IN THE HIGH COURT OF JUDICATURE AT BOMBAY
RAJESH S. PATIL, J.
M/S. Truly Pest Solution Private Limited (Being A MSME) - Petitioner
Versus
Principal Chief Mechanical Engineering (P.C.M.E.) Central Railway - Respondent
Arbitration Petition No.43 of 2023
Decided on : 11-11-2024
JUDGMENT :
Rajesh S. Patil, J
1. The present petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short ‘the Arbitration Act’), by the original claimant seeking to quash and set aside the arbitral award dated 4th February 2022, passed by the sole arbitrator.
FACTS
2. On 5th May 2016, a tender was published by the Divisional Railway Manager (Mechanical), Central Railway, Mumbai (for short ‘Railways’) towards the work of Pest and Rodent Control, in railway passenger coaches maintained at CSTM, WB, MZN, DRT and LDT, Coaching Depots and Rodent Control in Coaching Depots yard and premises. The petitioner participated in the tender process and on 7th June 2016, was declared as the successful bidder. Accordingly, the contract work of the said tender was awarded to the petitioner, for an amount of Rs.1,96,32,255/-. The contract period was for three years i.e. from 30th November 2016 to 29th November 2019.
3. Meanwhile, Government issued Notification on 19th January 2017, by which the rates of minimum wages payable to labourers were increased. Additionally, the railways issued a Joint Procedure Order (for short ‘JPO’) dated 20th December 2017, wherein all the contractors were permitted to foreclose their contracts on the condition that the contractors would continue the ongoing work till the finalisation of a new contract, and the minimum wages would be paid to the labourer till the foreclosure of the contract and no dues financial or otherwise shall be staked by the contractor.
4. The petitioner vide their letter dated February 2018 and a further letter dated January 2019 communicated their intention to withdraw from the contracted work as per the terms of the JPO. The railways accordingly on 8th January 2019 issued a new contract for the balance work and foreclosed the contract with the petitioner.
5. The petitioner claimed an additional manpower expense of Rs.20,91,522/- along with interest from the railways. As the said amount was disputed, the petitioner, on 7th December 2020, issued a legal notice to the railways and invoked Arbitration Clause, thereby calling upon them to pay the differential wages of Rs.20,91,522/- along with interest.
6. Subsequently on 18th December 2020 the petitioner signed and stamped the “Waiver off agreement”, under Section 12(5) of Arbitration Act. The Railways accordingly proceeded further and on 28th April 2021 appointed Shri D. K. Tripathi, Deputy Mechanical Engineer (D), Central Railway, Mumbai, CSMT, to act as a ‘Sole Arbitrator”.
7. The petitioner/claimant, on 8th June 2021, filed their Statement of Claim along with all the relevant annexures with the sole Arbitrator. The Railways being the respondents filed their reply to the statement of claim before the sole Arbitrator.
8. On 1st October 2021, the Railways issued Work Completion Certificate, to the petitioner in respect of the contracted work, mentioning therein that the work completed on 10th January 2019, amounting to Rs.1,29,74,966/-.
9. The proceedings before the Arbitral Tribunal, consisting of Sole Arbitrator went ahead and after hearing both the sides the Sole Arbitrator, on 4th February 2022 passed an Award, thereby dismissing the claim of the petitioner.
10. Being dissatisfied with the dismissal of their claim by impugned Award dated 4th February 2022 the petitioner/claimant have challenged the same by way of present Arbitration Petition, filed under Section 34 of the Arbitration Act.
SUBMISSIONS
11. Mr. Shekhar Jagtap appeared on behalf of the petitioner/claimant and made his submissions.
(i) He submitted that the sole Arbitrator was appointed by the Railways, therefore, under the provisions of Section 12 (5) read with Schedule VII of the Arbitration Act, the award passed by the Sole Arbitrator who was himself de jure ineligible to be an Arbitrator, hence, the Award is void ab initio.
(ii) The Waiver mentioned in the proviso of Section 12(5) of the Arbitration Act is required to be exercised in true letter and spirit
Bharat Broadband Network Limited Versus United Telecom Limited
Ellora Papermills Limited vs. State of Madhya Pradesh
Associate Builders Vs. Delhi Development Authority
Bharat Broadband Network Ltd. vs. United Telecoms Ltd.
JMC Projects (India) Ltd. vs. Indure Private Limited
M/s.Voestalpine Schienen GMBH Vs. Delhi Metro Rail Corporation Ltd.
MMTC Limited v/s. Vedanta Limited
The court upheld the validity of the waiver of objections regarding arbitrator eligibility and affirmed that it does not review arbitral awards on merits, focusing only on public policy and patent il....
Point of law: As per the legal position settled by the Supreme Court in catena of judgments, the High Court has the jurisdiction under Section 11(6) of the said Act to nullify the appointments made b....
The appointment of an arbitrator must comply with the Arbitration and Conciliation Act, particularly Section 12(5), which disqualifies certain individuals from serving as arbitrators.
A unilateral appointment of an arbitrator from an ineligible party is void ab initio without an express written waiver of Section 12(5) of the Arbitration and Conciliation Act, which cannot be implie....
2020 Rules which came into force from the date of their publication in the Official Gazette, i.e. 12.02.2020, cannot be given retrospective effect. The intention of Government of India to make the 20....
Participation in arbitration without objection constitutes a waiver of the right to challenge the appointment of the arbitrator, as per Sections 4 and 12 of the Arbitration and Conciliation Act.
A unilateral appointment of an arbitrator by one party contravenes Section 12(5) of the Arbitration and Conciliation Act, rendering the arbitral award void ab initio and against public policy.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.