Liability for Transmission Charges During Delay - Generating companies are generally liable to pay transmission charges from the date of deemed COD or actual COD if delayed, unless explicitly excused due to force majeure. Several sources clarify that delays attributable to force majeure events do not automatically exempt the generator from paying transmission charges, especially if the transmission system has achieved COD or is deemed ready ["2023 Supreme(Online)(APTEL) 95"], ["Fatehgarh Bhadla Transmission Company Limited. vs Central Electricity Regulatory Commission & Ors. - Appellate Tribunal for Electricity"], ["2025 Supreme(Online)(CERC) 97"].
Force Majeure and Its Impact - Force majeure events, including natural calamities, land acquisition issues, or contractor delays beyond the control of the parties, are recognized as uncontrollable factors that can justify extension of COD but do not necessarily absolve the generator from transmission charges during the period of delay. For instance, the order states, the delay due to force-majeure events does not exempt the associated upstream/downstream elements from bearing transmission charges for the period of mismatch ["2025 Supreme(Online)(CERC) 225"], ["2025 Supreme(Online)(CERC) 160"], ["2025 Supreme(Online)(CERC) 256"].
Delay Due to Contractor or Agency - Delays caused by contractors, suppliers, or agencies of the generating company or transmission licensee are also considered uncontrollable factors, potentially justifying extensions but not necessarily relieving the generator of liability for transmission charges ["2025 Supreme(Online)(CERC) 160"], ["2025 Supreme(Online)(CERC) 256"].
Specific Regulatory Provisions - Regulations and sharing regulations specify that if the transmission system or associated assets achieve deemed COD and the generator is delayed due to force majeure, the liability to pay transmission charges often remains with the generator until the system is operational or the delay is excused ["2023 Supreme(Online)(APTEL) 95"], ["Fatehgarh Bhadla Transmission Company Limited. vs Central Electricity Regulatory Commission & Ors. - Appellate Tribunal for Electricity"], ["2025 Supreme(Online)(CERC) 97"].
Court and Tribunal Judgments - Judicial orders emphasize that the entity responsible for the delay or the one for whom the asset is developed is liable to pay transmission charges from the date of deemed COD until the asset is operational, even in cases of force majeure, unless explicitly exempted ["Fatehgarh Bhadla Transmission Company Limited. vs Central Electricity Regulatory Commission & Ors. - Appellate Tribunal for Electricity"], ["2023 Supreme(Online)(APTEL) 89"], ["Fatehgarh Bhadla Transmission Company Limited. vs Central Electricity Regulatory Commission & Ors. - Appellate Tribunal for Electricity"].
Analysis and Conclusion:Based on the collected references, generating companies are liable to pay transmission charges during delays caused by force majeure events unless the delay is directly attributable to the transmission system or other uncontrollable factors that have been explicitly recognized as exempting liability. The key principle is that force majeure may extend the COD but does not automatically absolve the generator from paying transmission charges during the period of delay, especially if the transmission system has achieved or is deemed to have achieved COD. The liability ultimately depends on the specific circumstances, contractual provisions, and whether the delay is attributable to the generator, transmission licensee, or external uncontrollable factors.
References:["2023 Supreme(Online)(APTEL) 95"]["Fatehgarh Bhadla Transmission Company Limited. vs Central Electricity Regulatory Commission & Ors. - Appellate Tribunal for Electricity"]["2025 Supreme(Online)(CERC) 97"]["2025 Supreme(Online)(CERC) 225"]["2025 Supreme(Online)(CERC) 160"]["2025 Supreme(Online)(CERC) 256"]["Fatehgarh Bhadla Transmission Company Limited. vs Central Electricity Regulatory Commission & Ors. - Appellate Tribunal for Electricity"]["2023 Supreme(Online)(APTEL) 89"]["Fatehgarh Bhadla Transmission Company Limited. vs Central Electricity Regulatory Commission & Ors. - Appellate Tribunal for Electricity"]