IN THE HIGH COURT OF JUDICATURE AT MADRAS
A.D. Maria Clete, J.
The Superintending Engineer, Tamil Nadu Electricity Board - Petitioner
Versus
T.Babu, S/o. Thirumalaisamy and ors. – Respondent
W.P.Nos. 12192 of 2020 and 14822 of 2021 and W.M.P. No.14930 of 2020 and W.M.P.Nos.3812, 3817, 3818, 3827, 3828, 3832, 3834, 3836, 3844, 3845 and 3847 of 2021
Decided On : 20-03-2025
| Table of Content |
|---|
| 1. challenge to the labour court's award on worker's reinstatement. (Para 2 , 3 , 4 , 5 , 6 , 7) |
| 2. framing issues regarding employer-employee relationship and contract legitimacy. (Para 8 , 12 , 14) |
| 3. evidence against the claims of contract work legitimacy. (Para 9 , 10) |
| 4. precedents affecting the resolution of delay and reinstatement. (Para 13 , 28 , 36) |
| 5. delay in filing the claim and implications on the case. (Para 22 , 24 , 26) |
| 6. legal implications of retrenchment under the industrial disputes act and court's rationale. (Para 27) |
| 7. final observations and decisions regarding the claims raised by workmen. (Para 34 , 35) |
| 8. outcome dismissing both writ petitions. (Para 38) |
JUDGMENT :
A.D. Maria Clete, J.
Heard.
2.In the first writ petition, the Petitioner, the Superintending Engineer of the Tamil Nadu Electricity Board, Kadamparai Electricity Generation Circle (hereinafter referred to as the "Electricity Board"), challenges a common award issued by the First Additional Labour Court, Coimbatore, on 05.04.2018. The award pertains to 11 industrial disputes raised by 11 respondents (hereinafter referred to as the "workmen"), each of whom had individually approached the labour court. By the impugned award, the labour court set aside the oral terminations of the 11 workmen and directed their reinstatement within one month from the date the award takes effect. However, the labour court declined to grant continuity of service, back wages, or attendant benefits.
3. Aggrieved by the common award, the Electricity Board filed a single writ petition. When the matter was taken up on 08.09.2020, notice was ordered in the writ petition, and private notice was also permitted. In the meantime, upon receiving notice of the writ petition filed by the Electricity Board, the 11 workmen, who were also aggrieved by the same common award dated 05.04.2018, filed a second writ petition challenging the portion of the award that denied them continuity of service, back wages, and other attendant benefits.
4. In the second writ petition, when the matter was taken up on 19.07.2021, it was admitted, and notice was ordered to the respondent Electricity Board. It was further directed that the said writ petition be heard along with the first writ petition filed by the Electricity Board. However, when the matter was subsequently listed on 05.11.2024, it was referred for adjudication before the Lok Adalat scheduled for 14.12.2024. As no settlement was reached in the Lok Adalat, and when the first writ petition filed by the Electricity Board was taken up for final disposal, the second writ petition filed by the workmen was also tagged along. Consequently, a common judgment has been pronounced in both matters.
5. The records reveal that the 11 workmen raised disputes before the Government Labour Officer, Coimbatore, challenging their oral termination on different dates as follows: I.D.No.234/2006 (T. Babu) – 20.07.1998 I.D.No.235/2006 (T. Ravichandran) – 30.10.1998, I.D.No.236/2006 (T. Rajaselvan) – 31.12.1997, I.D.No.237/2006 (P. Suresh) – 30.10.1998, I.D.No.240/2006 (S. Ramesh) – 30.04.1999, I.D.No.243/2006 (K. Parvathi) – 05.03.1998, I.D.No.248/2006 (K. Arumugam) – 31.07.1996, I.D.No.249/2006 (K. Selvaraj) – 31.03.1998, I.D.No.250/2006 (K. Mylsami) – 23.08.1998, I.D.No.254/2006 (K. Manikandan) – 31.12.1997, I.D.No.256/2006 (P. Lawrence D’Cruz) – 16.12.1999.
6. The Labour Officer, after issuing due notice to the Electricity Board, submitted failure reports on various dates, including 03.03.2006, 27.07.2006, 27.03.2006, 24.03.2006, and 09.11.2006. Based on these failure reports, the 11 workmen filed their respective claim statements dated 08.09.2006 before the Labour Court, Coimbatore. The Labour Court registered the disputes as I.D.Nos. 234 to 237 of 2006, 240 of 2006, 243 of 2006, 248 to 250 of 2006, and 254 of 2006, 256 of 2006. The Electricity Board entered an appearance and filed separate but identical counter statements dated 07.06.2017 in the first 1


Prabhakar Vs. Joint Director Sericulture Department
Uttaranchal Forest Development Corporation Vs. M.C.Joshi
State of Karnataka & Anr. Vs. Ravi Kumar
Director, Fisheries Terminal Division v. Bhikubhai Meghajibhai Chavda
J.K.Synthetics Ltd Vs. K.P.Agrawal & Anr
Gaziabad Development Authority & Anr. Vs. Ashok Kumar & Anr
Sita Ram Vs. Moti Lal Nehru Farmers Training Institute
Uttar Pradesh State Electricity Board Vs. Laxmi Kant Gupta
Assistant Engineer Rajastan Development Corporation & Anr. Vs. Gitam Singh
K.V.Anil Mithra Vs. Sree Sankaracharya University of Sanskrit
State Bank of India v. Sundara Money
Deepali Gundu Surwase Vs. Kranti Junior Adhyapak Mahavidyala
Manager, Reserve Bank of India, Bangalore Vs. S.Mani & Ors
Bharat Heavy Electricals Ltd Vs. Anil & Ors.
Rajasthan State Transport Corporation & anr. Vs. Krishna Kant & Ors.
Kanpur Electricity Board Company Ltd Vs. Shamim Mirza
Harjinder Singh Vs. Punjab State Warehousing corporation
Anoop Sharma Vs. Executive Engineer, Public Health Division No.1, Haryana
Devinder Singh Vs. Municipal Council, Sanaur
Hari Nandan Prasad Vs. Employer I/R to Management of Food Corporation of India
Court upheld the labour court's decision, recognizing the workmen as employees despite the employer's claims of a contract system, while denying back wages due to the workmen's delay in pursuing clai....
The central legal point established in the judgment is the requirement for contract labourers to comply with the terms and conditions stipulated for regularisation and permanent absorption, including....
Termination due to discontinuation of a scheme amounts to retrenchment requiring compliance with statutory provisions under the Industrial Disputes Act.
there is a breach of Section 25-F of the I.D. Act and as there is a delay of 11 years in preferring the reference, instead of granting reinstatement a lump sum amount as full and final settlement wil....
Labour Court has held against the workman on the basis that the documents like pay sleep, muster roll etc. are not produced. But, at this juncture, it is require to peruse the oral evidence of the wo....
Labour law – Reinstatement - Granting of relief of reinstatement after such a long gap will not serve any purpose and, therefore, this Court is of the view that if the order to grant compensation
The main legal point established in the judgment is the requirement for compliance with the provisions of the Industrial Disputes Act, 1947, particularly in cases of termination and retrenchment, and....
Point of law :Labour Law - There is no proof that the workman has worked for 240 days and, therefore, it was held by the Labour Court that there is no proof that the workman was working continuously ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.