IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
R. RAGHUNANDAN RAO, J.
Navyauga Machilipatnam Port Limited – Petitioner
Versus
The State of Andhra Pradesh – Respondent
W.P. No. 12980 of 2019
Decided On : 25-08-2022
Indian Contract Act, 1872 – Section 39, 75 – Respondent pursuance of its intention to develop an all-weather deep-water port at Machilipatnam, Krishna District Infrastructure and Investment Department awarded contract of developing such a port to a consortium of companies. Pursuant to this award Concession Agreement executed – Held, Court is that it would not take any steps for achieving financial closure or undertake any step towards development of Port unless entire extent of land is handed over as a condition precedent stand not in consonance with terms of Concession petitioner has effectively refused to perform its obligation under Concession and has committed repudiatory breach of Concession situation non-adherence to procedure set out in Concession would not vitiate said termination –Writ Petition fails and is accordingly dismissed.
ORDER :
1. The State of Andhra Pradesh, which is the 1st respondent herein, in pursuance of its intention to develop an all weather deep water port at Machilipatnam, Krishna District, vide G.O.Ms. No. 2 Infrastructure and Investment (Ports-I) Department, dated 30.01.2008, awarded the contract of developing such a port to a consortium of companies. Pursuant to this award, a Concession Agreement dated 21.04.2008 was executed. The consortium of companies had incorporated a company by the name M/s. Vajra Sea Port Pvt. Ltd. as a special purpose vehicle to execute the Concession agreement. The name of this company was subsequently changed to M/s. Machilipatnam Port Limited and thereafter, to M/s. Navayuga Machilipatnam Port Limited. The said special purpose vehicle is the writ petitioner in the present writ petition.
2. The petitioner on 28.08.2009 informed 1st respondent that some of its promoters had exited the project and sought permission for inducting another company called Navayuga Engineering Company Pvt., Ltd. as the lead promoter. This request was accepted by the 1st respondent, which issued G.O.Ms. No. 7 dated 15.04.2010, for such a change. After the induction of the new lead promoter, a revised Concession agreement dated 07.06.2010 was executed whereby the petitioner was to develop, build, own, operate and maintain the port at it’s own cost and expense during the Concession period and to transfer the port to the Government of Andhra Pradesh at the end of the concession period. After the induction of the new lead promoter, the name of the petitioner was changed to M/s. Navayuga Machilipatnam Port Limited.
3. Under the revised Concession Agreement (hereinafter referred to as “the Concession”) the petitioner was to implement and construct a Green Field All Weather Deep Water Multi Purpose Port at Machilipatnam, on the land, which was to be given by the 1st respondent on a leasehold basis. The concession envisaged an initial period of construction and development of the port, which was termed as “in-operation period” defined under Clause 1.37 of the Concession and a operation period of 30 years after the in-operation period. The operation period would start from the commercial operation date, which was defined in Clause 1.10 to mean the date on which the petitioner is entitled to commence operation of the Port or part of the Port facilities. The in-operation period or the development period and the milestones for such development are set out in Clause 4.3, which is set out here:
(a) The following major milestones with regard to implementation of the Port Project shall be achieved.
(i) Completion of Detailed Project Report for Port Development by Concessionaire within 6 months from the commencement Date.
(ii) Achievement of Financial Closure by concessionaire within 12 months from the commencement Date.
(iii) Completion of construction of Port Development within 36 months from the Commencement Date.
(iv) Invest the amount agreed as per the detailed proposal for Port Development.
(v) Preparation of plans for future developments whenever that traffic volumes warrant such expansions like addition of berths/terminals and allied port infrastructures.
(b) Starting from the Commencement Date of this Agreement, the Concessionaire shall commence the construction/ implementation, strictly adhering to the Project Development Plan and implementation schedule as given in the Detailed Project Report any variation from the Project Development Plan shall be carried out only with the prior written approval of GoAP.
(c) For non-achievement of the milestones within the specified period as given in Clause (a) (i) to (vi) above the Performance Security in the form of Bank Guarantee shall be encashed. In case of two defaults in succession, GoAP may also consider termination of this Agreement. No prior notice will be given before encashment of Bank Guarantees.
(d) The Performance Security amount will be
Attorney General of Belize vs. Belize Telecom Ltd. (2009) 1 WLR 1988 (PC)
Aligarh Muslim University and Others vs. Mansoor Ali Khan
ABL International Ltd. and Another vs. Export Credit Guarantee Corporation of India Ltd. and Others
Canara Bank and Others vs. Debasis Das and Others
Godhra Electricity Co. Ltd. vs. State of Gujarat
Her Highness Maharani Shantidevi P. Gaikwad vs. Savjibai Haribai Patel and Others
Investors Compensation Scheme Ltd. vs. West Bromwich Building Society
K.L. Tripathi vs. State Bank of India
M.C. Mehta vs. Union of India and Others
M.O.H. Uduman and Others vs. M.O.H. Aslum
Managing Director, ECIL, Hyderabad vs. B. Karunakar
Nabha Power Limited vs. Punjab State Power Corporation Limited and Another
Popatrao Vyankatrao Patil vs. State of Maharashtra and Others
Satya Jain vs. Anis Ahmed Rushdie
State Bank of Patiala vs. S.K. Sharma
Trollope and Colls Ltd. vs. North West Metropolitan Regl. Hospital Board
United India Insurance Co. Ltd. vs. Manubhai Dharmasinhbhai Gajera
The court affirmed that disputes arising from contractual agreements lacking statutory characteristics are to be resolved through arbitration, and the invocation of performance guarantees is valid wh....
The main legal point established in the judgment is the violation of principles of natural justice in the termination of the agreement and invocation of bank guarantees, leading to the court setting ....
A binding agreement requires absolute and unqualified acceptance; silence alone is insufficient. When a contract provides specific machinery for termination and financial consequences, parties cannot....
Since appropriate remedy is available to proceed ahead against the respondent No.3, i.e. Sterling Group and its promoters, and having efficacious remedy, the reliefs prayed for in the petition may no....
The main legal point established in the judgment is that the presence of contingent conditions in a Letter of Acceptance can impact the formation of a concluded contract, and the intention of the par....
A concession period extension under a contract requires compliance with specific procedural conditions, and is not automatic despite recommendations from an independent engineer.
it is clear that generally, the Court should not exercise its writ jurisdiction to enforce the contractual obligation. It is designed to promote justice. The grant or refusal of the writ is at the di....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.