2011 AIR(SC) 2979
Supreme Court of India
P. SATHASIVAM & THE HONOURABLE DR. JUSTICE B.S. CHAUHAN
M/s. MSK Projects (I) (JV) Ltd.
Versus
State of Rajasthan & Another
CIVIL APPEAL NO. 5416 OF 2011 with CIVIL APPEAL NO. 5417 OF 2011
Decided on : 21-07-2011
ii) What could be the effect on the contract as a whole for non-executing the work of the second phase?
The private appellant shall be entitled only for a sum of Rs.26.34 lacs awarded by the tribunal for delay in issuing the notification with 10% interest, if not paid already or it could be adjusted in the final accounts bills. With these observation, the appeals stand disposed of.
Judgment :
Dr. B.S. CHAUHAN, J.
1. Both these appeals have been preferred by the rival parties against the judgment and order dated 24.4.2007 passed by the High Court of Rajasthan (Jaipur Bench) in Civil Misc. Appeal No.1581 of 2006 under Section 37(1)(A) of the Arbitration and Conciliation Act, 1996 (hereinafter called “Act 1996”) against the order dated 17.1.2006 passed by the District Judge, Jaipur City, Jaipur in Arbitration Case No.89/2004 whereby the application filed by the State of Rajasthan under Section 34 of the Act 1996 for setting aside the arbitral award dated 1.12.2003 had been allowed.
2. Facts and circumstances giving rise to these appeals are:
A. The Public Works Department of the State of Rajasthan(hereinafter called “PWD”) decided in September 1997 to construct the Bharatpur bye-pass for the road from Bharatpur to Mathura, which passed through a busy market of the city of Bharatpur. For the aforesaid work, tenders were invited with a stipulation that the work would be executed on the basis of Build Operate and Transfer (BOT). The total extent of the road had been 10.850 k.ms. out of which 9.6 k.ms. was new construction and 1.25 k.ms. was improvement, i.e. widening and strengthening of the existing portion of Bharatpur-Deeg Road.
B. After having pre-bid conference/meeting and completing the required formalities it was agreed between the tenderers and PWD that compensation would be worked out on the basis of investment made by the concerned entrepreneur. The tender submitted by MSK-appellant for Rs.1,325 lacs was accepted vide letter dated 5.2.1998 and the MSK-appellant was called upon to furnish security deposit which was done on 25.7.1998. Concession agreement dated 19.8.1998 was entered into between the parties authorising collection of toll fee by MSK-appellant. According to this agreement, period of concession had been 111 months including the period of construction. The said period would end on 6.4.2008. It also contained the provisions for making repayment/collection of toll fee and in case of any difference/dispute to refer the matter to the Arbitrator.
C. MSK-appellant completed the Bharatpur bye-pass Project on 10.4.2000 and also started collection of toll fee as provided under the agreement with effect from 28.4.2000. There had been some problem in collecting the toll fee because of agitation by local people. The State issued Notification dated 1.9.2000 under the provisions of the Indian Tolls Act, 1851 and Rajasthan Motor Vehicles Taxation (Amendment) Act, 1994 (hereinafter called the `Notification dated 1.9.2000') preventing the entry of vehicles into Bharatpur city stipulating its operation with effect from 1.10.2000. MSK-appellant invoked arbitration clause raising the dispute with respect to:
(a) Delay in issuance of Notification prohibiting entry of commercial vehicles into Bharatpur town and diverting traffic through the bye-pass; and
(b) Collection of toll from vehicles using Bharatpur-Deeg patch of the road.
D. The State/PWD failed to make appointment of the Arbitrator. MSK-appellant preferred SB Civil Arbitration Application No.31 of 2002 before the High Court and the High Court vide order 12.4.2002 appointed the Arbitrator. The Arbitrators so appointed in their meeting on 8.5.2002 appointed the third Arbitrator. Claim Petition was filed before the Tribunal by MSK-appellant on 23.9.2002. The State submitted its reply to the claim petition on 7.12.2002.
E. The Arbitral Award was made in favour of MSK-appellant on 1.12.2003 according to which there had been delay on the part of the State of Rajasthan in issuing the Notification and the State failed to implement the same and the contractor was entitled to collect toll fee even from the vehicles using Bharatpur-Deeg part of the road. The State of Rajasthan was directed to pay a sum of Rs.990.52 lacs to MSK-appellant as loss due upto 31.12.2003 with 18% interest from 31.12.2003 onwards. The Tribunal further gave various other directions to the
Oil & Natural Gas Corporation Ltd. v SAW Pipes Ltd. AIR 2003 SC 2629
Hindustan Zinc Ltd. v Friends Coal Carbonisation (2006) 4 SCC 445
Union of India v Bungo Steel Furniture Pvt. Ltd. AIR 1967 SC 1032
Executive Engineer, Irrigation
Secretary, Irrigation Department, Govt. of Orissa & ors. v G.C. Roy
Hindustan Construction Co. Ltd. v State of Jammu & Kashmir AIR 1992 SC 2192
Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa v N.C. Budharaj (Dead) by Lrs.
Bhagawati Oxygen Ltd. v Hindustan Copper Ltd. AIR 2005 SC 2071
Indian Hume Pipe Co. Ltd. v State of Rajasthan (2009) 10 SCC 187).
Krishna Bhagya Jala Nigam Ltd. v G. Harischandra Reddy & anr. AIR 2007 SC 817
H.U.D.A v Raj Singh Rana AIR 2008 SC 3035
Ghaziabad Development Authority v Balbir Singh AIR 2004 SC 2141
Bihar State Housing Board v Arun Dakshy (2005) 7 SCC 103
Haryana Urban Development Authority v Manoj Kumar & anr. (2005) 9 SCC 541
H.U.D.A v Prem Kumar Agarwal & anr. JT 2008 (1) SC 590
State of U.P. & ors. v Devi Dayal Singh AIR 2000 SC 961
State of Gujarat v Shantilal Mangaldas & ors. AIR 1969 SC 634
Tata Iron & Steel Co. Ltd. v Union of India & ors. AIR 2000 SC 3706
Dwaraka Das v State of Madhya Pradesh & anr. AIR 1999 SC 1031
M/s. A.T. Brij Paul Singh & ors. v State of Gujarat AIR 1984 SC 1703
B.S.N.L v. Reliance Communication Ltd.
Grid Corporation of Orissa Ltd. & anr. v Balasore Technical School AIR 1999 SC 2262
Associated Engg. Co. v Govt. of Andhra Pradesh & anr. AIR 1992 SC 232
Gobardhan Das v Lachhmi Ram & ors. AIR 1954 SC 689
Seth Thawardas Pherumal v The Union of India AIR 1955 SC 468
Union of India v Kishorilal Gupta & Bros. AIR 1959 SC 1362
Alopi Parshad & Sons. Ltd. v Union of India AIR 1960 SC 588
Jivarajbhai Ujamshi Sheth & ors. v Chintamanrao Balaji & ors. AIR 1965 SC 214
Renusagar Power Co. Ltd. v General Electric Company & anr. AIR 1985 SC 1156
Kishore Kumar Khaitan & anr. v Praveen Kumar Singh (2006) 3 SCC 312
Williams v Lourdusamy & anr. (2008) 5 SCC 647
Cellular Operators Association of India & ors. v Union of India & ors. (2003) 3 SCC 186
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.