SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Bom) 424

IN THE HIGH COURT OF BOMBAY
P. D. Naik, Manish Pitale, JJ.
Goa Shipyard Limited - Appellant
Versus
Shoft Shipyard Pvt. Ltd. - Respondent
Arbitration Appeal No. 38 of 2024 with Arbitration Appeal No. 37 of 2024 with Arbitration Appeal No. 39 of 2024 with Arbitration Appeal No. 40 of 2024 with Arbitration Appeal No. 41 of 2024 with Arbitration Appeal No. 42 of 2024 with Arbitration Appeal No. 43 of 2024 with Arbitration Appeal No. 44 of 2024 with Commercial Arbitration Appeal No. 3 of 2024 with Commercial Arbitration Appeal No. 4 of 2024 with Commercial Arbitration Appeal No. 5 of 2024 with Commercial Arbitration Appeal No. 6 of 2024 with Commercial Arbitration Appeal No. 7 of 2024
Decided On : 26-04-2024

Advocates appeared:
Mr. Soli Cooper, Senior Advocate a/w. Mr. Surjendu Sankar Das, Ms. Annie Mittal for Appellant (Goa Shipyard Limited).; Mr. Ashwin Shankar a/w. Ms. Ridhi Nyati for Respondent (Shoft Shipyard Private Limited).

The court reaffirmed that it lacks jurisdiction to modify arbitral awards under Section 34 of the Arbitration Act, emphasizing the principle that modifications could only be exercised under Article 142 of the Constitution in exceptional cases.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37 - Appeals filed challenging orders under Section 34 - Issues of delay, limitation, entitlement to set-off, interest on awarded amount discussed - Claimant's objection to arbitration process and appointments noted. (Paras 1, 5-34)

(B) Limitation - Assertion of acknowledgment of debt sufficient to trigger fresh period of limitation - District Court's findings on limitation upheld as not perverse. (Paras 42-44)

(C) Set-Off - Claims of set-off not entailed as counter-claims were not properly presented, leading to rejection of GSL's assertions. (Paras 46-49)

(D) Modification of Awards - Court lacks jurisdiction under Section 34 to modify arbitral awards; previous rulings binding upon District Court's modified awards deemed against law. (Paras 53-60)

Findings of Court:
District Court failed to appropriately apply law concerning modification of awards; findings regarding limitations were adequate and justifiable.

Issues: Key issues include questions of delay in filing appeals, claims of limitation, entitlement to set-off, and appropriateness of interest adjustments.

Ratio Decidendi: Court reiterated adherence to established precedents regarding limitations and set-off claims and clarified that modifications of awards cannot occur outside defined jurisdiction.

Result: GSL's appeals allowed in part; orders set aside; SHOFT's appeals dismissed.

Table of Content
1. overview of arbitration appeals and background. (Para 1 , 2 , 3 , 4)
2. arguments by gsl on limitation and adjustments. (Para 5 , 6 , 7 , 8 , 9 , 10)
3. discussion on issues arising in gsl's appeal. (Para 11 , 12 , 14 , 15)
4. counterarguments from shoft. (Para 13 , 18 , 19)
5. analysis of jurisdiction under section 37. (Para 20 , 21 , 24)
6. court's decision regarding condonation of delay. (Para 23)
7. arguments concerning interest payable. (Para 25 , 26 , 27 , 28)
8. scope of jurisdiction under section 37 discussed. (Para 29 , 30 , 31 , 32)
9. details on applications for condonation of delay. (Para 33 , 34 , 36)
10. observations on limitation issues. (Para 41 , 42 , 43)
11. set-off considerations analyzed. (Para 46 , 47 , 49 , 50)
12. jurisdictional limits on modification of awards. (Para 51 , 52 , 59)
13. court's decision on appeals. (Para 58)

ORDER

Manish Pitale, J. - This is a bunch of thirteen appeals filed under Section 37 of the Arbitration and Conciliation Act, 1996 (Arbitration Act), challenging orders passed by the District Court disposing of applications under Section 34 of the Arbitration Act. While Goa Shipyard Limited (GSL) has filed ten appeals, Shoft Shipyard Private Limited (SHOFT) has filed three appeals. Amongst the ten appeals filed on behalf of GSL, two suffer from delay and hence they are accompanied by applications for condonation of delay.

2. In the light of the submissions made on behalf of the rival parties, various issues arise for consideration. It would be appropriate to first refer to the chronology of events in brief, in order to appreciate the background in which the rival submissions have been advanced.

3. SHOFT is the original claimant in the proceedings initiated under the Arbitration Act. GSL had floated a tender on 05.09.2007 for awarding contracts concerning construction of hull and for installation of machinery. The claimant SHOFT was the successful bidder and workorders were issued in its favour. Subsequently, certain additional works were added, which were also carried out by SHOFT. There were arbitration clauses in the contracts executed between the parties. Since disputes arose between them, SHOFT called upon GSL to refer the disputes to arbitration. The arbitration clauses required the disputes to be referred to the Chairman and Managing Director of GSL, but SHOFT objected to the same. In this situation, in the context of some of the work-orders / contracts, GSL appointed a former Judge of this Court as the sole arbitrator and in respect of other work-orders / contracts, proceedings under Section 11 of the Arbitration Act had to be instituted. This led to appointment of another former Judge of this Court as the sole arbitrator. As a consequence, arbitral awards were rendered by the two former Judges of this Court. Three awards were rendered by the sole arbitrator, Justice A. P. Lavande, former Judge of this Court on 29.09.2017 and two awards were rendered by Justice F. I. Rebello, former Judge of this Court on 17.04.2018.

4. Both GSL and SHOFT filed applications under Section 34 of the Arbitration Act to challenge the said awards. By the impugned orders, the District Court disposed of the applications, leading to filing of the present appeals. As noted hereinabove, two appeals filed by GSL suffer from delay of 1040 days. The original claimant i.e. SHOFT, in the said appeals, has vehemently opposed the applications for condonation of delay and hence, this Court is called upon to decide the aforesaid issue, in addition to the issues arising on merits in the context of the submissions made on behalf of the rival parties.

5. Mr. Soli Cooper, learned senior counsel appearing for the appellant GSL in the ten appeals filed on behalf of GSL submitted that the major issues arising on merits in the present appeals pertain to limitation; the entitlement of GSL for adjustment or set-off while determining the quantum payable to SHOFT, if any; interest payable on the awarded amount; absence of p

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top