IN THE HIGH COURT AT CALCUTTA
Krishna Rao, J.
Steel Authority of India Ltd. –IISCO Steel Plant - Appellant
Vs.
Balaji Industrial Products Ltd. - Respondent
AP 1097 of 2013
Decided On : 08-08-2023
SAIL v. BALAJI INDUSTRIAL PRODUCTS LTD. - ARBITRATION - AWARD - CHALLENGE - GROUNDS - SECTION 34 OF ARBITRATION AND CONCILIATION ACT, 1996 - CONTRACT FOR SALE OF RUN OF MINES (IRON ORE) - NON-DELIVERY OF BALANCE QUANTITY OF FIRST DELIVERY ORDER BY PETITIONER TO RESPONDENT - NON-PAYMENT OF BALANCE AMOUNT WITH RESPECT OF SECOND LOT OF IRON ORE BY RESPONDENT TO PETITIONER - NON-DELIVERY OF BALANCE 30,000 MT OF IRON ORE BY PETITIONER TO RESPONDENT - ARBITRATOR'S AWARD IN FAVOUR OF RESPONDENT - CHALLENGE BY PETITIONER - HELD, AWARD DOES NOT SUFFER FROM ANY PATENT ILLEGALITY OR PERVERSITY - AWARD DOES NOT REQUIRE ANY INTERFERENCE.
Fact of the Case:
Petitioner (SAIL) floated a tender inviting offers for sale of 60,000 Metric Tonnes of Run of Mines (Iron Ore), from the mining face of Ranichua Bench of Gua Ore Mines. The respondent (Balaji Industrial Products Ltd.) participated in the tender process and emerged as the highest bidder. Accordingly, the petitioner issued a Letter of Intent dated 26th February, 2005 to the respondent offering the material at the rate of Rs. 807/- per MT exclusive of excise duty, sale tax and other taxes and duties. On acceptance of the letter of intent, the respondent deposited security deposit of Rs. 24,21,000/- on 16th March, 2005. The contract period was 90 days from the date of issuance of first delivery order. On 16th March, 2005, the first delivery order was issued for lifting 30,000/- MT of materials and the respondent paid an amount of Rs. 2,52,26,760/- towards the value of 30,000/- MT of the Run of Mines (ROM) in advance in terms of the clauses of the contract contained in the terms of conditions. As per the Notice Inviting Tender and the contract entered between the parties, payment for the second instalment of 30,000/- MT of the said material was to be paid within 45 days from the issue of the first delivery order and only on such receipt of second instalment by the petitioner, the second delivery order would be issued to the respondent.
Finding of the Court:
The Court found that the arbitrator's award was well-reasoned and had been passed after considering all the material facts. The Court also found that the award did not suffer from any patent illegality or perversity. Accordingly, the Court dismissed the petition challenging the award.
Issues: 1. Whether the arbitrator's award was well-reasoned and had been passed after considering all the material facts? 2. Whether the award suffered from any patent illegality or perversity?
Ratio Decidendi: 1. The Court held that the arbitrator's award was well-reasoned and had been passed after considering all the material facts. The Court noted that the arbitrator had considered the evidence and materials on record, as well as the pleadings and oral evidence adduced by the parties. The Court also noted that the arbitrator had specifically come to a finding that the total 60,000 MT of Iron Ore was not ready for delivery. 2. The Court held that the award did not suffer from any patent illegality or perversity. The Court noted that the arbitrator had not committed any errors of law or exceeded his jurisdiction. The Court also noted that the award was not based on no evidence or on evidence which did not measure up in quality to a trained legal mind.
Final Decision: The Court dismissed the petition challenging the arbitrator's award.
JUDGMENT :
Krishna Rao, J.
1. The petitioner, Steel Authority of India Limited has filed the present application under Section 34 of the Arbitration and Conciliation Act, 1996 challenging the award passed by the learned sole Arbitrator dated 19th June, 2013 between (Balaji Industrial Products Limited vs. Steel Authority of India).
2. A Tender Notice was published by the Steel Authority of India inviting offers for sale of 60,000 Metric Tonnes of Run of Mines (Iron Ore), from the mining face of Ranichua Bench of Gua Ore Mines. The respondent had participated in the said tender process. The respondent being the highest bidder and as such the petitioner issued a Letter of Intent dated 26th February, 2005 to the respondent offering the material at the rate of Rs. 807/- per MT exclusive of excise duty, sale tax and other taxes and duties.
3. On acceptance of the letter of intent, the respondent has deposited security deposit of Rs. 24,21,000/- on 16th March, 2005. The contract period was 90 days from the date of issuance of first delivery order. On 16th March, 2005, the first delivery order was issued for lifting 30,000/- MT of materials and the respondent has paid an amount of Rs. 2,52,26,760/- towards the value of 30,000/- MT of the Run of Mines (ROM) in advance in terms of the clauses of the contract contained in the terms of conditions.
4. As per the Notice Inviting Tender and the contract entered between the parties, payment for the second instalment of 30,000/- MT of the said material was to be paid within 45 days from the issue of the first delivery order and only on such receipt of second instalment by the petitioner, the second delivery order would be issued to the respondent.
5. The delivery will be by road from Mining face Ranichua Bench of Gua Ore Mines and the petitioner will arrange mechanical loading from the located site to truck/dumper. The delivery of the materials in terms of delivery order issued shall be taken up by the respondent within the stipulated period mentioned in the delivery order.
6. A dispute was cropped up between the parties on the allegation and counter allegation to the effect that the petitioner had the knowledge about the labour unrest at the site of delivery and it would be impossible for the petitioner to give delivery of the materials within the stipulated time to the respondent, suppressing the said fact of labour unrest, the petitioner incorporated the force majeure conditions clause with the object of protecting the petitioner against the loss and damages and the petitioner has not delivered the material of first delivery orders as per schedule and even after extension of time some quantity was undelivered. The further dispute is that the respondent has not paid the balance amount of the balance quantity of the materials within 45 days from the date of receipt of the first delivery order.
7. By an order dated 24th October, 2005, the petitioner had terminated the contract by forfeiting the security deposit and leftover quantity was treated as abandoned goods by applying the provisions of Clause 11 of the special terms and conditions of the contract.
8. Mr. Anindya Mitra, learned Senior Advocate representing the petitioner submitted that as per contract term, if loading or dispatch was affected due to any reason attributable to the petitioner, respondent will get suitable extension of time. He submits that the respondent complained that loading was affected due to labour unrest at the mine site for 71 days and dispatch by breakdown of weighbridge of the petitioner was affected for 5 days. The respondent had applied for extension of time and the petitioner had granted more than 76 days till 29th August, 2005. He submits that the respondent had lifted only 28,435.230 MT and had left 1564.780 MT un-lifted. He submits that the respondent had not applied for further extension for delivery of unlifted item and thus the balance 1564.780 MT of the first lot stood abandoned as per clause 11 of the contract.
Hindustan Zinc Ltd vs. Friends Coal Carbonation
State of Chhattisgarh and Another vs. Sal Udyog Private Limited
Hindustan Zinc Ltd. vs. Friends Coal Carbonisation
Shiji alias Pappu & Ors. vs. Radhika & Anr.
Sikkim Subba Associates vs. State of Sikkim
General Manager, Northern Railway & Anr. vs. Sarvesh Chopra
Ssangyong Engineering and Construction Company Ltd. vs. National Highways Authority of India (NHAI)
Dyna Technologies Pvt. Ltd. vs. Crompton Greaves Ltd.
Associate Builders vs. Delhi Development Authority
State of Andhra Pradesh vs. Associated Engineering Enterprises, Hyderabad
Booz Allen and Hamilton Inc. vs. SBI Home Finance Ltd. Ors.
G. Ramachandra Reddy & Company vs. Union of India & Anr.
Som Datt Builders Limited vs. State of Kerala (2009) 10 SCC 259
Kailash Nath Associates vs. Delhi Development Authority and Another (2015) 4 SCC 136
The court upheld the Arbitrator's findings that the rescission of the contract was unjust and delays were primarily attributable to the petitioner, affirming the award under Section 34 of the Arbitra....
The court emphasized the requirement for the arbitrator to assign reasons in support of the award and the limited scope of interference by the court in arbitration awards.
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
An arbitrator's award may be upheld if it conforms to contract terms, despite challenges regarding procedural compliance or interpretation, provided it does not contravene public policy.
The court affirmed the limited scope of review under Section 34 of the Arbitration and Conciliation Act, emphasizing respect for arbitral awards unless stark violations of public policy or procedural....
The main legal point established in the judgment is the interpretation of contract terms, breach of contract, and the limited scope of interference with the arbitrator's award based on the violation ....
An arbitral tribunal's jurisdiction is limited to the matters that are submitted to it for arbitration and that an arbitrator cannot exceed his or her jurisdiction by deciding matters that are not wi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.