SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(J&K) 622

IN THE HIGH COURT OF JAMMU AND KASHMIR AND LADAKH AT JAMMU
Pankaj Mithal, Rajnesh Oswal, JJ.
Ashiq Hussain & Ors. – Petitioners
Versus
State of J&K & Ors. – Respondents
OWP No. 1149 of 2017
Decided On : 09-09-2021

Advocates:
Advocate Appeared:
For the Petitioner: R.D.S. Bandral
For the Respondent: S.S. Nanda, Ravinder Gupta

The mandatory nature of Section 11-B of the Jammu and Kashmir Land Acquisition Act, 1990, and the consequences of failing to make the award within the prescribed time period.

Headnote:

Land Acquisition - Jammu and Kashmir Land Acquisition Act, 1990 - Section 6/7, Section 9, Section 9-A, Section 11, Section 17 - The court held that the land acquisition proceedings lapsed for want of award under Section 11 of the Act within two years of the declaration. The possession of the land was taken over by the respondents before the pronouncement of the award, and the court directed the respondents to issue a fresh notification for acquisition and determine compensation accordingly.

Fact of the Case:

The petitioners sought to quash a notification and consequential notices issued under the Jammu and Kashmir Land Acquisition Act, 1990, alleging that the land acquisition proceedings lapsed for want of award as no final award had been pronounced within two years from the date of the declaration.

Finding of the Court:

The court found that the land acquisition proceedings had indeed lapsed due to the failure to make the award within the stipulated time period. It also noted that the possession of the land had been taken over by the respondents before the award was pronounced.

Issues: The main issue was whether the land acquisition proceedings had lapsed due to the failure to make the award within the prescribed time period.

Ratio Decidendi: The court relied on the mandatory nature of Section 11-B of the Act, which stipulates that the award must be made within two years from the date of publication of the declaration, failing which the entire acquisition proceedings would lapse.

Final Decision: The court allowed the writ petition, directed the respondents to issue a fresh notification for acquisition, determine compensation, and complete the process within six months.

JUDGMENT :

1. Heard Sh. R.D. Singh Bandral, Sh. S.S. Nanda and Sh. Ravinder Gupta learned counsel for the parties.

2. The petitioners have invoked the writ jurisdiction of this court for quashing of notification dated 08.10.2012 issued under Section 6/7 of the Jammu and Kashmir Land Acquisition Act, 1990 (hereinafter referred to as the Act) and the consequential notices issued under Section 9 and 9-A thereof and pray that the acquisition proceedings be started afresh, if necessary so as to acquire the land in question.

3. The petitioners allege that about 130 kanals and 4.5 marlas of land was notified for proposed acquisition under Section 4 of the Act for the construction of Mavalkote-Suranda to Thetharka Road in Village Thetherka, Tehsil Gool District Ramban. It was followed by a declaration under Section 6(1) of the Act dated 18.10.2012. Thereafter, a tentative award was prepared on 13-06-2013 in respect of the above acquisition but till date no final award as contemplated vide Section 11 of the Act has been pronounced.

4. The respondents have filed objections to the writ petition admitting that the declaration under Section 6 of the Act was made on 08.10.2012 and that a tentative award was given but the final award could not be made for want of funds as the same were not made available by the intending department.

5. The argument is that the entire land acquisition proceedings have lapsed for want of award as no award was declared within a period of two years from the date of publication of the declaration under Section 6 of the Act.

6. Sh. Nanda, Senior Additional Advocate General has pointed out to the tentative award where it has been stated that the papers were submitted to the Divisional Commissioner Jammu for issuance of the notification under Section 6, 7 and 17 of the Act and, thus, contends that as the provisions of Section 17 of the Act were invoked, Section 11-B would not be applicable and the proceedings would not lapse.

7. The contention that the papers were submitted to the Divisional Commissioner Jammu for issuance of notification under Sections 6, 7 and 17 of the Act is not conclusive proof of the fact that in effect notification was issued under Section 17 of the Act and the enquiry under Section 5-A of the Act was dispensed with.

8. The respondents have not placed on record any material to demonstrate or establish that a notification under Section 17 of the Act was issued and the enquiry under Section 5-A was dispensed with.

9. It is not a case of the respondents that the land acquisition proceedings or the making of the award was stayed by any order of the court.

10. Sh. Nanda submits that most of the land-owners have accepted compensation and that compensation as per the tentative award has been distributed.

11. Learned counsel for the petitioners accepts that as per the tentative award 80% of the compensation has been received by some of the petitioners.

12. The payment and receipt of 80% of the compensation would not dilute the rigor of the statutory provisions, i.e., Section 11-B of the Act which mandates for the making of the award within a period of two years from the publication of the declaration under Section 6 of the Act and further provides that if such declaration is not made within the time, the entire acquisition proceedings would lapse.

13. Section 11-B of the Act clearly lays down that the Collector shall make the award under Section 11 of the Act within a period of two years from the date of publication of the declaration and if no award is made within the said time period, the entire proceedings for the acquisition of land shall lapse.

14. In the case at hand, the declaration under Section 6 of the Act was made on 08.10.2012 and it is admitted on record that till date final award under Section 11 has not been made despite the period of 2 years having lapsed long back. There is no dispute to the legal proposition that the provisions of Section 11-B are mandatory in nature.

15. The submission that Secti

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top