IN THE HIGH COURT OF MADHYA PRADESH AT JABALPUR
S.K. Seth, Sujoy Paul, J.P. Gupta, JJ.
Viva Highways Ltd. - Appellant
Versus
Madhya Pradesh Road Development Corporation Ltd. - Respondent
A.A. No.14 of 2017, 14 of 2017, A.C. No.27 of 2013, 79 of 2016
Decided on : 05-05-2017
Whether, any agreement by whatever name called, if it falls within the meaning and definition of work contract as defined under Section 2(I) of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 has to be referred for adjudication before the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym? Whether, in view of statutory provisions of Section 7 of the Adhiniyam of 1983, the matter has to be referred to the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym, even in cases where the parties have incorporated a clause in agreement regarding resolution of dispute by some other forum or under the Arbitration and Conciliation Act, 1996? Which of the views taken by the Division Bench of Ashoka Infraways Ltd. is correct relying on Jabalpur Corridor (India) Pvt. Ltd. ? Whether, the substituted definition of work contract in the M.P. Madhyastham Adhikaran Adhiniyam, 1983 by Act No.7 of 2017 is clarifactory and is applicable to the pending or future contracts? Any other ancillary issues arising out of the reference order.
Fact of the Case:
The order of reference dated 31.1.2017 which occasioned the constitution of this Full Bench has been passed by a Division Bench in AC No.27/2013 (M/s ESSEL Infra Projects Ltd. v. State of M.P.). The relevant facts giving rise to the reference are that the aforesaid arbitration case filed under Section 11(6) of Arbitration and Conciliation Act, 1996 (for short 'Act of 1996') was listed before the learned Single Judge wherein it is prayed that an appropriate Arbitrator may be appointed as per the relevant dispute resolution clause in the agreement. During the course of hearing of the said matter before the learned Single Judge, the respondents have raised an objection as to maintainability of the application under Section 11(6) of the Act of 1996 on the ground that the provisions of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 (Adhiniyam of 1983) are applicable for the dispute between the parties and; therefore, matter has to be referred to the Tribunal constituted under the Adhiniyam of 1983.
Finding of the Court:
Any agreement by whatever name called, if it falls within the meaning and definition of "works contract" as defined under Section 2(I) of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 has to be referred for adjudication before the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym. In view of statutory provisions of Section 7 of the Adhiniyam of 1983, the matter has to be referred to the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym, even in cases where the parties have incorporated a clause in agreement regarding resolution of dispute by some other forum or under the Arbitration and Conciliation Act, 1996. The view taken by the Division Bench in Ashoka Infraways Ltd. relying on Jabalpur Corridor (India) Pvt. Ltd. is correct. The substituted definition of work contract in the M.P. Madhyastham Adhikaran Adhiniyam, 1983 by Act No.7 of 2017 is clarifactory and is applicable to the pending or future contracts. The words "claim of ascertained money" have a definite connotation and therefore only such difference arising out of execution or non-execution of a 'works contract' which are related with claims of above nature will be covered under Section 2(d) of the Adhiniyam of 1983.
Issues: Whether, any agreement by whatever name called, if it falls within the meaning and definition of work contract as defined under Section 2(I) of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 has to be referred for adjudication before the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym? Whether, in view of statutory provisions of Section 7 of the Adhiniyam of 1983, the matter has to be referred to the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym, even in cases where the parties have incorporated a clause in agreement regarding resolution of dispute by some other forum or under the Arbitration and Conciliation Act, 1996? Which of the views taken by the Division Bench of Ashoka Infraways Ltd. is correct relying on Jabalpur Corridor (India) Pvt. Ltd. ? Whether, the substituted definition of work contract in the M.P. Madhyastham Adhikaran Adhiniyam, 1983 by Act No.7 of 2017 is clarifactory and is applicable to the pending or future contracts? Any other ancillary issues arising out of the reference order.
Ratio Decidendi: The definition of "works contract" as defined under Section 2(I) of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 is wide enough to include the concession agreement if it fulfils the necessary ingredients of a works contract. The amendment in the definition of "works contract" is clarificatory in nature and is applicable to pending and future contracts. The words "claim of ascertained money" have a definite connotation and therefore only such difference arising out of execution or non-execution of a 'works contract' which are related with claims of above nature will be covered under Section 2(d) of the Adhiniyam of 1983.
Final Decision: The reference is decided accordingly.
Sujoy Paul, J.
1. The order of reference dated 31.1.2017 which has occasioned the constitution of this Full Bench has been passed by a Division Bench in AC No.27/2013 (M/s ESSEL Infra Projects Ltd. v. State of M.P.).
2. The relevant facts giving rise to the reference are that the aforesaid arbitration case filed under Section 11(6) of Arbitration and Conciliation Act, 1996 (for short 'Act of 1996') was listed before the learned Single Judge wherein it is prayed that an appropriate Arbitrator may be appointed as per the relevant dispute resolution clause in the agreement. During the course of hearing of the said matter before the learned Single Judge, the respondents have raised an objection as to maintainability of the application under Section 11(6) of the Act of 1996 on the ground that the provisions of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 (Adhiniyam of 1983) are applicable for the dispute between the parties and; therefore, matter has to be referred to the Tribunal constituted under the Adhiniyam of 1983.
3. During the course of hearing before the learned Single Judge, the parties cited single bench decision of this court rendered in the case of Jabalpur Corridor (India) Pvt. Ltd. v. M.P. Road Development Corporation, 2014 (2) MPLJ 276 and judgment of another Single Bench in the case of Mrs. Kamini Malhotra v. State of M.P., AIR 2003 MP 13. The learned single judge opined that there is a conflict between the aforesaid two decisions and therefore ordered that the matter be placed before Hon'ble the Chief Justice for constituting a larger bench.
4. In view of aforesaid order of learned Single Judge, the matter was placed before the Division Bench. Before the Division Bench, it was fairly admitted by the parties that earlier decision in the case of Mrs. Kamini Malhotra(Supra) was not brought to the notice of the subsequent bench which decided the case of Jabalpur Corridor(Supra). Before the Division Bench, two Division Bench decisions were placed i.e. in the case of Ashok Infraways Ltd. And another v. State of M.P. and another, 2016 (2) MPLJ 685 and State of M.P. and another v. M/s K.T. Construction (India) Ltd. and another (A.A. No.5/2009 decided on 27.4.2016). It was argued before the Division Bench that in aforesaid two Division Bench decisions, the judgment in the case of Jabalpur Corridor(Supra) has been affirmed and confirmed. Since the Single Bench judgment of Jabalpur Corridor was applied and affirmed in aforesaid two Division Bench judgments, the question of any conflict between Jabalpur Corridor and Mrs. Kamini Malhotra does not arise.
5. The Division Bench during the course of hearing noticed that between the same parties who were involved in Division Bench decision rendered in the case of Ashok Infraways Ltd.(Supra) previously WP No.1122/2015 was filed wherein challenge was made to the order of District Judge, Dewas passed while deciding an application under Section 9 of the Act of 1996. The said WP was initially dismissed as not maintainable but subsequently taken up in Review Petition No.191/2015. The Division Bench in said RP passed an order dated 31.7.2015 holding that contract between the parties i.e. Ashoka Infraways Ltd. and another v. State of Madhya Pradesh and another was in the nature of a "works contract" and; therefore, the provisions of Adhiniyam of 1983 would apply. It was noticed by Division Bench that the aforesaid order passed in writ petition as well as review petition was challenged before the Supreme Court in SLP(Civil) No.22890-22891/2015. The Supreme Court disposed of the aforesaid SLPs by quoting findings recorded by Division Bench of this Court to the effect that the dispute between the parties pertains to a works contract and shall be referred to the Tribunal under the provisions of Adhiniyam, 1983. Thereafter, taking note of the fact that an arbitration appeal under Section 17 of the Act of 1996 was pending before this court, disposed of the SLP by observing that
APS Kushwaha (SSI Unit) v. The Municipal Corporation, Gwalior
Ashoka Infraways Ltd. v. State of M.P., 2016 (2) MPLJ 685 : WP No.3057 of 2016
Board of Mining Examining v. Ramjee
Commissioner of Income Tax (Central)-I, New Delhi v. Vatika Township Pvt. Ltd.
Delhi Cloth and General Mills Ltd. v. CIT Delhi
Gurbachan Singh v. Satpal Singh
Hitendra Vishnu Thakur v. State of Maharashtra
Indian Aluminium Co. v. State of Kerala
Jabalpur Corridor (India) Pvt. Ltd. v. M.P. Road Development Corporation
Kone Elevator India Pvt. Ltd. v. State of Tamil Nadu
Koteshwar Vitthal Kamad v. K. Rangappa Baliga
Larsen and Toubro Ltd. v. State of Karnataka
Lucknow Development Authority v. M.K. Gupta
Mahalakshmi Oil Mills v. State of Andhra Pradesh
Mescot Hospital & Research Centre v. State of M.P.
Molar Mal (Dead)] v. KAY Iron Works (P) Ltd.
Mrs. Kamini Malhotra v. State of M.P.
P. Kasilingam v. P.S.G. College of Technology
R.B.I. v. Peerless General Finance Co. Ltd.
R.V. Infrastructure Engineers Pvt. Ltd. v. State of M.P.
Raja Soap Factory v. S.P. Shantharaj
Shri Shankarnarayan Construction Co. v. State of M.P.
State of H.P. v. Nurpur Private Bus Operator Union
State of Himachal Pradesh v. Narain Singh
State of M.P. v. Anshuman Shukla
State of Punjab v. Salil Sabhlok
State of Rajasthan v. Mangilal Pindwal
State of W.B v. Kesoram Industries Ltd
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
A valid signature must be in the candidate's own handwriting, as emphasized by the General Clauses Act and relevant case law.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.