IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR
SANJEEV PRAKASH SHARMA, ACJ, SANGEETA SHARMA, J.
M/s Anamika Conductors Private Limited – Appellant
Versus
Se (Mm) Ajmer Vidyut Vitran Nigam Limited – Respondent
D.B. Civil Miscellaneous Appeal Nos. 4842, 4843 of 2025
Decided On : 20-01-2026
| Table of Content |
|---|
| 1. timeline of arbitration dispute and procedural closure. (Para 2 , 3 , 4) |
| 2. contention on limitation considering delays. (Para 5 , 6) |
| 3. clarification on section 34(3) enforcement. (Para 8 , 9) |
| 4. negation of argument on dies non applicability. (Para 10 , 11) |
| 5. rejection of reliance on previous judgments. (Para 12 , 13 , 14) |
| 6. final dismissal of appeals. (Para 15 , 16) |
JUDGMENT :
1. Heard.
2. In both the appeals, the challenge is to the judgment passed by the learned Commercial Court-II, Jaipur Metro-II, whereby the objections raised under Section 34 of the Arbitration and Conciliation Act, 1996 (for short ‘the Act of 1996’), were rejected by the learned Commercial Court on the ground that the same had been raised beyond period of limitation, as provided for filing objections in terms of Section 34(3) of the Act of 1996.
3. Brief facts which have come up before us are that the appellant had initially raised a dispute and in terms of Section 18 of the Micro, Small and Medium Enterprises Development Act, 2006 (for short ‘MSMED Act’) preferred an application before the Micro, Small and Medium Enterprises Facilitation Council, Jaipur (for short ‘Council’) claiming compound interest. The Council vide its order dated 10.05.2022, noticed that in terms of the contract, there was a provision of raising a dispute before the Settlement Committee of the Ajmer Vidyut Vitran Nigam Limited in terms of the conditions of tender. It is further observed that the claim had been directly put up before the Council. Thereafter, it proceeded to examine the claim on merits and reached to the conclusion that there had been no violation of Section 15 of the MSMED Act by the respondent-purchaser and, therefore, the claim of three times compound interest on the ground of delay of one month was not acceptable. Having reached to that conclusion, the Council closed the case unanimously. It however, further proceeded to observe that the supplier could further raise its claim relating to interest before the Settlement Committee, which would examine the case separately and pass an order taking into consideration the interest payable and lay down the same accordingly. It appears that after the dispute had been closed by the Council, the appellant approached the Settlement Committee, which passed an order on 05.08.2022 allowing simple interest at the prevailing bank rate to the appellant with direction that the same be paid within a further period beyond 45 days in all the cases referred to it.
4. After the said order has been passed by the Settlement Committee, the appellant raised objections relating to the order passed by the Council dated 10.05.2022 under Section 34 of the Act of 1996 before the learned Commercial Court. Learned Commercial Court, however, found the said claim of objections under Section 34 of the Act of 1996 to be beyond the period of limitation, as provided under Section 34(3) of the Act of 1996 and rejected the same. Aggrieved thereto, the present appeals have been filed.
5. Learned counsel for the appellant submits that period during which the proceedings remained pending i.e. between 10.05.2022 and the order passed by the Council dated 05.08.2022, should be treated as dies non and should not be counted for the purpose of counting limitation, as provided under Section 34(3) of the Act of 1996 and, therefore, the objections raised under Section 34 of the Act of 1996, would be treated to be within limitation and on that count, he assails the order passed by the learned Commercial Court to be unjustified and illegal.
6. Learned counsel for the appellant relied on the judgments passed by the Hon’ble Supreme Court in the cases of M/s Sonali Power Equipments Pvt. Ltd. Vs. Chairman, Maharashtra State Electricity Board, Mumbai & Ors., 2025 SCC OnLine SC 1467 and Geo Miller and Company Private Limited Vs. Chairman, Rajasthan Vidyut Utpadan Nigam Limited , (2020) 14 SCC 643 .
7. We have carefully considered the submissions.
8. It would be ap
Geo Miller and Company Private Limited Vs. Chairman, Rajasthan Vidyut Utpadan Nigam Limited
AI
Limitations under Section 34(3) of the Arbitration and Conciliation Act are strict, and additional proceedings or negotiations do not extend the prescribed three-month period for filing objections.
The Court emphasized the importance of providing sufficient cause for delay in filing Objections under Section 34 of the Act, 1996 and highlighted the inflexibility of the limitation period.
The main legal point established in the judgment is the absolute and unextendible nature of the time-limit prescribed under Section 34 of the Arbitration and Conciliation Act, 1996 to challenge an aw....
The court emphasized the importance of adhering to the prescribed period for setting aside an award, the exclusion of Section 5 of the Limitation Act, and the court's discretion to condone the delay ....
Point of Law : Even if the period of delay is considered to be of 21 days. Since Section 34(3) of the Act, 1996 bars condonation of delay beyond the period of 30 days after the period of 3 months is ....
The scope of interference in an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 is limited and narrow. The Courts shall not sit in an appeal while adjudicating a challen....
The period for challenging an arbitral award under Section 34 of the Arbitration and Conciliation Act cannot be extended beyond the prescribed period, as the Act is a self-contained special law and t....
The main legal point established in the judgment is that the limitation period for challenging an award under Section 34(3) of the Arbitration and Conciliation Act is strict and cannot be extended be....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.