SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Del) 1821

IN THE HIGH COURT OF DELHI AT NEW DELHI
C. Hari Shankar, J.
Sms Limited - Appellant
Versus
Oil & Natural Gas Limited - Respondent
OMP (I) (Comm) 428/2020 & I.A. 12771/2020
Decided On : 12-01-2021

Advocates appeared:
Mr. Vikram Nankani, Sr. Adv, With Mr. Naresh Thacker, Mr. Abhileen Chaturvedi, Mr. Rohit Sharma And Mr. Dhruv Jain, Advs, for the Appellant; Mr. Abhimanyu Garg, Adv, for the Respondent.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 9 - Pre-arbitral injunction sought by contractor against customer for payment of liquidated damages and encashment of bank guarantees. Court held that the guarantees are unconditional and must be honored on demand. The contractor's claims of delay due to customer were insufficient to prevent invocation. (Paras 1, 60, 76)

(B) The court reinforced that invocation of unconditional bank guarantees cannot be stayed unless exceptional fraud or irretrievable injustice is demonstrated. (Paras 42, 96)

Facts of the case:
The contractor appealed for an injunction against the customer's demand for liquidated damages and encashment of guarantees before arbitration proceedings commenced. Disputes regarding delays and responsibilities were evident.

Findings of Court:
Court noted the relevant clauses and upheld the enforceability of unconditional bank guarantees, dismissing the appeal for injunction.

Issues: Main issues were the nature of the bank guarantees and whether there existed grounds for injunction against their invocation given the ongoing disputes.

Ratio Decidendi: The court reasoned that the bank guarantees were absolute and unconditional; thus, ONGC's invocation would not be restrained based on the existing contractual disputes.

Result: Petition dismissed with no costs.

Table of Content
1. introduction of the case and parties. (Para 1 , 2)
2. background facts of the contract and obligations. (Para 3 , 6 , 10 , 12 , 30)
3. petitioner's arguments on liquidated damages. (Para 4 , 5 , 18 , 19)
4. court's reasoning on bank guarantees and invocation. (Para 38 , 55 , 56 , 78)
5. conclusion and dismissal of the petition. (Para 100)

Judgment

1. By this petition, under Section 9 of the Arbitration & Conciliation Act 1996 (hereinafter referred to as "the 1996 Act"), the petitioner SMS Ltd. prays for pre-arbitral injunction, restraining the respondent ONGC Ltd. from acting in furtherance of a letter dated 15th December, 2020, issued by the latter to the former. The letter reads thus:

"OIL AND NATURAL GAS CORPORATION LIMITED

Onshore Engineering Services

Materials Management Section

2nd Floor, Tower -B Deendayal Urja Bhava, 5,

Nelson Mandela Road, Delhi-110070

Ref No. DLH/OES/MM/ETP-NADA &

AF/X11PC11001/2011 Dated: 15.12.2020

From: Office of GGM (MM)- i/c MM, Engineering Services, DDU Bhawan, Delhi

Onshore

TO:

M/s. SMS Limited (Formerly M/s.

SMS Infrastructure Limited)

(Consortium of M/s. SMS Limited,

Nagpur, M/s. Zen Marketing &

Technologies, Kolkata and M/s.

Tolani Projects Pvt. Ltd.,

Ankleshwar)

IT PARK. 20 S.T.P.I

GAYATRI NAGAR,

PARSODI, NAGPUR-

440022

Kind Attn:

Shri Hemant

Hathiwala, CEO

Sub: Amendment No. 11 to the Contract No. DLH/OES/MM/ETP-NADA & AF/X11PC11001/2011 dtd. 27.06.2012 for the Project 'Construction of ETP at Nada, Additional Handling Facilities alongwith laying of associated Pipelines in Area-Nat Ankleshwar Asset (ETP-Nada & AF)'______________________________________

Dear Sir(s),

Please refer the Contract No. DLH/OES/MM/ETP-NADA & AF/X11PC11001/2011 dated 27.06.2012 for the Project for "Construction of ETP at Nada, Additional Handling Facilities alongwith laying of associated Pipelines in Area-IV at Ankleshwar Asset (ETP-Nada & AF)". ONGC hereby extends the scheduled completion period of the LSTK contract (Refer clause 6.3 of General conditions of contract for LSTK portion, Annexure-A, Part-A of the contract) from 31.07.2014 to 31.07.2018 with levy of 10 % Liquidated Damages amounting to Rs. 12,09,83,122.10 as per the clause no.6.3.2 of General conditions of contract for LSTK portion, Annexure-A Part-A of the contract, plus GST thereon of Rs.2,17, 76,961.97 (as per GST legislation effective from 01.07.2017) totaling to Rs. 14,27,60,084.00 as detailed below:

Delay solely attributable to Consortium as on 18.07.2018

a) 3 Years 5 Months and 12 days in completion of standalone facilities (at Padra, Dabka, Jambusar, North Gandhar, GGS-Nada and ETP-Nada)

b) 3 Years 11 Months and 18 days in completion of GRE Pipelines.

Liquidated Damages@ 0.5% per week & part thereof for the delay

10% (maximum)

Liquidated Damages amount

Rs.12,09,83,122.10

GST on Liquidated Damages amount @ 18%

Rs. 2,17,76,961.97

Total Liquidated Damages + GST

Rs. 14,27,60,084.00

Accordingly, ONGC hereby requests you to remit the amount of Rs. 14,27,60,084.00 towards Liquidated damages and GST thereon to ONGC by 22.12.2020.

In case the amount of Rs. 14,27,60,084.00 is not remitted to ONGC by 22.12.2020, then LD and GST shall be recovered by invoking and encashing the Bank Guarantees submitted by you towards Liquidated damages and GST thereon as per provisions of the contract, as detailed below:

Bank Guarantee particulars

(i) Bank Guarantee No. 0713614BG0000139 for Rs.12,09,90,000.00 issued by SBI, Industrial Finance Branch, Nagpur.

(ii) Bank Guarantee No. 3761ILG003620 for Rs.2,66,17,800.00 issued by Punjab National Bank, Dharmpeth, Nagpur.

Total amount of bank Guarantees

Rs.14,76,07,800.00 (i.e. Rs.12,09,90,000.00 + Rs.2,66, 17,800.00)

GST@ 18% on the total amount of Bank Guarantees

Rs. 2,65,69,404.00

Balance available after deposit of GST to Government authorities whi

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top