IN THE HIGH COURT OF DELHI AT NEW DELHI
C. Hari Shankar, J.
Sms Limited - Appellant
Versus
Oil & Natural Gas Limited - Respondent
OMP (I) (Comm) 428/2020 & I.A. 12771/2020
Decided On : 12-01-2021
| Table of Content |
|---|
| 1. introduction of the case and parties. (Para 1 , 2) |
| 2. background facts of the contract and obligations. (Para 3 , 6 , 10 , 12 , 30) |
| 3. petitioner's arguments on liquidated damages. (Para 4 , 5 , 18 , 19) |
| 4. court's reasoning on bank guarantees and invocation. (Para 38 , 55 , 56 , 78) |
| 5. conclusion and dismissal of the petition. (Para 100) |
Judgment
1. By this petition, under Section 9 of the Arbitration & Conciliation Act 1996 (hereinafter referred to as "the 1996 Act"), the petitioner SMS Ltd. prays for pre-arbitral injunction, restraining the respondent ONGC Ltd. from acting in furtherance of a letter dated 15th December, 2020, issued by the latter to the former. The letter reads thus:
"OIL AND NATURAL GAS CORPORATION LIMITED
Onshore Engineering Services
Materials Management Section
2nd Floor, Tower -B Deendayal Urja Bhava, 5,
Nelson Mandela Road, Delhi-110070
Ref No. DLH/OES/MM/ETP-NADA &
AF/X11PC11001/2011 Dated: 15.12.2020
From: Office of GGM (MM)- i/c MM, Engineering Services, DDU Bhawan, Delhi
Onshore
TO:
M/s. SMS Limited (Formerly M/s.
SMS Infrastructure Limited)
(Consortium of M/s. SMS Limited,
Nagpur, M/s. Zen Marketing &
Technologies, Kolkata and M/s.
Tolani Projects Pvt. Ltd.,
Ankleshwar)
IT PARK. 20 S.T.P.I
GAYATRI NAGAR,
PARSODI, NAGPUR-
440022
Kind Attn:
Shri Hemant
Hathiwala, CEO
Sub: Amendment No. 11 to the Contract No. DLH/OES/MM/ETP-NADA & AF/X11PC11001/2011 dtd. 27.06.2012 for the Project 'Construction of ETP at Nada, Additional Handling Facilities alongwith laying of associated Pipelines in Area-Nat Ankleshwar Asset (ETP-Nada & AF)'______________________________________
Dear Sir(s),
Please refer the Contract No. DLH/OES/MM/ETP-NADA & AF/X11PC11001/2011 dated 27.06.2012 for the Project for "Construction of ETP at Nada, Additional Handling Facilities alongwith laying of associated Pipelines in Area-IV at Ankleshwar Asset (ETP-Nada & AF)". ONGC hereby extends the scheduled completion period of the LSTK contract (Refer clause 6.3 of General conditions of contract for LSTK portion, Annexure-A, Part-A of the contract) from 31.07.2014 to 31.07.2018 with levy of 10 % Liquidated Damages amounting to Rs. 12,09,83,122.10 as per the clause no.6.3.2 of General conditions of contract for LSTK portion, Annexure-A Part-A of the contract, plus GST thereon of Rs.2,17, 76,961.97 (as per GST legislation effective from 01.07.2017) totaling to Rs. 14,27,60,084.00 as detailed below:
| Delay solely attributable to Consortium as on 18.07.2018 | a) 3 Years 5 Months and 12 days in completion of standalone facilities (at Padra, Dabka, Jambusar, North Gandhar, GGS-Nada and ETP-Nada) b) 3 Years 11 Months and 18 days in completion of GRE Pipelines. |
| Liquidated Damages@ 0.5% per week & part thereof for the delay | 10% (maximum) |
| Liquidated Damages amount | Rs.12,09,83,122.10 |
| GST on Liquidated Damages amount @ 18% | Rs. 2,17,76,961.97 |
| Total Liquidated Damages + GST | Rs. 14,27,60,084.00 |
Accordingly, ONGC hereby requests you to remit the amount of Rs. 14,27,60,084.00 towards Liquidated damages and GST thereon to ONGC by 22.12.2020.
In case the amount of Rs. 14,27,60,084.00 is not remitted to ONGC by 22.12.2020, then LD and GST shall be recovered by invoking and encashing the Bank Guarantees submitted by you towards Liquidated damages and GST thereon as per provisions of the contract, as detailed below:
| Bank Guarantee particulars | (i) Bank Guarantee No. 0713614BG0000139 for Rs.12,09,90,000.00 issued by SBI, Industrial Finance Branch, Nagpur. (ii) Bank Guarantee No. 3761ILG003620 for Rs.2,66,17,800.00 issued by Punjab National Bank, Dharmpeth, Nagpur. |
| Total amount of bank Guarantees | Rs.14,76,07,800.00 (i.e. Rs.12,09,90,000.00 + Rs.2,66, 17,800.00) |
| GST@ 18% on the total amount of Bank Guarantees | Rs. 2,65,69,404.00 |
| Balance available after deposit of GST to Government authorities whi |
American Cyanamid Company vs. Ethicon Ltd.
BSES Ltd. vs. Fenner India Ltd.
Hindustan Construction Co. Ltd. vs. State of Bihar
Hindustan Construction Company Ltd. vs. State of Bihar
M. R. Engineers & Contractors Pvt Ltd. vs. Som Datt Builders Ltd.
Mohd. Alauddin vs. Karam Thamarjit Singh (2010) 7 SCC 530
Shiv Kumar Sharma vs. Santosh Kumari (2007) 8 SCC 600
Supreme Court in O.N.G.C. vs. S.B.I.
U.P. Cooperative Federation Ltd. vs. Singh Consultants & Engineers
U.P. State Sugar Corpn. vs. Sumac International Ltd
U.P. State Sugar Corpn. vs. Sumac International Ltd.
The court clarified that injunction against unconditional bank guarantees requires proof of egregious fraud, irretrievable injustice, or special equities, none of which were sufficiently substantiate....
A confirmed Bank Guarantee/irrevocable Letter of Credit cannot be interfered with unless there is established fraud or irretrievable injustice involved in case.
The court emphasized the independence and unconditional nature of bank guarantees, while recognizing exceptions such as fraud, irretrievable injustice, or special equities.
Unconditional bank guarantees may only be reviewed for egregious fraud or irretrievable injustice; disputes over contract performance must be resolved through arbitration.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.