Can a Builder Charge Interest on Delayed Milestone Payments When the Project Itself Is Delayed?

When a Builder Demands Interest on Milestone Payments Despite Its Own Delay in Handing Over Possession

One of the most common flashpoints in Indian real estate is the construction-linked payment plan. The buyer — the allottee — agrees to pay in instalments tied to construction milestones, while the promoter agrees to complete the project and hand over possession by a fixed date. When construction slips and possession is delayed, a familiar question arises: can the promoter claim interest from the allottee for not making payments as per the milestone schedule when the project itself is delayed?

The consistent position emerging from consumer commissions, RERA authorities, and High Courts is that a promoter generally cannot unilaterally demand such interest when the delay in construction is attributable to the developer. The right to interest is not a one-way street running only against the homebuyer.

The Core Principle: The Developer Cannot Profit From Its Own Default

The promoter bears the primary obligation of completing construction and delivering possession within the stipulated timeframe. When the developer fails to meet that obligation, the allottee's entitlement flips: the homebuyer becomes entitled to a refund of the amount paid along with interest and compensation 2019 4 Supreme 174. The burden lies on the developer to explain the steps it took to comply with the contractual timeline, and a purchaser is entitled to compensation once the agreed period for handing over possession — in one case, three and a half years — has expired 2021 6 Supreme 669.

Against this backdrop, clauses that impose interest on allottees for delayed milestone payments while the developer is itself in default of delivering possession are routinely treated as one-sided and unenforceable. A developer cannot benefit from its own failure to complete the project on time 2019 4 Supreme 174 and 2021 6 Supreme 669. Terms that leave the possession date indefinite or at the absolute discretion of the developer suffer from the same infirmity.

How RERA Strengthens the Allottee's Position

The Real Estate (Regulation and Development) Act, 2016 materially changes the balance of power. Section 18 confers an unconditional, absolute statutory right to interest for delayed possession — a right that cannot be defeated by waiver, acquiescence, or the allottee's continued participation in the project 2026 0 Supreme(Bom) 754. Courts have held that this statutory right prevails over general contract law principles, including the notice requirement under Section 55 of the Indian Contract Act, 1872, because the 2016 Act carries an overriding effect 2026 0 Supreme(Bom) 756.

Key implications for delayed projects include:

  • Acceptance of delayed performance does not waive the right to interest. Even if allottees accepted revised timelines or payment schedules communicated by the developer, their statutory entitlement to interest for every month of delay survives 2026 0 Supreme(Bom) 754.
  • Unilateral extensions are not binding. A developer cannot extend deadlines on its own and then rely on those revised dates to escape liability 2026 0 Supreme(Bom) 756.
  • Force majeure has limits. Pandemic-related delays occurring after the original agreed deadline cannot be invoked to escape interest liability where the project was already delayed before such events 2026 0 Supreme(Bom) 756.
  • Offer of possession without a completion certificate is ineffective. Where possession is offered before the completion certificate is obtained, or the certificate's existence is not disclosed, the offer carries little weight

    Complaint No.RAJ-RERA-C-N-2021-4595 Bloom Suppliers Pvt. Ltd. Vs Shivshakti Realhome Pvt. Ltd.

    .

As the courts have put it, when allottees part with their money and the promoter enjoys the benefit of that consideration without delivering possession, it is not unreasonable to require the promoter to pay interest to the allottees whose money it is when the project is delayed beyond the contractual agreed period 2018 0 Supreme(Bom) 1358 and 2017 0 Supreme(Bom) 1982. Under Section 8 of the Maharashtra Ownership Flats Act, 1963, a defaulting promoter may even be liable to refund with simple interest at 9% per annum 2017 0 Supreme(Bom) 1982.

Can the Promoter Pursue Its Own Claim Under RERA?

Interestingly, even where an allottee genuinely defaults on payments, the promoter's remedies under RERA are narrow. RERA does not confer a substantive right on the promoter to claim compensation from allottees, and a complaint for compensation by a promoter before the Adjudicating Officer is generally not maintainable — such claims, if at all, must be pursued before the civil court 2025 0 Supreme(Ker) 206.

That said, exceptions exist. If the developer is not in default of delivering possession, has properly served demand notices, and can demonstrate actual construction progress, it may have a limited right to claim interest on genuinely delayed instalments. But where the project itself is delayed by the developer, this defense typically collapses.

Enforcement Realities: Pre-Deposit and Accountability

Promoters who challenge RERA orders face additional hurdles. Under the proviso to Section 43(5) of RERA, an appeal filed by a promoter requires a mandatory pre-deposit of the interest amount directed by the regulatory authority — even where the liability to pay is deferred until the occupancy certificate is obtained 2024 Supreme(Online)(Bom) 2093 and 2024 0 Supreme(Bom) 289. This requirement exists to prevent promoters from engaging in endless litigation without consequences. Allottees, by contrast, face no pre-deposit requirement when filing appeals 2024 Supreme(Online)(Bom) 2093. Regulatory authorities have also clarified that extensions granted to complete a project do not absolve the promoter of its liability to pay interest for delayed delivery of possession 2022 0 Supreme(P&H) 2243.

Practical Guidance for Allottees and Developers

For allottees facing delayed projects:

  • Document the developer's failure to deliver possession, including the agreed date and any unilateral revised timelines.
  • Assert the right to refund with interest under the Consumer Protection Act and RERA.
  • Remember that staying with the project preserves, rather than forfeits, the statutory right to interest for delayed possession 2026 0 Supreme(Bom) 754.

For developers considering interest claims:

  • First ensure you are not in default of your own obligation to deliver possession.
  • Maintain proof of service of demand notices and actual construction progress.
  • Recognize that one-sided clauses imposing interest only on allottees are vulnerable to being struck down.

Key Takeaways

A promoter generally cannot claim interest from an allottee for missed milestone payments when the project itself is delayed, because the developer's own default in delivering possession takes precedence. Section 18 of RERA guarantees homebuyers an absolute statutory right to interest for delayed possession, unaffected by acceptance of delayed performance or lack of formal notice. One-sided contractual terms that penalize allottees while the builder is in default are typically held unenforceable. Since outcomes depend on the specific agreement, project facts, and forum involved, anyone facing such a dispute should obtain advice tailored to their circumstances.

#RERA #DelayedPossession #HomebuyerRights #RealEstateLaw #InterestOnDelay