SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2011 Supreme(SC) 690

2011 AIR(SC) 2979
Supreme Court of India
P. SATHASIVAM & THE HONOURABLE DR. JUSTICE B.S. CHAUHAN
M/s. MSK Projects (I) (JV) Ltd.
Versus
State of Rajasthan & Another
CIVIL APPEAL NO. 5416 OF 2011 with CIVIL APPEAL NO. 5417 OF 2011
Decided on : 21-07-2011

Advocates Appeared:
For the Appellant :K. K. Venugopal Sr. Advocate, Shirish Patel, Karan Patel, Ankur Saigal, Abhay Anand, Gaurav Singh, Ms. Bina Gupta, Advocates.
For the Respondents:Dr.Manish Singhvi, AAG, Vijay Verma, Milind Kumar, Advocates.

Headnote:A) ARBITRATION AND CONCILIATION ACT : S.31(7)(b), S.34, S.34(2), S.37(1)(a), CIVIL PROCEDURE CODE : O.8 R.5, CONTRACT ACT : S.73, INTEREST ACT : S.3, Rajasthan Motor Vehicles Taxation Amendment Act : TOLLS ACT : - This appeal arises out of the allowing the petition under Section 37 of Arbitration and Conciliation Act filed by the State of Rajasthan against the on the ground that the Arbitration Tribunal had travelled beyond its reference by awarding compensation for the loss suffered by the OBT operator of the road for delay in issuing notification restricting entry into Bharathpur Market and also imposing the interest at 18%. While holding that the Tribunal cannot travel beyond its reference, the court gave fallowing directions:- i) What amount could have been recovered by the private appellant for Bharatpur-Deeg part of the road from the vehicles using the road?

       ii) What could be the effect on the contract as a whole for non-executing the work of the second phase?

       The private appellant shall be entitled only for a sum of Rs.26.34 lacs awarded by the tribunal for delay in issuing the notification with 10% interest, if not paid already or it could be adjusted in the final accounts bills. With these observation, the appeals stand disposed of.

       

Judgment :

Dr. B.S. CHAUHAN, J.

1. Both these appeals have been preferred by the rival parties against the judgment and order dated 24.4.2007 passed by the High Court of Rajasthan (Jaipur Bench) in Civil Misc. Appeal No.1581 of 2006 under Section 37(1)(A) of the Arbitration and Conciliation Act, 1996 (hereinafter called “Act 1996”) against the order dated 17.1.2006 passed by the District Judge, Jaipur City, Jaipur in Arbitration Case No.89/2004 whereby the application filed by the State of Rajasthan under Section 34 of the Act 1996 for setting aside the arbitral award dated 1.12.2003 had been allowed.

2. Facts and circumstances giving rise to these appeals are:

A. The Public Works Department of the State of Rajasthan(hereinafter called “PWD”) decided in September 1997 to construct the Bharatpur bye-pass for the road from Bharatpur to Mathura, which passed through a busy market of the city of Bharatpur. For the aforesaid work, tenders were invited with a stipulation that the work would be executed on the basis of Build Operate and Transfer (BOT). The total extent of the road had been 10.850 k.ms. out of which 9.6 k.ms. was new construction and 1.25 k.ms. was improvement, i.e. widening and strengthening of the existing portion of Bharatpur-Deeg Road.

B. After having pre-bid conference/meeting and completing the required formalities it was agreed between the tenderers and PWD that compensation would be worked out on the basis of investment made by the concerned entrepreneur. The tender submitted by MSK-appellant for Rs.1,325 lacs was accepted vide letter dated 5.2.1998 and the MSK-appellant was called upon to furnish security deposit which was done on 25.7.1998. Concession agreement dated 19.8.1998 was entered into between the parties authorising collection of toll fee by MSK-appellant. According to this agreement, period of concession had been 111 months including the period of construction. The said period would end on 6.4.2008. It also contained the provisions for making repayment/collection of toll fee and in case of any difference/dispute to refer the matter to the Arbitrator.

C. MSK-appellant completed the Bharatpur bye-pass Project on 10.4.2000 and also started collection of toll fee as provided under the agreement with effect from 28.4.2000. There had been some problem in collecting the toll fee because of agitation by local people. The State issued Notification dated 1.9.2000 under the provisions of the Indian Tolls Act, 1851 and Rajasthan Motor Vehicles Taxation (Amendment) Act, 1994 (hereinafter called the `Notification dated 1.9.2000') preventing the entry of vehicles into Bharatpur city stipulating its operation with effect from 1.10.2000. MSK-appellant invoked arbitration clause raising the dispute with respect to:

(a) Delay in issuance of Notification prohibiting entry of commercial vehicles into Bharatpur town and diverting traffic through the bye-pass; and

(b) Collection of toll from vehicles using Bharatpur-Deeg patch of the road.

D. The State/PWD failed to make appointment of the Arbitrator. MSK-appellant preferred SB Civil Arbitration Application No.31 of 2002 before the High Court and the High Court vide order 12.4.2002 appointed the Arbitrator. The Arbitrators so appointed in their meeting on 8.5.2002 appointed the third Arbitrator. Claim Petition was filed before the Tribunal by MSK-appellant on 23.9.2002. The State submitted its reply to the claim petition on 7.12.2002.

E. The Arbitral Award was made in favour of MSK-appellant on 1.12.2003 according to which there had been delay on the part of the State of Rajasthan in issuing the Notification and the State failed to implement the same and the contractor was entitled to collect toll fee even from the vehicles using Bharatpur-Deeg part of the road. The State of Rajasthan was directed to pay a sum of Rs.990.52 lacs to MSK-appellant as loss due upto 31.12.2003 with 18% interest from 31.12.2003 onwards. The Tribunal further gave various other directions to the




















































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top