IN THE HIGH COURT OF DELHI AT NEW DELHI
Chandra Dhari Singh, J.
Delhi State Industrial And Infrastructure – Appellant
Versus
M/s Bawana Infra Development Pvt. Ltd. – Respondent
O.M.P. (COMM) 6 of 2019 and I.A. No. 179 of 2019
Decided On : 16-03-2023
| Table of Content |
|---|
| 1. factual background of arbitration dispute. (Para 2 , 3 , 4 , 5 , 6) |
| 2. petitioner's arguments against the award. (Para 10 , 11 , 12 , 13 , 14 , 15 , 20) |
| 3. respondent's defense of the award. (Para 23 , 24 , 26 , 28 , 30) |
| 4. court's observations on the award's validity. (Para 32 , 33 , 34 , 35 , 36) |
| 5. court's conclusion on setting aside part of the award. (Para 64 , 70 , 106 , 110) |
JUDGMENT
Chandra Dhari Singh, J.
1. The instant petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as "the Act") has been filed on behalf of petitioner seeking the following reliefs:
"It is, therefore, most respectfully prayed that this Hon'ble Court may graciously be pleased to set-aside award with respect to Claim No.1, 2, 5, 9 and 12.
Any other order or relief as this Hon'ble Court deems fit and proper may be passed in the facts and circumstances of the present case."
FACTUAL MATRIX
2. The petition is filed against the impugned Award dated 12th September 2018 passed by Justice R.C. Jain (Retd.), the learned Sole Arbitrator. The Arbitration proceeding in the current matter arose out of Concessionaire Agreement dated 20.07.2011 with respect to the re- development, operation, and maintenance of the 'Bawana Industrial Area' (hereinafter referred to as the 'Project Area') situated in Delhi.
3. The facts necessary for the disposal of this instant petition are that the petitioner is DSIIDC, a Government Company incorporated under the Companies Act, 1956. The petitioner circulated a tender inviting bid from interested parties on a Public Private Partnership modality. After rejecting multiple bids, Abhudaya Housing and Constructions Pvt. Ltd. and Jyoti Buildtech Pvt. Limited (hereinafter collectively referred to as the 'Selected Bidder') were awarded the Contract. The Respondent Company was established as a special-purpose vehicle for the furtherance of the same.
4. According to the Agreement, the respondent (Concessionaire) was required to re-develop, construct, operate and maintain the Project Area for fifteen years. The first two years of this period were earmarked for the construction of mandatory capital projects, whereas the remaining thirteen years were reserved for maintaining and operating the Project Area. The date set for the completion of Material Project Facilities was 15th December 2013.
5. On 14th December 2013, there was a request by the respondent for the completion certificate. However, the third party issued a provisional certificate to the respondent instead of the petitioner. The petitioner further did not issue it to the respondent claiming their incomplete work. It is alleged by the petitioner that the respondent tried to obtain the completion certificate from the third party without completing the consignment. They further alleged that it was a mischievous act on the part of the respondent to possess a provisional certificate that was not issued by the third-party engineer to the respondent.
6. On the contrary, the respondent vehemently denied the allegations of the petitioner, and claimed that the work was complete, and they had received the certificate legitimately form the third-party engineer.
7. The respondent raised claims for payment due to them, the onus of the payment of which was on the respondent, as alleged by the petitioner.
8. The dispute reached to this Court requesting the appointment of an Arbitrator. This Court appointed Justice R.C. Jain (Retd.) as the learned Sole Arbitrator to adjudicate upon the matter vide order dated 24th August 2016 passed in Arbitration Petition No. 420/2016 titled "Bawana Infra Development Pvt. Ltd. V/s DSIIDC".
9. The learned Arbitral Tribunal was pleased to make and publish the impugned Award on 12th September 2018. The petitioner being aggrieved of the impugned Award filed the instant petition.
SUBMISSIONS
(On behalf of the petitioner)
10. Learned counsel appearing on behalf of the petitioner, in support of the instant pet
MSK Projects Ltd v State of Rajasthan
ONGC Ltd. V. Saw Pipes Ltd. [(2003) 5 SCC 705 : AIR 2003 SC 2629
Rajasthan State Mines and Minerals Limited v. Eastern Engineering Enterprises and Another
Ssangyong Engineering & Construction Co. Ltd. v. NHAI
State of Haryana v. S.L. Arora & Co.
Union of India vs. D. Khosla and Company
Vedanta Ltd. v. Shenzhen Shandong Nuclear Power Construction Co. Ltd.
Associate Engineering Company v. Govt. of Andhra Pradesh and others
Champsey Bhara Company vs. The Jivraj Balloo Spinning and Weaving Company Ltd.
Associate Builders vs. Delhi Development Authority
Hindustan Zinc Ltd. v. Friends Coal Carbonisation
Indian Oil Corpn. Ltd. v. Shree Ganesh Petroleum
J.G. Engineers (P) Ltd. v. Union of India
Morgan Securities and Credits Pvt. Ltd. v Videocon Industries Ltd.
The Court held that the impugned award with respect to Claim 7 was not well-reasoned as required by the Act under Section 31(3), and the impugned award with respect to the award in Claim 11 is contra....
The Court held that the learned Arbitrator had erred in decreeing the award with respect to the rate of interest, and hence, the Award qua issue no. 20 with regards to the rate of interest is liable ....
The main legal point established in the judgment is the limited scope for interference with arbitral awards under the Arbitration and Conciliation Act, 1996, and the discretion of the Arbitrator in a....
Limited grounds for interference with an Arbitral Award under Section 34 of the Arbitration Act
Section 31(7)(a) of Act deals with grant of pre-award interest.
The limited scope of intervention by Courts in arbitral awards under Section 34 of the Arbitration and Conciliation Act, emphasizing the need to satisfy specific grounds for setting aside an arbitral....
Employees are entitled to wage arrears from 01.01.1997 despite a Presidential Directive limiting payments, as the directive was deemed unjustified by the Tribunal.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.