SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(J&K) 223

IN THE HIGH COURT OF JAMMU AND KASHMIR AND LADAKH AT SRINAGAR
RAJNESH OSWAL, J.
The Chief Engineer, Upper Sindh Hydle Project – Petitioner
Versus
Karam Chand Thapar and Bros (Coal Sales) Ltd. – Respondent
A.A. No. 17 of 2017
Decided On : 30-01-2024

Advocates:
Advocate Appeared:
For the Petitioner: M.A. Chashoo.
For the Respondents: Pranav Kohli, Arun Dev Singh, Megina.

An arbitral award must stay within the bounds of the arbitration agreement; claims exceeding this scope can be annulled, underscoring limited judicial interference in arbitration matters.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitral award - Majority Award upheld for claims related to suspension of work and delay in completion, whereas Minority Award rejected the claim for bonus as it did not arise from the agreement - Court emphasized limited grounds for interference with arbitral awards, specifically highlighting the need for established jurisdictional relevance. (Paras 10, 15, 17)

(B) Legal principles governing arbitration - The scope of judicial review of arbitral awards is limited; courts cannot reassess evidence and must respect the autonomy of the arbitrators in matters within their jurisdiction. (Paras 12, 14)

Facts of the case:
The dispute arises from a contract for construction work where delays occurred due to force majeure conditions and disturbances in the region, leading to a lengthy arbitration process with claims of over Rs. 9.54 crores submitted against counterclaims of Rs. 7.04 crores, culminating in multiple issues regarding the enforceability of claims related to labor and project delays. (Paras 2-4)

Findings of Court:
The Court concluded that the award regarding claims for suspension and delay was sustainable, but the award relating to bonus lacked contractual foundation and was thus set aside. (Paras 17)

Issues: Key issues addressed included (i) the validity of claims under force majeure conditions, (ii) the definition of bonus and its applicability, and (iii) whether the arbitration awards exceeded the scope of the agreed contract. (Paras 4, 8, 15)

Ratio Decidendi: The court underscored that an arbitrator’s power is defined by the contractual framework, and any awards made that exceed this framework are subject to annulment. The definition of compensation awarded must establish clear ties to the contractual obligations outlined. (Paras 10, 14, 15)

Result: Application allowed to the extent of claim No. 2, upheld for claims Nos. 1 and 8.

Table of Content
1. scope of arbitration and necessity of adherence to contract terms. (Para 1)
2. contract completion and delays due to unforeseen events. (Para 2 , 3 , 4)
3. details of claims submitted to arbitral tribunal. (Para 5 , 6)
4. arguments on grounds for impugning the arbitral awards. (Para 7 , 8)
5. dispute on tribunal's award and bounds of judicial interference. (Para 9 , 10)
6. judicial approach towards arbitral award challenges. (Para 11 , 12 , 13 , 14)
7. final decisions regarding claims and arbitration clarity. (Para 15)
8. final judgment on award validity and claims sustenance. (Para 16 , 17)

JUDGMENT :

RAJNESH OSWAL, J.

1. This application under section 34 of the Arbitration and Conciliation Act, 1996 (for short ‘the Act’) has been preferred by the applicants for setting aside the award dated 25.03.2017, which includes the Majority Award issued by the Arbitrators, namely, Mr. Y.P. Singh and Mr. Sheikh Abdul Salam, as well as the Minority Award issued by Arbitrator, namely, Mr. Ali Mohd. Magray.

Facts:

2. Brief facts necessary for the disposal of the present application are that a contract for construction of the Tunnel RD 640-M to 3060-M of Sumbal Power Link Channel USHP Kangan was initially awarded to M/S National Projects Construction Corporation Ltd. (NPCC) for an estimated cost of Rs. 3.70 crores but the NPCC could execute the work only to the extent of Rs. 120 lacs (approx.) as such, the balance work was allotted to the respondent (hereinafter to be referred as ‘the claimant’) in the year 1988 on the rates as well as the terms and conditions as indicated in the agreement dated 04.06.1988, for an amount of Rs. 421.00 lacs. The period of completion of work was 30 months i.e. w.e.f. 01.06.1988 (date of start of work) to 31.12.1990 (date of completion of work), but the said work was actually completed on 30.04.2002. The completion certificate was issued on 14.09.2002.

3. This is an admitted case of both the parties that there were disturbed conditions in the Valley, as a result of which, the work could not be executed within time and numerous extensions were granted to the claimant. It needs to be noted that both the applicants as well as the claimant have levelled allegations against each other for non-completion of work within the stipulated time. After the completion of work, the claimant raised the issue with the applicants in respect of losses suffered by the claimant on account of delay in completion of the project. The claimant as such, lodged as many as 12 claims for an amount of Rs. 9.54 crores with the applicants, but the applicants rejected all the claims of the claimant. The claimant opted for arbitration and, as such, the matter was referred to the Arbitral Tribunal.

4. The claimant submitted 12 claims in total before the Arbitral Tribunal claiming Rs. 9,54,47,132.15/- along with interest at the rate of 24% per annum, whereas the applicants besides objecting the claims of the claimant, lodged counter-claim of Rs. 7,04,76,800/-. The claimant filed the rejoinder to the reply as well as the counter-claim filed by the applicants and denied the counter-claims of the applicants. On the basis of the claims as well as counter-claims submitted by the parties, the Arbitral Tribunal framed as many as 15 issues for its determination, the same are extracted as under:

    (i) Whether the Claimants are entitled to compensation to the tune of Rs. 19,24,479.00 and Rs. 17,64,150.00 for suspension of work for different spells, between October, 1989 to December, 1990. If so how?

    (ii) Whether the claimants are entitled to bonus for the reasons and on the ground mentioned under Claim 2 of the Statement of Claims, to the tune of Rs. 1,32,15,759.00. If so, how?

    (iii) Whether the Claimants are entitled to the compensation on account of non-availability of electric power at site and/ or erratic supply of electric power and/or low voltage to the tune of various amounts claimed under Claim No. 3 in the Statement of Claim. If so, how?

    (iv) Whet

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top