SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Raj) 134

IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR
SANJEEV PRAKASH SHARMA, ACJ, SANGEETA SHARMA, J.
M/s Anamika Conductors Private Limited – Appellant
Versus
Se (Mm) Ajmer Vidyut Vitran Nigam Limited – Respondent
D.B. Civil Miscellaneous Appeal Nos. 4842, 4843 of 2025
Decided On : 20-01-2026

Advocates Appeared:
For the Appellant : Amol Vyas

Limitations under Section 34(3) of the Arbitration and Conciliation Act are strict, and additional proceedings or negotiations do not extend the prescribed three-month period for filing objections.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34(3) - Limitation for filing objections - Objections raised beyond three-month period found ineligible - Period between decision of Council and Settlement Committee not excluded for limitation calculation - Three months + one month extension not applicable in case of independent proceedings. (Paras 2, 4, 5, 11, 15)

(B) Micro, Small and Medium Enterprises Development Act, 2006 - Section 18 - Application for claims regarding interest - Supplier's claim for compound interest rejected; allowed simple interest determined by Settlement Committee - Independent nature of decision-making noted. (Paras 3, 11)

Facts of the case:
The appeals arise from the rejection of objections to an arbitration award by the Commercial Court, dealing with the limitation period for filing under Section 34 of the Arbitration Act. Previous proceedings under the MSMED Act were noted, with a decision on interest made by the Settlement Committee after the Council closed the case.

Findings of Court:
The objections against the arbitration award were dismissed as not being raised within the prescribed limitation period under Section 34(3).

Issues: The primary issue was whether the period during which the arbitration proceedings were pending should be excluded for calculating limitation under the Arbitration Act.

Ratio Decidendi: The court held that the limitation period under Section 34(3) is strict and cannot be extended based on independent proceedings or discussions, emphasizing that the objections to the arbitration award were not timely filed.

Result: Appeals dismissed.

Table of Content
1. timeline of arbitration dispute and procedural closure. (Para 2 , 3 , 4)
2. contention on limitation considering delays. (Para 5 , 6)
3. clarification on section 34(3) enforcement. (Para 8 , 9)
4. negation of argument on dies non applicability. (Para 10 , 11)
5. rejection of reliance on previous judgments. (Para 12 , 13 , 14)
6. final dismissal of appeals. (Para 15 , 16)

JUDGMENT :

1. Heard.

2. In both the appeals, the challenge is to the judgment passed by the learned Commercial Court-II, Jaipur Metro-II, whereby the objections raised under Section 34 of the Arbitration and Conciliation Act, 1996 (for short ‘the Act of 1996’), were rejected by the learned Commercial Court on the ground that the same had been raised beyond period of limitation, as provided for filing objections in terms of Section 34(3) of the Act of 1996.

3. Brief facts which have come up before us are that the appellant had initially raised a dispute and in terms of Section 18 of the Micro, Small and Medium Enterprises Development Act, 2006 (for short ‘MSMED Act’) preferred an application before the Micro, Small and Medium Enterprises Facilitation Council, Jaipur (for short ‘Council’) claiming compound interest. The Council vide its order dated 10.05.2022, noticed that in terms of the contract, there was a provision of raising a dispute before the Settlement Committee of the Ajmer Vidyut Vitran Nigam Limited in terms of the conditions of tender. It is further observed that the claim had been directly put up before the Council. Thereafter, it proceeded to examine the claim on merits and reached to the conclusion that there had been no violation of Section 15 of the MSMED Act by the respondent-purchaser and, therefore, the claim of three times compound interest on the ground of delay of one month was not acceptable. Having reached to that conclusion, the Council closed the case unanimously. It however, further proceeded to observe that the supplier could further raise its claim relating to interest before the Settlement Committee, which would examine the case separately and pass an order taking into consideration the interest payable and lay down the same accordingly. It appears that after the dispute had been closed by the Council, the appellant approached the Settlement Committee, which passed an order on 05.08.2022 allowing simple interest at the prevailing bank rate to the appellant with direction that the same be paid within a further period beyond 45 days in all the cases referred to it.

4. After the said order has been passed by the Settlement Committee, the appellant raised objections relating to the order passed by the Council dated 10.05.2022 under Section 34 of the Act of 1996 before the learned Commercial Court. Learned Commercial Court, however, found the said claim of objections under Section 34 of the Act of 1996 to be beyond the period of limitation, as provided under Section 34(3) of the Act of 1996 and rejected the same. Aggrieved thereto, the present appeals have been filed.

5. Learned counsel for the appellant submits that period during which the proceedings remained pending i.e. between 10.05.2022 and the order passed by the Council dated 05.08.2022, should be treated as dies non and should not be counted for the purpose of counting limitation, as provided under Section 34(3) of the Act of 1996 and, therefore, the objections raised under Section 34 of the Act of 1996, would be treated to be within limitation and on that count, he assails the order passed by the learned Commercial Court to be unjustified and illegal.

6. Learned counsel for the appellant relied on the judgments passed by the Hon’ble Supreme Court in the cases of M/s Sonali Power Equipments Pvt. Ltd. Vs. Chairman, Maharashtra State Electricity Board, Mumbai & Ors., 2025 SCC OnLine SC 1467 and Geo Miller and Company Private Limited Vs. Chairman, Rajasthan Vidyut Utpadan Nigam Limited , (2020) 14 SCC 643 .

7. We have carefully considered the submissions.

8. It would be ap

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top