SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Guj) 1762

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
Sunita Agarwal, C.J., D.N.Ray, J.
Arvind Mills Ltd. – Appellant
Versus
Bharat Heavy Electrical Ltd. – Defendant
R/First Appeal No. 1180 of 2007, R/Cross Objection No. 29 of 2009
Decided On : 14-11-2025

Advocates Appeared: For the Appellant :Mr. Saurabh Soparkar, Sr. Advocate with Mr. Parth Contractor, Mr Mihir Thakore, Sr. Advocate with Varun K.Patel For the Defendant:Mr. Mihir Thakore, Sr. Advocate with Varun K.Patel, Mr. Saurabh Soparkar, Sr. Advocate with Mr. Parth Contractor

The scope of an arbitrator's authority includes adherence to contract terms, and errors in jurisdiction arise from deviations from those terms, leading to the reinstatement of the original arbitral award.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Appeal against partial setting aside of arbitral award - The learned Judge set aside the award based on a cryptic reasoning without engaging with the evidence or provisions outlined in Annexure-A, leading to an intelligibility issue in the order. The appellant was awarded Rs. 3,56,62,000 including interest. The appeal upheld the arbitrator's decision recognizing that non-installation of wind masts resulted in inadequate evaluation of performance under the contract. The contract stated guaranteed performance, but the awarded evaluation used published data from insufficient wind measurements. (Paras 1-128)

(B) Arbitration - Scope of the Arbitrator's Authority - The Arbitrator must adhere to contract terms; deviations lead to jurisdictional errors. (Paras 75-84)

Facts of the case:
The dispute arose concerning the performance of Wind Turbine Generators under contract terms leading to arbitration. The respondent (BHEL) failed to perform under terms, resulting in claims against them which were partially upheld by arbitration.

Findings of Court:
The judgment by the lower court failed to adequately reason its decision, focusing on technical details without addressing key documents and evidence that supported the award.

Issues: The ambiguity regarding the use of wind data for performance evaluation and the implications of the absence of actual data were central to the case.

Ratio Decidendi: The court concluded that relying on the Arbitrator's interpretations was paramount and that the contractual obligations and mutual expectations must guide any performance assessments.

Result: The appeal was allowed, reinstating the original arbitrator’s award in favor of the appellant.

Table of Content
1. facts surrounding the arbitration case. (Para 1 , 2 , 3)
2. parties contest the validity of the arbitrator's award. (Para 4 , 5 , 6)
3. court identifies procedural shortcomings in arbitrator's decision. (Para 7 , 8 , 9 , 10 , 11)
4. court analyzes parties' arguments and appointed procedural details. (Para 12 , 14 , 15)
5. conditions of contract specifying wind data validity questions. (Para 19 , 20 , 21)
6. clarification of whether wind data must pertain to the actual site. (Para 22 , 25 , 26 , 32)
7. final decision reinstating the arbitral award based on established facts. (Para 121 , 126 , 128)

JUDGMENT :

Sunita Agarwal, C.J., D.N.Ray, J.

1. This is an old appeal filed under Section 37 of the Arbitration and Conciliation Act, 1996 (in short as ‘the Act, 1996’) of the year 2007, challenging the judgment and order dated 02.01.2007 passed by the Court of City Civil Judge, Ahmedabad in allowing the Civil Misc. Application No. 51 of 2004 under the Act, 1996, whereby the award dated 15th October, 2003 passed by the learned sole Arbitrator has been set aside in part.

2. The facts, in brief, for effective adjudication of the present appeal are to be noted at the outset. Bharat Heavy Electrical Ltd. (BHEL), namely the respondent herein, had submitted an offer for supply, erection, commissioning and starting up operations and maintenance of 15 numbers of Wind Turbine Generators (WTGs) including the designing, supply and commissioning and associated electricals, auxiliary equipments, civil work and connected services at the proposed site. Accordingly, the order to install the wind power plants was placed by the appellant herein. The order placed on record contains the detail terms and conditions of the contract regarding payments, and in case of non- performance of contract, penalty etc. and also other substantial clauses.

3. It appears that a dispute arose between the parties pertaining to the terms of the agreement and the matter was referred to the learned Arbitrator, who had passed the award dated 15.10.2003 in favour of the appellant herein awarding a sum of Rs. 3,56,62,000.00/- including interest of amount Rs. 73,22,000.00. The total awarded amount came to Rs.4,01,33,000.00 alongwith interest @ 10% p.a.. till realisation.

4. The respondent (BHEL) herein filed application under Section 34 of the Act, 1996 challenging the award on the ground that once the learned Arbitrator had held that the time was not the essence of the contract and that the original contract did not survive and there was novatio contract, the award of penalty of Rs. 64,000.00, as per the original contract was illegal. It was also contended that the erection of wind masts by the applicant/respondent herein was not with any time schedule and the wind mast could be erected after the completion of erection of Wind Turbine Generators. It was submitted that the learned Arbitrator has himself held that there was delay on the part of the appellant to provide land and hence, the respondent could not be saddled with the responsibility of not erecting the wind mast. Moreover, as per the terms of the contract, the working of the machines (WTGs) was to be calculated on the basis of the wind data at Harshad site and the learned Arbitrator has wrongly relied on the data published for Navadra site, which was otherwise for the previous year and not for the period in question. It was, thus, contended that the basis of calculation being the previous year data to assess the working capacity of the machines (WTGs) itself makes the award bad, inasmuch as, the learned Arbitrator himself admitted that wind power change from month to month due to ecological change in the atmosphere. The whole comparison made by the learned Arbitrator for Navadra wind area was, thus, an absurd decision.

5. From a perusal of the order passed by the Court under Section 34 of the Act, 1996, it may be noted that the contention of the respondent therein was that it was further agreed between the partie

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top