Construction and services contracts often contain termination clauses, and employers sometimes invoke them for what appears to be a relatively minor lapse by the contractor. This raises a practical and important question: a contract permits the employer to terminate the services of the contractor even for a — is the amount of damages awarded by the court in a termination based on a different from that of a termination based on a ? The short answer is yes, generally the measure of damages differs significantly, and the difference can also determine whether the termination itself was lawful.
The Core Distinction: Fundamental Versus
The law draws a clear line between terms of fundamental importance and terms of subsidiary or minor importance in every contract. The Court of Appeal in articulated the principle that where the breached term is fundamental, the innocent party may treat itself as discharged from further obligations, but where the obligation breached is only subsidiary or minor, the innocent party may not treat itself as free of its obligations, although it may sue and recover damages for non-performance of that subsidiary term
RICHALLENGE CORPORATION SDN BHD vs POTECK ENTERPRISE SDN BHD - 2020 MarsdenLR 3220
.This distinction has a striking consequence: a party who terminates a contract in reliance upon the is himself guilty of a breach of contract
RICHALLENGE CORPORATION SDN BHD vs POTECK ENTERPRISE SDN BHD - 2020 MarsdenLR 3220
. In other words, if an employer terminates for a truly when the contract does not validly permit it, the employer — not the contractor — may become the wrongdoer.Damages for a : Loss Flowing From That Breach Alone
Where the breach is minor, the innocent party's remedy is confined to compensation for the loss naturally arising from that specific breach. provides the statutory basis:
When a contract has been broken, the party who suffers by the breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from the breach, or which the parties knew, when they made the contract, to be the likely result from the breach of it.
SPM MEMBRANE SWITCH SDN BHD vs KERAJAAN NEGERI SELANGOR - 2015 MarsdenLR 2499
This means a contractor terminated for a is typically limited to damages for the immediate loss caused by that breach — and if the employer's termination was itself wrongful, the contractor may claim damages for rather than being treated as a defaulting party.
Damages for a : The
A is a different matter entirely. Where a promisor wrongfully repudiates a contract in its entirety, the promisee has a choice: accept the , treat the contract as at an end, and sue for damages. The rationale is that the primary obligation to perform is substituted with the the promisee for the breach
DREAM PROPERTY SDN BHD vs ATLAS HOUSING SDN BHD - 2013 MarsdenLR 2868
. The innocent party may therefore recover damages for the loss of the entire bargain, including and consequential losses flowing from the termination.How Courts Decide Whether a Breach Is Fundamental
The test is a mixed question of fact and law. According to the reasoning in , whether a breach constitutes a depends on the construction of the contract and on all the facts and circumstances of the case. The court must have regard to the character of the breach and determine whether, in consequence of it, the performance of the contract becomes something totally different from that which the contract contemplates
ATTORNEY-GENERAL OF SINGAPORE vs WONG WAI CHENG - 1978 MarsdenLR 377
.Many standard-form construction contracts codify this. For instance, typically allows the Employer to terminate if the Contractor causes a , with listing examples such as , contractor bankruptcy or liquidation, failure to correct notified defects, and corrupt or fraudulent practices in competing for or executing the contract 2017 0 Supreme(Jhk) 196 and 2012 0 Supreme(Pat) 753 and 2020 0 Supreme(Del) 1242. Termination and forfeiture of security deposits and performance guarantees must be legally justified; courts have quashed terminations and ordered refunds with interest where the employer failed to establish the alleged breaches 2012 0 Supreme(Pat) 753.
and Its Costly Consequences
Terminating on the wrong footing carries real financial risk. In a railway contract dispute, the employer's termination was held wrongful, leading to awards for refund of security deposits and encashed performance guarantee amounts 2022 0 Supreme(Ori) 463. Conversely, where a contractor claims , it must actually prove that loss — an arbitral award granting compensation without evidential support has been set aside as perverse, since an award for loss not proved is contrary to the principles of the Contract Act 2021 0 Supreme(Ker) 954.
A Note on Employment Contexts
The same framework applies in employment. requires proof that the employer breached an essential term going to the root of the contract — the unilateral and prolonged withholding of an employee's salary, for example, has been held a serious breach of essential terms
Badlysham Bin Fauzi vs Syarikat Kenderaan Melayu Kelantan Bhd - Industrial Court (2025)
Kalaivani a/p Nadeson vs Siti Healthcare Sdn Bhd - 2024 MarsdenLR 42
. Minor contractual variations, such as changes to office access, generally do not suffice.Key Takeaways
- The measure of damages differs: supports only damages for the loss naturally arising from that breach; opens the door to damages for the , including lost profit.
- Terminating for a can backfire: unless the contract expressly permits it and the clause is enforceable, the terminating party risks being in breach itself.
- Proof matters: any damages award must be supported by evidence of actual loss; unproven loss-of-profit claims may be struck down.
- Draft carefully: parties should define which breaches are fundamental and what remedies attach to each, since contractual termination rights may override the general common law position.