IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, Amit Mahajan, JJ.
Nabinagar Power Generating Company Ltd. – Appellant
Versus
Amr India Ltd. – Respondent
FAO(OS) (COMM) 196 of 2019 & CM APPL. 37019 of 2019
Decided On : 20-03-2023
Arbitration and Conciliation Act - NPGC's Challenge to Impugned Award - Section 34 - Section 37 - [Section 34, Section 37] - The court upheld the view of the learned Single Judge that the interpretation of the Arbitral Tribunal of Clause 33.3.0 of the Special Conditions of the Contract was a plausible interpretation and therefore, could not be interfered with in proceedings under Section 34 of the A&C Act.
Fact of the Case:
The disputes arose from a contract for 'Site Levelling and Infrastructure Package for Nabinagar Super Thermal Power Project (3 X 660 MW)' dated 04.07.2011. NPGC terminated the contract and awarded the balance works to other parties. AIL invoked the arbitration agreement on 29.03.2014. NPGC filed its counter-claims on 18.09.2017.
Finding of the Court:
The court found that NPGC's counter-claims were barred by limitation as they were filed after three years had elapsed from the date on which the cause of action for the claims had arisen.
Issues: The main issue was whether NPGC's counter-claims were barred by limitation.
Ratio Decidendi: The court held that the counter-claims were filed after the stipulated time had elapsed from the date on which the cause of action for the claims had arisen, and therefore, were barred by limitation.
Final Decision: The court dismissed NPGC's challenge to the impugned award, upholding the rejection of NPGC's counter-claims as barred by limitation.
JUDGMENT
Vibhu Bakhru, J. The appellant (hereafter `NPGC') has filed this intra-court appeal under Section 37(1) of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act') impugning an order dated 05.07.2019 passed by the learned Single Judge of this Court (hereafter `the impugned order'), whereby the learned Single Judge dismissed NPGC's application under Section 34 of the A&C Act to set aside the arbitral award dated 10.12.2018 (hereafter `the impugned award').
2. The arbitral proceedings were commenced pursuant to the notice dated 29.03.2014, issued by the respondent (hereafter `AIL') seeking reference of the disputes to arbitration. The Arbitral Tribunal substantially allowed most of the claims made by the respondent and rejected the counter-claims raised by NPGC. NPGC had assailed the impugned award by filing an application under Section 34 of the A&C Act [being OMP (COMM.) 248/2019]. The said application was rejected by the learned Single Judge in terms of the impugned order. The learned Single Judge did not find that the arbitral award was vitiated by patent illegality or was in conflict with the public policy of India. The learned Single Judge also held that the impugned award rested on the findings of facts rendered after appreciation of evidence, and such findings were not amenable to challenge under Section 34 of the A&C Act.
3. The present appeal was listed for the first time before a Co-ordinate Bench of this Court on 20.08.2019 and thereafter on 26.09.2019. After briefly hearing the counsel for NPGC at the said hearing, the Court held that the question regarding the interpretation of clauses of the contract were within the exclusive domain of the Arbitral Tribunal and it was not open for the Court, either under Section 34 or under Section 37 of the A&C Act, to act as the first or second appellate court and re-examine the import and effect of the contractual clauses. The Court held that if the Arbitral Tribunal's interpretation of contractual clauses was a plausible interpretation, the same could not be interfered with. The Court referred to the decision of the Supreme Court in Ssangyong Engineering and Construction Company Limited v. National Highways Authority of India (NHAI), (2019) 15 SCC 131 and on the strength of the said decision, upheld the view of the learned Single Judge to the effect that the interpretation of the Arbitral Tribunal of Clause 33.3.0 of the Special Conditions of the Contract was a plausible interpretation and therefore, could not be interfered with in proceedings under Section 34 of the A&C Act.
4. Thus, by an order dated 26.09.2019, NPGC's challenge of the impugned award, inasmuch as it had declined to interfere with the decision of the Arbitral Tribunal to award certain claims raised by AIL, was rejected; the notice in this appeal was confined to NPGC's plea that the Arbitral Tribunal had erroneously rejected its counter-claims as barred by limitation.
5. This Court is informed that NPGC has preferred a Special Leave Petition impugning the order dated 26.09.2019 passed by the Coordinate Bench of this Court, rejecting NPGC's challenge to the impugned award and the impugned order insofar as AIL's claims are concerned.
6. It is agreed that, the only question that requires to be considered by this Court is whether the impugned award, to the extent that it rejects NPGC's counter-claims as barred by limitation, is patently illegal or is it in conflict with the fundamental policy of the Indian law.
Factual Context
7. Briefly stated, the relevant facts necessary to address the aforesaid controversy are as under:
7.1. The disputes between the parties arose in connection with the agreement for "Site Levelling and Infrastructure Package for Nabinagar Super Thermal Power Project (3 X 660 MW)" dated 04.07.2011. AIL had submitted its bid for the said contract pursuant to the notice inviting tender issued by NPGC. AIL's bid was accepted and the same was communicated by NPGC to AIL by
Geo Miller and Company Private Limited v. Chairman, Rajasthan Vidyut Utpadan Nigam Limited
Major (Retd.) Inder Singh Rekhi v. Delhi Development Authority
The main legal point established in the judgment is that counter-claims must be filed within the stipulated time from the date on which the cause of action for the claims had arisen, and failure to d....
Execution of the works was delayed and the respondent sought Extension of Time for completion of the works on successive occasions, which were approved by NHAI.
The main legal point established in the judgment is the application of limitation principles under the Arbitration and Conciliation Act to determine the timeliness of the counter claim and the reject....
The right to file a counter-claim exists independent of any liberty granted by the Arbitral Tribunal, and an interim award is susceptible to challenge under Section 34 of the 1996 Act.
Article 113 of the Limitation Act reads as Any suit for which no period of limitation is provided elsewhere in the Schedule, the period of limitation is three years and the time begins to run when th....
The court affirmed that claims for breach of contract are subject to statutory limitation periods, which cannot be extended by claims of continuing breaches.
The limitation period for arbitration claims commences from the date of the Cure Notice, and claims not filed within three years are barred, affirming the arbitrator's findings.
The right to file counter-claims in arbitration is independent of previous permissions, and decisions rejecting such claims qualify as interim awards subject to challenge under Section 34 of the Arbi....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.