SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Del) 963

IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, Amit Mahajan, JJ.
Nabinagar Power Generating Company Ltd. – Appellant
Versus
Amr India Ltd. – Respondent
FAO(OS) (COMM) 196 of 2019 & CM APPL. 37019 of 2019
Decided On : 20-03-2023

Advocates appeared:
Ms. Manvinder Acharya, Senior Adv with Mr. R. Sudhinder, Mr. Dattatray Vyas and Mr. Akshay Singh Sengar, Advocates, for the Appellant.
Mr. Brijesh Kumar Goel, Mr. Rajeev Kumar, Mr. Sajal Goel and Ms. Rashmi Bhardwaj, Advocates, for the Respondent.

The main legal point established in the judgment is that counter-claims must be filed within the stipulated time from the date on which the cause of action for the claims had arisen, and failure to do so bars the remedy before the Arbitral Tribunal.

Headnote:

Arbitration and Conciliation Act - NPGC's Challenge to Impugned Award - Section 34 - Section 37 - [Section 34, Section 37] - The court upheld the view of the learned Single Judge that the interpretation of the Arbitral Tribunal of Clause 33.3.0 of the Special Conditions of the Contract was a plausible interpretation and therefore, could not be interfered with in proceedings under Section 34 of the A&C Act.

Fact of the Case:

The disputes arose from a contract for 'Site Levelling and Infrastructure Package for Nabinagar Super Thermal Power Project (3 X 660 MW)' dated 04.07.2011. NPGC terminated the contract and awarded the balance works to other parties. AIL invoked the arbitration agreement on 29.03.2014. NPGC filed its counter-claims on 18.09.2017.

Finding of the Court:

The court found that NPGC's counter-claims were barred by limitation as they were filed after three years had elapsed from the date on which the cause of action for the claims had arisen.

Issues: The main issue was whether NPGC's counter-claims were barred by limitation.

Ratio Decidendi: The court held that the counter-claims were filed after the stipulated time had elapsed from the date on which the cause of action for the claims had arisen, and therefore, were barred by limitation.

Final Decision: The court dismissed NPGC's challenge to the impugned award, upholding the rejection of NPGC's counter-claims as barred by limitation.

JUDGMENT

Vibhu Bakhru, J. The appellant (hereafter `NPGC') has filed this intra-court appeal under Section 37(1) of the Arbitration and Conciliation Act, 1996 (hereafter `the A&C Act') impugning an order dated 05.07.2019 passed by the learned Single Judge of this Court (hereafter `the impugned order'), whereby the learned Single Judge dismissed NPGC's application under Section 34 of the A&C Act to set aside the arbitral award dated 10.12.2018 (hereafter `the impugned award').

2. The arbitral proceedings were commenced pursuant to the notice dated 29.03.2014, issued by the respondent (hereafter `AIL') seeking reference of the disputes to arbitration. The Arbitral Tribunal substantially allowed most of the claims made by the respondent and rejected the counter-claims raised by NPGC. NPGC had assailed the impugned award by filing an application under Section 34 of the A&C Act [being OMP (COMM.) 248/2019]. The said application was rejected by the learned Single Judge in terms of the impugned order. The learned Single Judge did not find that the arbitral award was vitiated by patent illegality or was in conflict with the public policy of India. The learned Single Judge also held that the impugned award rested on the findings of facts rendered after appreciation of evidence, and such findings were not amenable to challenge under Section 34 of the A&C Act.

3. The present appeal was listed for the first time before a Co-ordinate Bench of this Court on 20.08.2019 and thereafter on 26.09.2019. After briefly hearing the counsel for NPGC at the said hearing, the Court held that the question regarding the interpretation of clauses of the contract were within the exclusive domain of the Arbitral Tribunal and it was not open for the Court, either under Section 34 or under Section 37 of the A&C Act, to act as the first or second appellate court and re-examine the import and effect of the contractual clauses. The Court held that if the Arbitral Tribunal's interpretation of contractual clauses was a plausible interpretation, the same could not be interfered with. The Court referred to the decision of the Supreme Court in Ssangyong Engineering and Construction Company Limited v. National Highways Authority of India (NHAI), (2019) 15 SCC 131 and on the strength of the said decision, upheld the view of the learned Single Judge to the effect that the interpretation of the Arbitral Tribunal of Clause 33.3.0 of the Special Conditions of the Contract was a plausible interpretation and therefore, could not be interfered with in proceedings under Section 34 of the A&C Act.

4. Thus, by an order dated 26.09.2019, NPGC's challenge of the impugned award, inasmuch as it had declined to interfere with the decision of the Arbitral Tribunal to award certain claims raised by AIL, was rejected; the notice in this appeal was confined to NPGC's plea that the Arbitral Tribunal had erroneously rejected its counter-claims as barred by limitation.

5. This Court is informed that NPGC has preferred a Special Leave Petition impugning the order dated 26.09.2019 passed by the Coordinate Bench of this Court, rejecting NPGC's challenge to the impugned award and the impugned order insofar as AIL's claims are concerned.

6. It is agreed that, the only question that requires to be considered by this Court is whether the impugned award, to the extent that it rejects NPGC's counter-claims as barred by limitation, is patently illegal or is it in conflict with the fundamental policy of the Indian law.

Factual Context

7. Briefly stated, the relevant facts necessary to address the aforesaid controversy are as under:

7.1. The disputes between the parties arose in connection with the agreement for "Site Levelling and Infrastructure Package for Nabinagar Super Thermal Power Project (3 X 660 MW)" dated 04.07.2011. AIL had submitted its bid for the said contract pursuant to the notice inviting tender issued by NPGC. AIL's bid was accepted and the same was communicated by NPGC to AIL by

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top