IN THE HIGH COURT OF CHHATTISGARH, BILASPUR
GOUTAM BHADURI, SANJAY S. AGRAWAL, JJ.
The Superintending Engineer, National Highway Circle, Public Works Department - Appellant
Versus
ECI-Keystone (JV) through its Managing Director - Respondent
ARBA No. 51 of 2023
Decided On : 10-06-2024
Arbitration - Delay Condonation - Arbitration and Conciliation Act, 1996 - Section 34 - Section 31(5)
Fact of the Case:
The appellant, a Superintending Engineer, National Highways, filed an application under Section 34 of the Arbitration and Conciliation Act, 1996 seeking condonation of delay in filing the application to set aside an arbitral award. The application was dismissed by the Commercial Court on the ground of limitation.
Finding of the Court:
The Court found that the appellant had received the signed copy of the arbitral award, as evidenced by postal receipts and communications. The Court also noted contradictory statements and a change in the appellant's stand regarding the receipt of the award.
Issues: The main issue was whether the appellant had received the signed copy of the arbitral award, as required under Section 31(5) of the Act, 1996, and whether the delay in filing the application under Section 34 could be condoned.
Ratio Decidendi: The Court held that the appellant had received the signed copy of the arbitral award, based on postal receipts and communications. The Court also emphasized that the limitation period for challenging an arbitral award is strict and cannot be extended beyond the prescribed period.
Final Decision: The Court dismissed the appeal, finding that the impugned order passed by the Commercial Court was just and proper, warranting no interference.
JUDGMENT :
Goutam Bhaduri, J.
1. This appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (henceforth ‘the Act, 1996’) is against the order dated 1-11-2023 (Annexure-A/1) passed by the Judge, Commercial Court (District Level), Naya Raipur, Chhattisgarh, in case No.Arb.MJC 26 of 2023 wherein the application preferred under Section 34 (3) of the Act, 1996 seeking condonation of delay in filing the application under Section 34 was dismissed. The appellant-Superintending Engineer, National Highways is in appeal.
2. (i) The facts involved in this case are that the joint venture company namely; ECI-KEYSTONE was entered into a contract agreement for construction of two lane road at certain different distances from Bhopalapatnam to Jagdalpur under the LWE scheme. The contract price was Rs.184,54,47,686.69. Admittedly, the extension was granted to the respondent up till 30-6-2019. During the course of execution of the contract, certain dispute arose between the parties which led to appointment of the Arbitrator as per clause 25.3 (a) of the contract. The respondent invoked the arbitration clause under special condition of contract. The appellant Department also acceded to such appointment, consequently, the Sole Arbitrator was appointed. Subsequently, the Department was advised by the Ministry of Road that since high stakes were involved in the project, therefore, in accordance with the provisions of clause 25.3 the arbitration should be conducted by a panel of three Arbitrators. Consequently, an application was moved and initial consent though was withdrawn by the Department on 16-8-2021, but the proceeding by the time conducted before the Sole Arbitrator and the award was passed on 2-9-2022 (Annexure - A/2).
(ii) The said arbitral award was assailed by the appellant before the Commercial Court (District Level), Naya Raipur, Chhattisgarh, by filing an application under Section 34 of the Act, 1996 along with the application under Section 36 (3) for grant of stay and application under Section 34 (3) for condonation of delay with a prayer to set aside the award on the ground that the appellant was not permitted to present the case and the prayer was made to set aside the ex parte award.
(iii) According to the appellant, the arbitral award was not signed and received by the appellant and only received a photocopy of the award lately. The date wise events are that :
- thereafter, the demand was raised for supply of signed copy of the award on 11-3-2023;
- on 14-3-2023 reply was sent by the Sole Arbitrator stating that he has already sent the award to the appellant;
- the Superintending Engineer by letter dated 17-3-2023 informed that no entry has been made in the office register regarding receipt of award;
- thereafter, on 20-3-2023 the legal opinion was sought by the Superintending Engineer from the office of the Advocate General;
- on 23-3-2023 legal opinion was sent;
- thereafter, on 24-3-2023 again a letter was sent by the Superintending Engineer to the Sole Arbitrator to send signed copy of the award;
- in reply to it on 25-3-2023 the Sole Arbitrator replied that the award has been sent by registered post;
- subsequently, on 27-4-2023 the Superintending Engineer wrote a letter to the Chief Engineer seeking departmental enquiry against the erring Clerk;
- a complaint was made to the police on 27-4-2023;
-again a letter dated 24-5-2023 was sent by the Superintending Engineer to the Sole Arbitrator and requested for signed copy of the award; and
- thereafter, the appeal was filed.
(iv) Learned Commercial Court observed that since the award was passed on 2-9-2022 and the application to set aside the same was preferred on 27-5-2023 after nine months, the application was barred by time and accordingly dismissed the same by the order impugned. Thus, this appeal.
3. (a) Learned Advocate General appearing for the appellant would submit that as per Section 31(5
Aktiebolaget Volvo v. R. Venkata Chalam
Prithi Chand v. State of Himachal Pradesh
State of Maharashtra and others v ARK Builders Private Limited
Union of India v TECCO Trichy Engineers & Contractors
Dakshin Haryana Bijli Vitran Nigam Limited v Navigant Technologies Private Limited
Union of India v Varindera Constructions Limited
D. Vinod Shivappa v Nanda Belliappa
Ajeet Seeds Limited v K. Gopala Krishnaiah
The limitation period for challenging an arbitral award under Sections 31(5) and 34(3) of the Arbitration Act begins upon receipt of a signed copy, making timely receipt crucial for valid appeals.
Effective service of an arbitral award must be made directly to the parties involved; service on an employee does not suffice to commence the limitation period.
The necessity of delivering a signed copy of the arbitral award to each party to begin the running of the limitation period under Section 34 of the A&C Act.
Arbitral Award – Limitation – S. 34(3) specifically states that an application for setting aside may not be made after three months have lapsed from date of which party making an application had rece....
The court established that non-compliance with the mandatory delivery of the arbitral award affects the limitation period for filing an application to set aside the award.
The issue of stamping and executability of an Award should be determined at the execution stage, not under section 34 of the Arbitration and Conciliation Act, 1996.
The reckoning point for limitation under the Arbitration and Conciliation Act begins only upon the party receiving the signed copy of the arbitral award, not merely upon its delivery to an advocate.
The delivery of the signed copy of the arbitral award to the party is a crucial stage in the arbitral proceedings, and the limitation period for filing objections commences only from the date of such....
The court confirmed that compliance with service requirements for an arbitral award can be established through proper postal dispatch and delivery confirmation under Section 31(5) of the Arbitration ....
(1) Petition against arbitral award – Commencement of period of limitation – Period of limitation prescribed for filing objections would commence only from date when signed copy of award is delivered....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.