SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(All) 1379

IN THE HIGH COURT OF ALLAHABAD
VIKRAM D. CHAUHAN, MANOJ KUMAR GUPTA, JJ.
Hindustan Steelworks Construction Limited - Appellant
Versus
New Okhla Industrial Development Authority - Respondent
Appeal Under Section 37 Of Arbitration And Conciliation Act 1996 No. 219 of 2022
Decided On : 22-09-2023

Advocates Appeared:
For the Appellant : Varad Nath, Agarwal Archi Piyush.
For the Respondent: Kaushalendra Nath Singh.

The court ruled that waivers in commercial contracts must be respected unless coercion is proven, clarifying that economic pressure does not inherently constitute duress.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37 - Commercial Courts Act, 2015 - Appeal against setting aside arbitral award - Appellant claimed price variation and damages for suspension of work under GCC clauses; respondent pleaded waiver of claims in supplementary MoU - Both parties entered a supplementary MoU where appellant agreed not to claim any damages - Court found the plea of coercion and undue influence failed and upheld the trial court’s decision, asserting that appellants' agreement was voluntary and within their economic interests. (Paras 125-148)

(B) Doctrine of Severability - Court held the doctrine applicable to allow severing unsustainable parts of the award - Valid claims upheld while void claims were set aside, allowing partial setting aside of the award without requiring a fresh arbitration process. (Para 147)

Facts of the case:
Dispute arose between a government corporation and a civic authority regarding contract execution of flyovers - Work suspended leading to arbitration over negotiations and claims.

Findings of Court:
The Commercial Court set aside part of the arbitral award, finding no coercion in signing the supplementary MoU.

Issues: The main issues included the validity of the supplementary MoU and whether the waiver of claims was made under coercion.

Ratio Decidendi: The Court held that coercion could not be established based on the presented evidence and emphasized the legitimacy of the commercial negotiations and voluntary agreement of the parties.

Result: Appeal allowed in part, claims for damages set aside while valid claims upheld.

Table of Content
1. appellant's challenge based on act provisions (Para 1 , 2 , 3 , 4 , 5)
2. details of contract negotiations and issues (Para 6 , 7 , 8 , 9 , 10)
3. formation and implications of supplementary mou (Para 11 , 12 , 13 , 14 , 15)
4. claims and arbitration initiation (Para 16 , 17 , 18 , 19 , 20)
5. overview of arbitration proceedings (Para 21 , 22)
6. findings of the arbitral tribunal (Para 23 , 24 , 25)
7. legal grounds for setting aside the arbitral award (Para 26 , 27 , 28 , 29 , 30)
8. arguments regarding the commercial court's findings (Para 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41)
9. respondent's counterarguments regarding coercion (Para 45 , 46 , 47 , 48 , 49 , 50)
10. judgement on the grounds for setting aside (Para 51 , 52)
11. discussion on section 34 of arbitration act (Para 53 , 54 , 55)
12. power of the court under section 34 (Para 114 , 115 , 116 , 117)
13. final remarks on severability principle (Para 118 , 119 , 120)

JUDGMENT :

(Manoj Kumar Gupta, J.)

1. The instant appeal has been filed under Section 13 of the Commercial Courts, Commercial Division and Commercial Appellate Division of High Courts Act , 2015 read with Section 37 of the Arbitration and Conciliation Act, 1996 (for the sake of brevity hereinafter referred to as 'the Act') challenging the order of the Commercial Court, Gautam Budh Nagar dated 23.5.2022 in Arbitration Case No. 13 of 2015, setting aside the Arbitral Award dated 15.12.2014, by the Sole Arbitrator, in a dispute between the parties.

BACKGROUND

2. In the year 2002, the New Okhla Industrial Development Authority (NOIDA), the respondent herein, entered into negotiation with U.P. State Bridge Corporation Limited for construction of two flyovers with clover leaves and allied work at M.P. Road No.3 Express Highway near Amity School and at T-junction near Film City, Gautam Budh Nagar. It submitted a proposal of Rs.106.10 crores for execution of the Project on turnkey basis, including centage charges but which was not accepted.

3. The appellant herein, i.e. Hindustan Steel Works Construction Limited (HSCL), is a Government of India Undertaking, registered under the Companies Act, 1956. It also gave proposal to NOIDA to execute the Project at the same cost of Rs.106.10 crores. The offer of HSCL was accepted by NOIDA and the parties entered into a formal contract-a Memorandum of Understanding (MoU) on 27.03.2003. The work under the contract was to be completed by the HSCL within 27 months from the date of start, which was to be counted from 30 days after the receipt of deposit advance from NOIDA or from the date of possession of land, which ever is earlier. The HSCL was obliged to submit performance security equivalent to 5% of the contract value in shape of bank guarantee. NOIDA was under obligation to pay interest free deposit advance of 15% of project cost secured by the bank guarantee (excluding centage charges) within thirty days from the date of award of work. The advance so paid was to be adjusted in the subsequent demand of funds on the basis of actual work executed by HSCL. The subsequent demand was to be submitted after utilization of 75% of the deposit advance released as above. Under Clause 7, HSCL was entitled to price variation in cost of building material as per NHAI guidelines and formula for computing the same was provided for in the General Conditions of Contract (GCC) executed between the parties in addition to the MoU. Clause 11 stipulated that if the work is temporarily suspended due to any reason which is not attributable to HSCL, suitable extension of time shall be granted by the NOIDA on the request of HSCL. In case the work is delayed due to reasons attributable to HSCL, it was made liable to penalty at the rate of 5% per month of centage charges to NOIDA. The period for which extension would be granted is provided in the GCC. The GCC also provided for compen

                              Click Here to Read the rest of this document
                              1
                              2
                              3
                              4
                              5
                              6
                              7
                              8
                              9
                              10
                              11
                              SupremeToday Portrait Ad
                              supreme today icon
                              logo-black

                              An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                              Please visit our Training & Support
                              Center or Contact Us for assistance

                              qr

                              Scan Me!

                              India’s Legal research and Law Firm App, Download now!

                              For Daily Legal Updates, Join us on :

                              whatsapp-icon Back to top