| 1. overview and objectives of the kidwai nagar redevelopment project. (Para 1 , 3 , 4 , 5 , 6 , 7) |
| 2. petitioner arguments against redevelopment impact on environment and infrastructure. (Para 2 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16) |
| 3. responsive measures taken by authorities to address project concerns. (Para 34 , 35 , 37 , 38 , 39 , 40) |
| 4. balancing development with environmental protections and legal framework. (Para 69 , 70 , 71 , 72) |
| 5. conclusion affirming the project's compliance with legal norms. (Para 130 , 131) |
JUDGMENT
1. The present petition has been filed by the petitioners praying for the following relief:
"(a) Pass a writ of mandamus thereby directing all the concerned agencies to ensure that the residential character of the colony of South Ex-II and the adjoining areas that have lost their residential nature due to unprecedented unchecked commercial growth is restored,
(b) Pass a writ of mandamus thereby directing the concerned authority to ensure that the illegal parking inside the colony is stopped forthwith,
(c) Pass a writ of mandamus thereby directing the respondent no. 3 to take action on the decision of the monitoring committee thereby denotifying the commercial street D8-D15 and take appropriate action against the illegal commercialization of streets D1-D7 and M1-M10, and
(d) Pass a writ of mandamus thereby directing the Environment Pollution Control Authority (EPCA) to give a comprehensive report on the impact of commercialization and development of Kidwai Nagar on the ring road and residents of colonies along the ring road with full details of environmental impact.
(e) Pass a writ of mandamus thereby directing the EPCA to give detailed survey and furnish report on the illegal commercial activities and also to produce the survey report and all other related facts based on which the illegal commercial activity has been permitted.
(f) Pass a writ of mandamus thereby directing TERI (The Energy and Research Institute) and DPCC (Delhi Pollution Control Committee) to submit report of sound and air pollution in the area. Also the location of testing instruments should be decided in consultation with the Petitioners in writing so that the true and correct reading of the instruments can be ensured.
(g) Pass a writ of mandamus thereby directing the Fire Department and Delhi Traffic Police to give report confirming the free access in case of emergency.
(h) Pass a writ of mandamus thereby directing EPCA/Fire Dept./Delhi Traffic Police to conduct a survey and provide their report/NOC whether NDSE-2 is suitable to access in case of emergency on account of presence of commercial activity.
(i) Pass a writ of mandamus thereby directing MCD/DDA to produce the rights/obligations under category B of House Tax classifications. Also to direct MCD to disclose on affidavit the house tax collected from South Ex residential area and its utilization in the residential area in the past 10 years.
(j) Pass a writ of mandamus thereby directing all the concerned agencies that the green belt within and surrounding the colony is protected and not used for any construction.
(k) Pass a writ of prohibition thereby restraining the re-development of Kidwai Nagar project till the present problems of traffic congestion and parking are not addressed by the respondent authorities.
(l) Pass a writ of mandamus directing ASI to disclose if and as to how it had granted permission of such huge project next to the heritage monument Tomb of Darya Khan."
2. At the outset, the learned counsel for the petitioners submits that she wishes to confine her prayer only to the issues pertaining to redevelopment of Kidwai Nagar (East) and for the other prayers, the petitioners will be seeking appropriate remedy in accordance with law, if so advised. In fact, it is noticed that right from the filing of the petition, the focus of the petition has been only on the redevelopment of Kidwai Nagar (East). The petition is therefore, confined to this lim
AI
The redevelopment of urban areas must conform to the statutory master plan while balancing development needs and environmental protections, with close adherence to traffic management and social infra....
The main legal point established in the judgment is that the closure of public roads must follow the mandatory procedure as per the provisions of Section 203 of the NDMC Act. The court's decision emp....
Public lands designated for parks cannot be repurposed for commercial use without proper authority and procedural compliance, as dictated by urban planning laws.
The court mandated the Jaipur Development Authority to construct a planned 100 ft. road as per the Master Plan and remove all encroachments obstructing public infrastructure, emphasizing judicial res....
Judgment underscores the need for regulatory compliance in urban development, confirming that unauthorized de-licensing and changes in land-use violate statutory framework, necessitating CBI investig....
Re-densification policy upheld with compensatory afforestation enhancing green cover, balancing development and environmental safeguards.
Re-densification policy upheld with enhanced green spaces and 10:1 tree plantation compensating park use and tree removal.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.