In construction projects, slow progress of work is a common dispute trigger. Contractors often face penalties or liquidated damages for delays, but is penalisation always justified? The search query For Slow Progress of Work Contractor Cannot be Penalised highlights a key debate: under what circumstances can contractors avoid penalties? This post examines Indian legal precedents, focusing on contract clauses, arbitration, and court interventions. While penalties are standard, they aren't automatic—especially if delays stem from the employer or other excusable factors.
Important Disclaimer: This is general information based on case law, not specific legal advice. Consult a lawyer for your situation, as outcomes vary by contract and facts.
Most construction contracts include clauses on time as essence, extensions, and liquidated damages (LD) for delays. Under the Indian Contract Act, 1872 (Sections 73-75), parties can stipulate reasonable compensation for breach.
Courts emphasize: Entire contract between parties and terms thereon have to be read as a whole to decide rights and liabilities.Mitra Guha Builders (India) Company VS Oil And Natural Gas Corporation Limited - 2019 Supreme(SC) 1250
Penalties apply if the contractor is solely responsible. Employers must prove fault.
The contractor is liable for penalties for delayed work unless he proves that the delay resulted from the Panchayat’s actions.MALAPPURAM DISTRICT PANCHAYAT Vs P.T.HAMSA & OTHERS - 2009 Supreme(Online)(KER) 2042
Contractors often escape penalties if delays are attributable to the employer. Key defenses:
Courts don't re-appreciate evidence: Courts cannot sit in judgment over the award of the arbitrator, nor re-appreciate the evidence.State of Rajasthan VS Ferro Concrete Construction Pvt - 2009 Supreme(SC) 800
| Case ID | Key Holding | Outcome |
|---------|-------------|---------|
| Mitra Guha Builders (India) Company VS Oil And Natural Gas Corporation Limited - 2019 Supreme(SC) 1250 | Finality to Engineer's LD decision; not arbitrable if excepted. | Appeals dismissed; LD upheld. |
| Supreme Panvel Indapur Tollways Private Limited vs National Highways Authority of India | Tribunal rejected stay for funding non-compliance; limited review. | No interim relief. |
| G. V. Malla Reddy & Co. , Represented By Its Managing Partner Sri G. V. Malla Reddy VS A. P. State Trading Corporation Limited, Represented By Its Vice-Chairman & Managing Director, Hyderabad - 2009 Supreme(AP) 944 | Interest sustainable even sans specific covenant; no LD if extension granted. | Award upheld. |
| ASHOK PATNI VS TURF ESTATE J. V. | Refund + interest for non-agreement/lack of progress (buyer side). | Complaint allowed. |
| COASTAL ENGINEERING Vs THE UNION OF INDIA - 2021 Supreme(Online)(KER) 9674 | No writ if arbitration pending; respect clauses. | Petition dismissed. |
Once parties have decided that certain matters are to be decided by Superintending Engineer and his decision would be final, same cannot be subject matter of arbitration.Mitra Guha Builders (India) Company VS Oil And Natural Gas Corporation Limited - 2019 Supreme(SC) 1250
Under Section 34/37, courts check only:
- Patent illegality
- Public policy violation
- No re-appreciation
The court does not sit in appeal over the award of the arbitrator and cannot re-appreciate the evidence.STATE OF RAJASTHAN VS FERRO CONCRETE CONSTRUCTION PVT. LTD. - 2009 Supreme(SC) 809
In Aadhaar/mining cases (tangentially related to govt contracts), strict timelines enforced, but irrelevant here.GOA FOUNDATION VS UNION OF INDIA - 2015 7 Supreme 257Justice K. S. Puttaswamy (Retd. ) VS Union of India - 2018 7 Supreme 129
To avoid/mitigate penalties:
1. Document Everything: Photos, correspondence on hindrances.
2. Seek Extensions Timely: Written requests with evidence.
3. Respond to Notices: Dispute LD levy immediately.
4. Arbitrate Promptly: Preserve claims.
5. Prove Employer Fault: Late payments/site issues shift blame.
Employers: Issue progressive notices, justify LD.
For Slow Progress of Work Contractor Cannot be Penalised if delays are employer-induced, procedures flouted, or arbitrator rules favorably. However, contractors must prove excuses; penalties stick otherwise. Courts protect contractual intent but curb arbitrariness.
Takeaways:
- Burden on Contractor: Prove no fault.
- Limited Judicial Interference: Uphold arbitration.
- Fair Process Essential: Notices mandatory.
- Proportionality: No permanent blacklisting for delays.
In sum, while contracts enable penalties, equitable application prevails. For tailored advice, engage counsel—delays can cost dearly, but defenses exist.
Courts cannot sit in judgment over the award of the arbitrator, nor re-appreciate the evidence - Awards on these claims do not suffer ... from any infirmity which can be the basis for interference either - Neither want of jurisdiction, nor legal misconduct, nor any ... water pipeline of a length of 37.41 km. under a water supply scheme - Tenders were received from various tenderers including respondent ... Claims 11 & 20 are for com....
leases – Cannot be allowed in absence of State government permission stating reasons therefor. ... working pit – Rule cannot be read as permitting dumping of overburden etc. outside the leased area. ... or rejects outside leased area without payment of royalty – Rues must give way to provisions of the Act – Therefore, dump cannot ... ) cannot be quashed by this Court. ... Rule 37....
(Rule in Oleum Gas case) whether respondents 4 to 8 are liable to pay compensation to villagers of Bichhri? ... liable to make good the loss caused to any other person by his activity irrespective of the fact whether he took reasonable care ... be the law applicable, it follows, in the light of our findings recorded hereinbefore, that Respondents Nos. 4 to 8 are absolutely ... T....
not attract any of the grounds on which award could be set aside - Therefore, rejection of these claims is also not open to interference ... the award of the arbitrator and cannot re-appreciate the evidence to arrive at a different conclusion - Award on these items does ... the arbitrator - Held, Rejection of Counter-Claim No. 5 is consequential - As noticed above, the court does not#HL_....
a work in progress – Act fulfilling larger public interest striving to benefit millions of deserving people – Whole scheme cannot ... algorithms or probabilities – Constitutional guarantees cannot be subject to the vicissitudes of technology. ... , not defined, held to be matter of policy not law – Disclosure of#HL_E....
failure of the opposite party to provide the draft agreement and lack of progress in the project. ... They terminated the allotment due to non-receipt of draft agreement and lack of progress in the project, seeking a refund of the ... Issues: Non-receipt of draft agreement, lack of progress in the project, entitlement to refund and compensation. ... the #HL_STA....
Instead of making submissions with regard to lack of progress in the project on hand, the opposite party’s attempt to shift the blame ... The responsibility of completion of the project remains that of builder and it cannot seek to transfer this responsibility to Government ... In the absence of any evidence being brought on record, merely a bald assertion that the project was delayed due to in #H....
the foreclosure of a contract with the respondents, citing lack of progress and subsequent termination as the issues affecting the ... Fact of the Case: The petitioner, a contractor, sought the release of Security Deposit and Earnest Money Deposit after ... release of funds. ... The Deputy Chief Engineer, however, issued Ext.P4 notice dated 19.01.2019 alleging the progress in work is slow. ... ~....
work, slow progress, and collusion with the contractor. ... Decidendi: The court upheld the punishment based on proven charges, disregarding the charge of lack of quality work. ... He was punished with censure, deprivation of increments, and transfer to a non-works post, which he challenged in the appeals. ... not being ,ensured, (ii) slow progress of ....
... ... Findings of Court: ... The court noted the inadequate progress and lack of accountability from responsive officials and emphasized ... ... ... Issues: The key issue explored is the lack of progress on critical infrastructure affecting livelihoods and the legal accountability ... of inordinate delay and quality issues - Directions issued by the court to the authorities to report progress and take necessary ... was underta....
The correspondence between the parties which is admitted in evidence at Exhibits - 130, 131, 133 and 134 shows that the Department had time to time informed the Plaintiff regarding slow progress of work. The Department had also imposed penalty for slow progress of work. ... The Defendants had informed the Plaintiff about slow progress of work through various communications. The Plaintiff did not reply any of the communications and a....
He further submitted that slow progress of the work was not due to any fault on the part of the petitioner, rather respondents themselves are responsible for the slow progress of work. He relied on 1994 Supp. (2) Supreme Court Cases 699 (Southern Painters vs. ... In any event, it is a case where according to the respondents, the work's progress of 89 contractors, including the petitioner is very slow and not in terms of the contract, whereas accordin....
The progress of work has been review by Hon‟ble Minister of Education on 20.01.03 and he expressed dissatisfaction over slow progress at work. ... C-2 to C-5, clearly states the progress of the work by the Contractor was very slow and there was no hindrance from the department’s side. ... In letter dated 13th December, 2002 exhibited as Ex.R-4, the department informed the contractor as under: “The work#HL....
The progress of work has been review by Hon'ble Minister of Education on 20.01.03 and he expressed dissatisfaction over slow progress at work. ... In letter dated 13th December, 2002 exhibited as Ex.R-4, the department informed the contractor as under: "The work was inspected on 9.12.02. The progress of work is very slow. Cement is not available in the store. There is shortage of steel of various diameters. ... A....
The above letters have been quoted in detail as their reading would show that the Team Leader and the Project Director were repeatedly pointing out the slow progress of the work to the respondent and calling upon it to expedite the work. ... The updated work programme and cash flow submitted by the Contractor for completing the work in Oct, 2014 are not workable it assumes 3.7% per month average progress. The balance work is estimat....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.