IN THE HIGH COURT OF JAMMU AND KASHMIR AND LADAKH AT SRINAGAR
RAJNESH OSWAL, J.
The Chief Engineer, Upper Sindh Hydle Project – Petitioner
Versus
Karam Chand Thapar and Bros (Coal Sales) Ltd. – Respondent
A.A. No. 17 of 2017
Decided On : 30-01-2024
| Table of Content |
|---|
| 1. scope of arbitration and necessity of adherence to contract terms. (Para 1) |
| 2. contract completion and delays due to unforeseen events. (Para 2 , 3 , 4) |
| 3. details of claims submitted to arbitral tribunal. (Para 5 , 6) |
| 4. arguments on grounds for impugning the arbitral awards. (Para 7 , 8) |
| 5. dispute on tribunal's award and bounds of judicial interference. (Para 9 , 10) |
| 6. judicial approach towards arbitral award challenges. (Para 11 , 12 , 13 , 14) |
| 7. final decisions regarding claims and arbitration clarity. (Para 15) |
| 8. final judgment on award validity and claims sustenance. (Para 16 , 17) |
JUDGMENT :
RAJNESH OSWAL, J.
1. This application under section 34 of the Arbitration and Conciliation Act, 1996 (for short ‘the Act’) has been preferred by the applicants for setting aside the award dated 25.03.2017, which includes the Majority Award issued by the Arbitrators, namely, Mr. Y.P. Singh and Mr. Sheikh Abdul Salam, as well as the Minority Award issued by Arbitrator, namely, Mr. Ali Mohd. Magray.
Facts:
2. Brief facts necessary for the disposal of the present application are that a contract for construction of the Tunnel RD 640-M to 3060-M of Sumbal Power Link Channel USHP Kangan was initially awarded to M/S National Projects Construction Corporation Ltd. (NPCC) for an estimated cost of Rs. 3.70 crores but the NPCC could execute the work only to the extent of Rs. 120 lacs (approx.) as such, the balance work was allotted to the respondent (hereinafter to be referred as ‘the claimant’) in the year 1988 on the rates as well as the terms and conditions as indicated in the agreement dated 04.06.1988, for an amount of Rs. 421.00 lacs. The period of completion of work was 30 months i.e. w.e.f. 01.06.1988 (date of start of work) to 31.12.1990 (date of completion of work), but the said work was actually completed on 30.04.2002. The completion certificate was issued on 14.09.2002.
3. This is an admitted case of both the parties that there were disturbed conditions in the Valley, as a result of which, the work could not be executed within time and numerous extensions were granted to the claimant. It needs to be noted that both the applicants as well as the claimant have levelled allegations against each other for non-completion of work within the stipulated time. After the completion of work, the claimant raised the issue with the applicants in respect of losses suffered by the claimant on account of delay in completion of the project. The claimant as such, lodged as many as 12 claims for an amount of Rs. 9.54 crores with the applicants, but the applicants rejected all the claims of the claimant. The claimant opted for arbitration and, as such, the matter was referred to the Arbitral Tribunal.
4. The claimant submitted 12 claims in total before the Arbitral Tribunal claiming Rs. 9,54,47,132.15/- along with interest at the rate of 24% per annum, whereas the applicants besides objecting the claims of the claimant, lodged counter-claim of Rs. 7,04,76,800/-. The claimant filed the rejoinder to the reply as well as the counter-claim filed by the applicants and denied the counter-claims of the applicants. On the basis of the claims as well as counter-claims submitted by the parties, the Arbitral Tribunal framed as many as 15 issues for its determination, the same are extracted as under:
(ii) Whether the claimants are entitled to bonus for the reasons and on the ground mentioned under Claim 2 of the Statement of Claims, to the tune of Rs. 1,32,15,759.00. If so, how?
(iii) Whether the Claimants are entitled to the compensation on account of non-availability of electric power at site and/ or erratic supply of electric power and/or low voltage to the tune of various amounts claimed under Claim No. 3 in the Statement of Claim. If so, how?
(iv) Whet
Delhi Airport Metro Express (P) Ltd. vs. DMRC
Dyna Technologies (P) Ltd. vs. Crompton Greaves Ltd. (2019) 20 SCC 1
Irrigation Department Govt. of Orissa vs. G.C. Roy
J.G. Engineers (P) Ltd. vs. Union of India
Konkan Railway Corporation Ltd. vs. Chenab Bridge Project
MSK Projects (I) (JV) Ltd. vs. State of Rajasthan
MSK Projects (I) (JV) Ltd. vs. State of Rajasthan and Another
Md. Army Welfare Housing Organization v. Sumangal Services (P) Ltd. (2004) 9 SCC 619
National Highways Authority of India vs. M. Hakeen and Another
Parsa Kente Collieries Ltd. vs. Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (2019) 7 SCC 236
State of Goa vs. Praveen Enterprises
Seth Thawardas Pherumal vs. Union of India
S.V. Samudram vs. State of Karnataka and Another
State of Orissa vs. Sudhakar Dass (Dead) by LRs. AIR 2000 SC 1294
Swan Gold Mining Ltd. vs. Hindustan Copper Ltd. (2015) 5 SCC 739
An arbitral award must stay within the bounds of the arbitration agreement; claims exceeding this scope can be annulled, underscoring limited judicial interference in arbitration matters.
The court affirmed the limited scope of review under Section 34 of the Arbitration and Conciliation Act, emphasizing respect for arbitral awards unless stark violations of public policy or procedural....
The judgment emphasizes the limited scope of interference with arbitral awards and the principle that courts should not interfere with arbitral awards unless there is a patent illegality or violation....
An arbitrator may award escalated costs due to employer delay despite prohibitory clauses, reinforcing that delays affecting contractor performance can lead to compensatory claims.
An arbitrator's award may be upheld if it conforms to contract terms, despite challenges regarding procedural compliance or interpretation, provided it does not contravene public policy.
The court emphasized the requirement for the arbitrator to assign reasons in support of the award and the limited scope of interference by the court in arbitration awards.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.