable, with limited exceptions. - [SPML Infra Ltd. vs Trisquare Switchgears Pvt. Ltd.]
"Impact on public policy grounds" - The 2015 amendments originally addressed grounds for setting aside awards, including public policy; subsequent jurisprudence continues to sculpt the contours of public policy review, aligning with pro-arbitration objectives while preserving core protections. - (general reference to reform and public policy within the Act)
"Interplay with other statutes and reforms" - The 2015 amendments were coordinated with Commercial Courts Act and CPC amendments to streamline commercial dispute adjudication; this alignment reduces delays and harmonizes pre-trial processing with arbitral timetables. - [SHINE TRAVELS & CARGO PVT. LTD VS MITISUI PRIME ADVANCED COMPOSITE INDIA LTD]
"Award costs and post-award interest" - Section 31(7) and 31A govern post-award interest on sums directed by an award and on costs fixed by the tribunal; Hyder Consulting clarifies the interaction between pre/post-award interest and post-award costs. - [Overeas Drilling Limitd VS Directorate General Of Hydrocarbons Of India]
"Arbitral tribunal’s disciplinary and procedural discretion" - The Act vests broad discretion in the arbitral tribunal for procedural matters, including costs and interest on costs under Section 31A; courts defer to the tribunal absent explicit directions in the award. - [Overeas Drilling Limitd VS Directorate General Of Hydrocarbons Of India]
"Effect of pre-conditions on appointment in sector-specific procurement" - Court decisions in procurement/tender contexts emphasize neutrality of arbitrators and compliance with Section 12(5), particularly where government or quasi-government entities are involved; this preserves integrity in public procurement arbitrations. - [Victory Oil Gram Udyog Association VS Managing Director]
"Limitations on judicial review of Section 11 orders" - Delhi and other High Courts have held that Section 11(6) orders are not subject to full merits-based review; review is typically confined to matters like manifest error of record or jurisdictional irregularities, not re-appraisal of arbitrability. - [VILLAYATI RAM MITTAL PVT. LTD. VS INSTITUTE FOR SOCIALIST EDUCATION]
"Post-2015 practice guidance on arbitrator independence" - The judiciary has consistently stressed independence/impartiality standards for arbitrators (Seventh/Schedule grounds) to prevent biased appointments, especially in public sector contexts; this is reinforced by 2015 amendments. - [Victory Oil Gram Udyog Association VS Managing Director]
"Practical takeaway for practitioners" - When seeking reference to arbitration under Section 8/11, ensure: (a) there is a valid arbitration agreement; (b) the agreement is properly stamped; (c) arbitrator independence is ensured by Section 12(5) and Seventh Schedule; (d) any stay applications align with Section 36 and CPC provisions; (e) timelines under Section 29A are observed with possible Court-approved extensions. - [IN RE: INTERPLAY BETWEEN ARBITRATION AGREEMENTS UNDER THE ARBITRATION AND CONCILIATION ACT 1996 AND THE INDIAN STAMP ACT 1899 VS . ], [Shyamjee Prepaid Services VS Top Steels And Mrs. Renu Devi], [Lots Shipping Company Limited VS Cochin Port Trust Board Of Trustees, Willingdon Island]
"Key caveat on jurisdictional scope" - The 2015 amendments explicitly limit court intervention to existence/validity of arbitration agreements at the pre-arbitral stage, and require arbitration for disputes within scope of the agreement; this limits court review on merits and non-arbitrability at the Section 11 stage. - [Vimlesh Baregama S/o Shri Khyali Lal Brregama VS Manglam Cement Ltd. ], [SPML Infra Ltd. vs Trisquare Switchgears Pvt. Ltd.]
"Cross-reference to Major cases cited" - Foundational judgments such as Duro Felguera (2017), Nortel Networks, Pratibha Industries, and SBP & Co. guide post-2015 interpretation, shaping the current framework for Section 11/6A and 12/5 neutrality. - [Akshay Verma Son Of Late Shri Dinesh Kumar Verma VS Sita Devi Verma Wife Of Late Shri Bhim Singh Verma], [Overeas Drilling Limitd VS Directorate General Of Hydrocarbons Of India]
Note: The above points are distilled from the provided sources and linked citations. Where a particular source did not directly address a point, that point has not been included.
Section 9 of the principal Act shall be renumbered as sub-section (1) thereof, and after sub-section (1) as so renumbered, the following sub-sections shall be inserted, namely:--
"(2) Where, before the commencement of the arbitral proceedings, a Court passes an order for any interim measure of protection under sub-section (1), the arbitral proceedings shall be commenced within a period of ninety days from the date of such order or within such further time as the Court may determine.
(3) Once the arbitral tribunal has been constituted, the Court shall not entertain an application under sub-section (1), unless the Court finds that circumstances exist which may not render the remedy provided under section 17 efficacious.".
In section 11 of the principal Act,--
(i) in sub-sections (4), (5) and (6), for the words "the Chief Justice or any person or institution designated by him" wherever they occur, the words "the Supreme Court or, as the case may be, the High Court or any person or institution designated by such Court" shall be substituted;
(ii) after sub-section (6), the following sub-sections shall be inserted, namely:--
"(6A) The Supreme Court or, as the case may be, the High Court, while considering any application under sub-section (4) or sub-section (5) or sub-section (6), shall, notwithstanding any judgment, decree or order of any Court, confine to the examination of the existence of an arbitration agreement.
(6B) The designation of any person or institution by
Section 6 of the Arbitration and Conciliation (Amendment) Act, 2015, primarily clarifies the procedure for the appointment of arbitrators, limiting judicial intervention and reinforcing the principle of minimal court interference in arbitration proceedings. It is part of the broader legislative effort to streamline arbitration, reduce delays, and promote alternative dispute resolution in India, aligning with international standards.
Section 6 stipulates that the appointment of an arbitrator shall be made in accordance with the procedure agreed upon by the parties. If the parties fail to agree, the appointment shall be made by the designated authority, typically the courts, following the procedure outlined in the arbitration agreement or, failing that, by the court or the arbitral institution as per the law. The section emphasizes that courts' role is limited to the examination of the existence of an arbitration agreement and does not extend to merits or non-arbitrability issues.
Section 6 of the Arbitration and Conciliation (Amendment) Act, 2015, marks a pivotal shift towards limiting judicial interference in arbitration proceedings. It enshrines the principle that courts' role is confined to verifying the existence of an arbitration agreement and ensuring procedural compliance, thereby fostering an arbitration-friendly environment. This aligns with international best practices, reduces delays, and enhances the enforceability of arbitral awards. Judicial pronouncements post-2015 reinforce this approach, emphasizing that substantive issues like validity, enforceability, or non-arbitrability are for the arbitral tribunal to decide, ensuring arbitration remains a swift and effective dispute resolution mechanism.
Note: The references are drawn from the provided sources, especially the judicial decisions and legislative provisions cited therein.
After section 11 of the principal Act, the following new section shall be inserted, namely:--
"11A. Power of Central Government to amend Fourth Schedule
(1) If the Central Government is satisfied that it is necessary or expedient so to do, it may, by notification in the Official Gazette, amend the Fourth Schedule and thereupon the Fourth Schedule shall be deemed to have been amended accordingly.
(2) A copy of every notification proposed to be issued under sub-section (1), shall be laid in draft before each House of Parliament, while it is in session, for a total period of thirty days which may be comprised in one session or in two or more successive sessions, and if, before the expiry of the session immediately following the session or the successive sessions aforesaid, both Houses agree in di
In section 12 of the principal Act,--
(i) for sub-section (1), the following sub-section shall be substituted, namely:--
"(1) When a person is approached in connection with his possible appointment as an arbitrator, he shall disclose in writing any circumstances,--
(a) such as the existence either direct or indirect, of any past or present relationship with or interest in any of the parties or in relation to the subject-matter in dispute, whether financial, business, professional or other kind, which is likely to give rise to justifiable doubts as to his independence or impartiality; and
(b) which are likely to affect his ability to devote sufficient time to the arbitration and in particular his ability to complete the entire arbitration within a pe
SupremeToday AI Service seems to be Down for a While!
In section 14 of the principal Act, in sub-section (1), in the opening portion, for the words "The mandate of an arbitrator shall terminate if ", the words "The mandate of an arbitrator shall terminate and he shall be substituted by another arbitrator, if " shall be substituted.
For section 17 of the principal Act, the following section shall be substituted, namely:--
"17. Interim measures ordered by arbitral tribunal
(1) A party may, during the arbitral proceedings or at any time after the making of the arbitral award but before it is enforced in accordance with section 36, apply to the arbitral tribunal--
(i) for the appointment of a guardian for a minor or person of unsound mind for the purposes of arbitral proceedings; or
(ii) for an interim measure of protection in respect of any of the following matters, namely:--
(a) the preservation, interim custody or sale of any goods which are the subject-matter of the arbitration agreement;
In section 23 of the principal Act, after sub-section (2), the following sub-section shall be inserted, namely:--
"(2A) The respondent, in support of his case, may also submit a counterclaim or plead a set-off, which shall be adjudicated upon by the arbitral tribunal, if such counterclaim or set-off falls within the scope of the arbitration agreement.".
Section 11 of the Arbitration and Conciliation Act, 1996, as amended by the Arbitration and Conciliation (Amendment) Act, 2015, delineates the procedure for courts to appoint arbitrators when parties fail to do so themselves. The 2015 amendment significantly restricted judicial inquiry, confining it primarily to the existence of an arbitration agreement, thereby emphasizing party autonomy and expediting arbitration proceedings.
Post-2015 Amendment, Section 11(6A) mandates that courts, while considering applications under subsections (4), (5), or (6), shall, notwithstanding any judgment or order, confine their examination solely to the existence of an arbitration agreement. The scope is limited to verifying whether a valid arbitration clause exists, excluding inquiry into validity, enforceability, or other preliminary issues unless explicitly permitted.
The 2015 amendments to Section 11 have significantly narrowed the scope of judicial intervention, emphasizing the importance of party autonomy and speedy resolution through arbitration. Courts are now confined to a preliminary, 'prima facie' verification of the existence of arbitration agreements, leaving substantive issues such as validity, enforceability, or arbitrability to the arbitral tribunal. This approach aligns with legislative intent, judicial pronouncements, and the overarching goal of promoting arbitration as an efficient dispute resolution mechanism.
Note: This commentary synthesizes multiple judicial decisions and authoritative sources to provide a comprehensive understanding of Section 11 post-2015 amendment.
In section 24 of the principal Act, after the proviso to sub-section (1), the following proviso shall be inserted, namely:--
"Provided further that the arbitral tribunal shall, as far as possible, hold oral hearings for the presentation of evidence or for oral argument on day-to-day basis, and not grant any adjournments unless sufficient cause is made out, and may impose costs including exemplary costs on the party seeking adjournment without any sufficient cause.".
In section 25 of the principal Act, in clause (b), at the end, after the words "allegations by the claimant", the words "and shall have the discretion to treat the right of the respondent to file such statement of defence as having been forfeited" shall be inserted.
In section 28 of the principal Act, for sub-section (3), the following sub-section shall be substituted, namely:--
"(3) While deciding and making an award, the arbitral tribunal shall, in all cases, take into account the terms of the contract and trade usages applicable to the transaction.".
After section 29 of the principal Act, the following new sections shall be inserted, namely:--
"29A. Time limit for arbitral award
(1) The award shall be made within a period of twelve months from the date the arbitral tribunal enters upon the reference.
Explanation.-- For the purpose of this sub-section, an arbitral tribunal shall be deemed to have entered upon the reference on the date on which the arbitrator or all the arbitrators, as the case may be, have received notice, in writing, of their appointment.
(2) If the award is made within a period of six months from the date the arbitral tribunal enters upon the reference, the arbitral tribunal shall be entitled to receive such amount of additional fees as the parties may agree.
&nb
In section 31 of the principal Act,--
(i) in sub-section (7), for clause (b), the following clause shall be substituted, namely:--
'(b) A sum directed to be paid by an arbitral award shall, unless the award otherwise directs, carry interest at the rate of two per cent. higher than the current rate of interest prevalent on the date of award, from the date of award to the date of payment.
Explanation.-- The expression "current rate of interest" shall have the same meaning as assigned to it under clause (b) of section 2 of the Interest Act, 1978 (14 of 1978).';
(ii) for sub-section (8), the following sub-section shall be substituted, namely:--
"(8) The costs of an arbitration shall be fixed by the arbitral t
After section 31 of the principal Act, the following new section shall be inserted, namely:--
'31A. Regime for costs
(1) In relation to any arbitration proceeding or a proceeding under any of the provisions of this Act pertaining to the arbitration, the Court or arbitral tribunal, notwithstanding anything contained in the Code of Civil Procedure, 1908 (5 of 1908), shall have the discretion to determine--
(a) whether costs are payable by one party to another;
(b) the amount of such costs; and
(c) when such costs are to be paid.
Explanation.-- For the purpose of this sub-section, "costs" means reasonable costs relating to--
In section 34 of the principal Act,--
(I) in sub-section (2), in clause (b), for the Explanation, the following Explanations shall be substituted, namely:--
"Explanation 1.-- For the avoidance of any doubt, it is clarified that an award is in conflict with the public policy of India, only if,--
(i) the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81; or
(ii) it is in contravention with the fundamental policy of Indian law; or
(iii) it is in conflict with the most basic notions of morality or justice.
Explanation 2.-- For the avoidance of doubt, the test as to whether there is a contravention wit
For section 36 of the principal Act, the following section shall be substituted, namely:--
"36. Enforcement
(1) Where the time for making an application to set aside the arbitral award under section 34 has expired, then, subject to the provisions of sub-section (2), such award shall be enforced in accordance with the provisions of the Code of Civil Procedure, 1908 (5 of 1908), in the same manner as if it were a decree of the court.
(2) Where an application to set aside the arbitral award has been filed in the Court under section 34, the filing of such an application shall not by itself render that award unenforceable, unless the Court grants an order of stay of the operation of the said arbitral award in accordance with the provisions of sub-section (3), on a separate application made for that
In section 37 of the principal Act, in sub-section (1), for clauses (a) and (b), the following clauses shall be substituted, namely:--
"(a) refusing to refer the parties to arbitration under section 8;
(b) granting or refusing to grant any measure under section 9;
(c) setting aside or refusing to set aside an arbitral award under section 34.".
In section 47 of the principal Act, for the Explanation, the following Explanation shall be substituted, namely:--
'Explanation.-- In this section and in the sections following in this Chapter, "Court" means the High Court having original jurisdiction to decide the questions forming the subject-matter of the arbitral award if the same had been the subject-matter of a suit on its original civil jurisdiction and in other cases, in the High Court having jurisdiction to hear appeals from decrees of courts subordinate to such High Court.'.
In section 48 of the principal Act, for the Explanation to sub-section (2), the following Explanations shall be substituted, namely:--
"Explanation 1.-- For the avoidance of any doubt, it is clarified that an award is in conflict with the public policy of India, only if,--
(i) the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81; or
(ii) it is in contravention with the fundamental policy of Indian law; or
(iii) it is in conflict with the most basic notions of morality or justice.
Explanation 2.-- For the avoidance of doubt, the test as to whether there is a contravention with the fundamental policy of Indian law shall not entail a review on
In section 56 of the principal Act, for the Explanation, the following Explanation shall be substituted, namely:--
'Explanation.-- In this section and in the sections following in this Chapter, "Court" means the High Court having original jurisdiction to decide the questions forming the subject-matter of the arbitral award if the same had been the subject-matter of a suit on its original civil jurisdiction and in other cases, in the High Court having jurisdiction to hear appeals from decrees of courts subordinate to such High Court.'.
In section 57 of the principal Act, in sub-section (1), for the Explanation, the following Explanations shall be substituted, namely:--
"Explanation 1.-- For the avoidance of any doubt, it is clarified that an award is in conflict with the public policy of India, only if,--
(i) the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81; or
(ii) it is in contravention with the fundamental policy of Indian law; or
(iii) it is in conflict with the most basic notions of morality or justice.
Explanation 2.-- For the avoidance of doubt, the test as to whether there is a contravention with the fundamental policy of Indian law shall not entail a review o
After the Third Schedule to the principal Act, the following new Schedules shall be inserted, namely:--
THE FOURTH SCHEDULE
[See section 11 (14)]
| Sum in dispute | Nothing contained in this Act shall apply to the arbitral proceedings commenced, in accordance with the provisions of section 21 of the principal Act, before the commencement of this Act unless the parties otherwise agree but this Act shall apply in relation to arbitral proceedings commenced on or after the date of commencement of this Act. |
(1) The Arbitration and Conciliation (Amendment) Ordinance, 2015 (Ord. 9 of 2015), is hereby repealed.
(2) Notwithstanding such repeal, anything done or any action taken under the principal Act, as amended by the said Ordinance, shall be deemed to have been done or taken under the corresponding provisions of the principal Act, as amended by this Act.
Section 27 of the Arbitration and Conciliation Act, 1996, as amended by the 2015 Amendment Act, plays a crucial role in defining the powers of arbitral tribunals and the courts in relation to the enforcement of arbitral proceedings, particularly concerning the assistance in obtaining evidence and the scope of judicial intervention.
Section 27 empowers arbitral tribunals or parties to seek assistance from courts to obtain evidence necessary for arbitral proceedings. It also delineates the scope of court intervention, including the power to punish disobedience or misconduct during arbitration, and clarifies the court's role in supporting arbitral processes.
Note: This commentary synthesizes legal interpretations and practical implications from various authoritative sources, emphasizing the significance of Section 27 in the arbitration framework post-2015 amendments.
Elevate your legal practice with advanced AI-driven research and drafting solutions. Experience unmatched efficiency, precision, and security, tailored exclusively for legal professionals.