IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
ANIL KSHETARPAL, J.
Parsvnath Developers Ltd. - Appellant
Versus
M/s Wisecan Engineering Pvt. Ltd. And another - Respondents
FAO-150-2021(O&M)
Decided on : 01-04-2021
A&C Act - Arbitration - MSMED Act 2006 - Section 18, 19, 34 - The court discussed the requirements of Section 31(5) of the A&C Act, emphasizing the necessity of delivering a signed copy of the arbitral award to each party to begin the running of the limitation period under Section 34. The court highlighted the importance of compliance with statutory provisions and the need for sensitivity to time in arbitration proceedings. The judgment also referenced relevant case law to support its interpretation of the legal provisions.
Fact of the Case:
The appellant filed a petition seeking condonation of delay in filing a petition under Section 34 of the A&C Act, asserting that the copy of the award was received after the original period of three months from the date of the award. The court found that the delay in filing the petition could be condoned and directed the lower court to decide the objection petition under Section 34 within two months.
Finding of the Court:
The court found that the delay in filing the petition could be condoned and directed the lower court to decide the objection petition under Section 34 within two months.
Issues: The issues included the delivery of a signed copy of the arbitral award, the condonation of delay in filing the petition under Section 34, and the sensitivity to time in arbitration proceedings.
Ratio Decidendi: The court emphasized the necessity of delivering a signed copy of the arbitral award to each party to begin the running of the limitation period under Section 34. It also highlighted the importance of compliance with statutory provisions and the need for sensitivity to time in arbitration proceedings.
Final Decision: The delay in filing the petition was condoned, and the lower court was directed to decide the objection petition under Section 34 within two months.
JUDGMENT :
ANIL KSHETARPAL, J.
1. Through this appeal filed under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘A&C Act’), the appellant assails the correctness of the order dated 12.11.2020 passed by the learned Additional District Judge while dismissing the application seeking condonation of delay in filing the petition u/s 34 of A& C Act.
The Facts:-
2. Some skeleton facts are required to be noticed. In this case, the sole Arbitrator commenced the proceedings under A&C Act in view of a reference made by the Micro and Small Enterprises Facilitation Council,(hereinafter referred to as 'the Council) in exercise of the powers conferred under Section 18 of the Micro Small and Medium Enterprises Development Act, 2006 (hereinafter referred to as the ‘MSMED Act 2006’) The Arbitrator, after reserving on 24.09.2018, pronounced the award on 27.09.2018. A photocopy of the award is available on the record requisitioned from the Court. On careful perusal thereof, it becomes apparent that a copy of the award was received by one person on 29.09.2018. Learned counsel representing the respondent submits that he has received a copy of the award. There is no endorsement either by the Arbitrator or by his Secretariat that a copy of the award has been received by the appellant or dispatched to the appellant.
3. In the petition filed by the appellant under Section 19 of MSMED Act, 2006 read with Section 34 of A&C Act on 18.04.2019, it was asserted that the copy of the award has been received on 19.12.2018. Apart therefrom, an application seeking condonation of delay of 30 days was also filed.
4. No reply to the application for condonation of delay was filed by the respondent, although, the proceedings remained pending before the learned Additional District Judge for a period of more than 1 year and 6 months. The Court held that since it was filed beyond the period of 30 days, after elapse of original period of three months from the date of award, therefore, the delay in filing the petition cannot be condoned.
5. It is important to note that pending proceedings before Additional District Judge, an application for summoning the record of the Arbitrator was filed by the appellant, however, it was kept pending. On the other hand, the respondent filed an application under Section 19 of the MSMED Act, 2006, before the learned Additional District Judge. Yet another application for release of the amount deposited and advancement of the date of hearing was also filed by the respondent. The respondent in support of his oral plea, produced a copy of a receipt issued by the Indian Posts alongwith a print out of the tracking details of the consignment in order to prove that the copy of the award was delivered to the appellant.
The Reasons for dismissal by the Court below:-
6. On careful perusal of the order passed by the learned Additional District Judge, it is apparent that the application for condonation of delay was dismissed on the following grounds:-
(ii) Learned counsel representing the respondent has stated at Bar that since he belongs to Panipat, therefore, he had sent a copy of the award to the appellant by speed post and from the receipt and tracking consignment details, it is proved that the item was delivered to appellant on 12.10.2018.
(iii) The appellant has pleaded that after a period of two months from the day when the Learned Arbitrator reserved its award, they enquired from the sole Arbitrator who informed them that the award has already been pronounced on 27.09.2018. The Court has observed that the only source to obtain the copy of the award was from the Council but photocopy of the award attached with the petition u/s 34 A & C Act does not show that it was issued by the council.
7. On these grounds the court has held that since the petition under Section 19 of the MSMED Act,
Banarsi Krishan Committee and Ors vs. Karamyogi Settlers Pvt. Ltd. (2012) 9 SCC 496
Karmyogi Shelters (P) Ltd. v. Benarsi Krishna Committee
State of Maharashtra and others vs. ARK Builders Pvt. Ltd. (2011) 4 SCC 616
Union of India vs. Tecco Trichy Engineers and Contractors (2005) 4 SCC 239
The necessity of delivering a signed copy of the arbitral award to each party to begin the running of the limitation period under Section 34 of the A&C Act.
The limitation period for challenging an arbitral award under Section 34 of the Arbitration & Conciliation Act, 1996, commences only from the date the aggrieved party receives a signed copy of the aw....
The limitation period for challenging an arbitral award under Sections 31(5) and 34(3) of the Arbitration Act begins upon receipt of a signed copy, making timely receipt crucial for valid appeals.
The main legal point established in the judgment is that the receipt of a signed copy of an arbitral award, as required under Section 31(5) of the Arbitration and Conciliation Act, 1996, triggers the....
The delivery of the signed copy of the arbitral award to the party is a crucial stage in the arbitral proceedings, and the limitation period for filing objections commences only from the date of such....
Effective service of an arbitral award must be made directly to the parties involved; service on an employee does not suffice to commence the limitation period.
The court ruled that statutory timelines under the Arbitration and Conciliation Act are strict and failure to properly file within these limits results in dismissal as barred by limitation.
The court established that non-compliance with the mandatory delivery of the arbitral award affects the limitation period for filing an application to set aside the award.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.