IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
K. Lakshman, J.
Disha Advertising - Appellant
Vs.
The Hyderabad Metropolitan Development Authority HMDA - Respondent
Writ Petition No.1009 of 2019
Decided On : 03-12-2021
Constitution of India,1950 - Article 226 - Indian Contract Act, 1872 - Section 7 - Tender notification process - Acceptance of bid - Seeking to demolish - Petitioners paid EMD bid security and submitted all bid documents in accordance with Request for Proposal (hereinafter RFP) document issued pursuant to tender notice - Last date to submit bids and bids were to be finalized - 1st petitioner’s bid was accepted as highest bid and it was awarded tender - Based on remarks reflected on Telangana e-Procurement Website, 1st Petitioner claimed that tender was awarded to it - This, according to the petitioner, was communication of acceptance and resulted in a concluded contract between itself and 1st respondent - Subsequent to online communication of awarding bid to 1st petitioner, no steps were taken by respondent authorities to act in accordance with RFP. No letter of acceptance was issued nor any license agreement was executed between parties - Whether acceptance of bid would be tantamount to entering into a contract needs to be decided by the Single Judge – Held, contention of petitioners that only ‘reasonable’ restrictions or least restrictive measures should be taken on fundamental right of petitioner cannot be accepted - Respondent Nos. 1 and 2 herein seeking recovery of amount earned by petitioners on each sign board - Said I.A. was closed leaving it open for respondent Nos. 1 and 2 to make submissions during final hearing - Said relief sought by the respondent Nos.1 and 2 is on factual basis - Court cannot go into the said factual aspects of amount collected by petitioners, period and quantification etc., by invoking jurisdiction under Article 226 of Constitution of India - Moreover, relief in said Interlocutory Application cannot be granted in a writ petition filed by another person - Therefore, liberty is granted to respondent Nos. 1 and 2 to take appropriate steps to recover amount, in accordance with law - Writ petition is dismissed.
ORDER:
The present writ petition is filed to direct respondent Nos.1 and 2 to act in accordance with law and their statutory and contractual duties pursuant to the conclusion of the tender notification process and the conclusion of contract pursuant to the acceptance of bid by the 1st respondent on 01.09.2018; to declare the action of respondent Nos. 1 and 2 in seeking to demolish the 80 advertisement LED boards erected from Pillar No. 120 to Pillar No. 200 of the PVNR Expressway, Hyderabad; to restrain the respondents from interfering with the said business of the petitioners’ right to conduct their legitimate and duly authorized business activity in accordance with the concluded contract; to issue a direction to the respondent Nos. 1 and 2 to forbear from interfering with the activity of the petitioners to continue with their lawful business exhibiting the advertisement boards from Pillar No. 120 to Pillar No. 200.
2. Heard Sri Anjana Taggarse Motupalli and Associates, learned counsel for the petitioners, Sri V.Narasimha Goud, learned standing counsel appearing for respondent Nos.1 and 2 and learned Government Pleader for Municipal Administration Department appearing for the 3rd respondent. Perused the record.
3. FACTS OF THE CASE
(ii) The petitioners paid the EMD bid security and submitted all the bid documents in accordance with the Request for Proposal (hereinafter RFP) document issued pursuant to the tender notice. The last date to submit the bids was 24.08.2021 and the bids were to be finalized on 01.09.2018.
(iii) The 1st petitioner’s bid was accepted as the highest bid and it was awarded the tender. Based on the remarks reflected on the Telangana e-Procurement Website, the 1st Petitioner claimed that the tender was awarded to it on 01.09.2018 5:23 PM. This, according to the petitioner, was communication of acceptance and resulted in a concluded contract between itself and the 1st respondent. However, subsequent to the online communication of awarding the bid to the 1st petitioner, no steps were taken by the respondent authorities to act in accordance with the RFP. No letter of acceptance was issued nor any license agreement was executed between the parties.
(iv) The petitioners claim that they received oral assent from the 1st respondent to install the advertisement boards as the contract was already concluded. The petitioners installed eighty advertisement boards on 40 pillars.
(v) The 1st Respondent denied any conclusion of contract and any oral assent to install the advertisement boards and removed the said advertisement boards.
(vi) The Petitioners have challenged the removal of the said advertisement boards contending that lawful agreement is subsisting as illegal and arbitrary and sought a direction against the respondent authorities not to interfere with their lawful conduct of business.
(vii) It is relevant to note that respondent Nos.1 and 2 herein had filed W.A.No.953 of 2019 against an order passed in I.A.No.1 of 2019 in the present Writ Petition. In the said W.A.No.953 of 2019, the Division Bench noted that issuance of Letter of Acceptance has to culminate in the signing of agreement. It was observed that whether acceptance of bid would be tantamount to entering into a contract needs to be decided by the Single Judge. Therefore, direction was given to decide the present writ petition as expeditiously as possible.
(viii) It is also relevant to note that the order passed in I.A.No.5 of 2019 filed to amend the writ petition, was also challenged by the petitioner herein vide W.A.No.271 of 2021. The said appeal was disposed of by th
Trimex International FZE Ltd. Dubai v. Vedanta Aluminum Ltd.
Maharashtra Land Development Corporation v. State of Maharashtra
Chairman, All Indian Railway Recruitment Board v. K. Shyam Kumar
Kumari Shrilekha Vidhyarthi v. State of UP
Mahabir Auto Stores v. Indian Oil Corporation
Kalabharti Advertising v. Hemant Vimalnath Narichania
Haryana Urban Development Authority v. Orchid Infrastructure
UP Avas Evan Vikas Parishad v. Om Prakash Sharma
TSRTC Nalgonda v. Siliveru Gyaneshwar Social Service Society.
Kollipara Sriramulu v. T. Aswathanarayana
PSA Mumbai Investments Pte. Limited v. The Board of Trustees of the Jawaharlal Nehru Port Trust
Apollo Health and Lifestyle Limited v. Anupam Saraogi of Indian Inhabitant
A letter of intent is a precursor to a contract and does not create a binding legal relationship. Mandatory tender conditions, such as bid capacity, must be satisfied at the time of bid submission; a....
The main legal point established in the judgment is that the contract stood concluded upon acceptance of the bid, and the subsequent signing of documents was only for formal documentation. The court ....
The main legal point established in the judgment is that the presence of contingent conditions in a Letter of Acceptance can impact the formation of a concluded contract, and the intention of the par....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.