IN THE HIGH COURT OF ORISSA AT CUTTACK
SANJEEB K. PANIGRAHI, J.
Paradip Port Trust (PPT) - Appellant
Versus
M/s.- Modi Projects Limited - Respondent
ARBA No.8 of 2023 Along with W.P.(C) No.7019 of 2024
Decided On : 26-08-2025
| Table of Content |
|---|
| 1. factual background of the arbitration case. (Para 4 , 5 , 6 , 7 , 10) |
| 2. arguments against the arbitral award's validity. (Para 14 , 15) |
| 3. legal standards for appellate review. (Para 19 , 21 , 22) |
| 4. mandatory nature of the 'vivad se vishwas ii' scheme. (Para 60 , 61 , 62) |
| 5. court's final decision on appeals. (Para 68 , 69) |
JUDGMENT :
S.K. Panigrahi, J.
1. Since these applications arise from the same facts and involve the same parties, the same were taken up for hearing together and are being dealt with by this Common Judgment and Order
2. This Appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “A&C Act” for brevity) has been filed seeking setting aside of the judgment dated 04.02.2023 passed by the learned District Judge, Jagatsinghpur in Arbitration Petition No.3 of 2019 arising out of arbitration award dated 12.04.2019 passed by the Ld. Sole Arbitrator Retd. Justice M.M.Das. The Writ Petition is preferred by the Respondent in ARBA No.8 of 2023 seeking a direction to the Appellant in ARBA No.8 of 2023 to accept the proposal submitted by the Respondent on 03.08.2023 in pursuance of the Vivad Se Viswas II Scheme.
3. As the Writ Petition seeks a direction that pertains to execution of the award that is under challenge in the ARBA, it is considered apposite to first deal with the questions raised vis-à-vis sustainability of the award itself.
I. FACTUAL MATRIX OF THE CASE:
4. The Appellant invited tenders for the work of “Railway Works for Deep Drought Berths at Paradip Port”. Pursuant to such invitation, the Respondent submitted its tender on 30.11.2013. Subsequently, the letter of award was issued in favour of the Respondent on 4.12.2014 for a total value of Rs.78,65,64,301.50/. The date of commencement of work was stipulated to be 5.1.2015 and the scheduled date of completion was by 4.4.2016.
5. On 1.6.2015 an agreement was executed between the Parties specifying all the terms and conditions for the work in question.
6. The Respondent submitted an application on 29.3.2016 seeking extension of time. The extension was provided up till 30.3.2017 with imposition of liquidated damages/penalty.
7. As the work could not be completed within the extended period, the Appellant terminated the contract vide letter dated 4.4.2017. The Respondent thereafter, invoked arbitration for adjudication of the dispute arising out of the termination, imposition of damages, delay and incidental issues.
8. Thereafter, Ld. Single Arbitrator, Retd. Justice M.M. Das was appointed to adjudicate upon the dispute between the Parties.
9. After hearing the parties, the Ld. Sole Arbitrator was pleased to pass his final award on 12.4.2019 wherein, the Ld. Sole Arbitrator was pleased award Rs.13,66,01,820/- in favour of the Respondent.
10. Aggrieved, the Appellant assailed the final award dated 12.4.2019 under Section 34 of the A&C Act in the Court of the learned District Judge, Jagatsinghpur in Arbitration Petition No. 3 of 2019. Vide judgment dated 4.2.2023, the Ld. District Judge, Jagatsinghpur was pleased to dismiss the same upon arriving at the conclusion that the award was not in violation of the public policy of India, did not contain any plausible fact that would shock the conscience of the court and did not have any patent illegality on the face of the record.
11. Aggrieved by the same, the instant Appeal has been preferred.
12. The Appeal u/s 37 of the A&C Act was filed on 23.3.2023. During the pendency of the same before this Court, the Respondent preferred Writ Petition No. 7019 of 2024 on 18.3.2024 seeking a direction against the Appellant to accept the proposal submitted by it on 3.8.2023 in pursuance to the Vivad se Vishwas II (contractual disputes) scheme dated 29.5.2023.
13. As the facts leading up to the instant Applications have been laid down, this Court shall endeavour to summarise the contentions of the Parties and the broad grounds that have been raised to seek the exercise of this Court’s





Haryana Tourism Limited v. Kandhari Beverages Limited
Surya Dev Rai v. Ram Chander Rai
Delhi Airport Metro Express (P) Ltd. v. DMRC
Indian Oil Corpn. Ltd. v. Shree Ganesh Petroleum
Raghunath G. Panhale v. Chaganlal Sundarji
Kuldeep Singh v. Commissioner of Police
Kuldeep Singh v. Commissioner of Police
Vishwanath Agrawal v. Sarla Vishwanath Agrawal
Sumitomo Heavy Industries Ltd. v. ONGC Ltd.
K. Sugumar and Anr. v. Hindustan Petroleum Corporation Ltd. & Anr.
UHL Power Company Ltd. v. State of Himachal Pradesh
Sutlej Construction Limited v. Union Territory of Chandigarh
Venture Global Engineering v. Satyam Computer Services Limited and Anr.
Patel Engineering Limited v. North Eastern Electric Power Corporation Limited
AI
Judicial review under Section 37 of the Arbitration and Conciliation Act is limited and requires interference only in cases of patent illegality or public policy violations; claims meeting the "Vivad....
The court emphasized that judicial interference with arbitral awards is strictly limited, focusing only on issues of public policy or jurisdictional errors and cannot re-evaluate the merits of the aw....
The court reaffirmed that judicial intervention in arbitration under Sections 34 and 37 is limited to ensuring no substantial legal errors occurred, emphasizing the importance of respecting the arbit....
Judicial scrutiny under the Arbitration and Conciliation Act is limited; courts must respect arbitral awards unless proven to violate public policy or statutory obligations, affirming the principle t....
(1) While exercising power under Section 34 of A & C Act, arbitral award can only be confirmed or set aside, but not modified.(2) Award passed by Arbitral Tribunal cannot be set aside on the ground t....
The court affirmed that limited judicial review under Section 34 of the Arbitration Act does not allow for re-evaluation of arbitration awards unless they are demonstrably perverse, illegal, or devoi....
Under Section 34, courts cannot interfere with arbitral awards based on joint departmental reconciliations and admissions unless patent illegality apparent on award's face; limited to upholding final....
The judgment emphasizes the limited scope of interference with arbitral awards and the principle that courts should not interfere with arbitral awards unless there is a patent illegality or violation....
The court reaffirmed the limited scope of judicial review of arbitral awards under Sections 34 and 37 of the Arbitration and Conciliation Act, emphasizing that courts cannot reappraise evidence or in....
Judicial review of arbitral awards under Sections 34 and 37 of the Arbitration Act is significantly limited, focusing solely on jurisdictional errors or procedural irregularities with no reassessment....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.