SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2017 Supreme(MP) 180

IN THE HIGH COURT OF MADHYA PRADESH AT JABALPUR
S.K. Seth, Sujoy Paul, J.P. Gupta, JJ.
Viva Highways Ltd. - Appellant
Versus
Madhya Pradesh Road Development Corporation Ltd. - Respondent
A.A. No.14 of 2017, 14 of 2017, A.C. No.27 of 2013, 79 of 2016
Decided on : 05-05-2017

Advocate Appeared:
For the Appellant :Shri Jai Savla, with Shri Akshay Sapre, Advocates
For the Respondent:Shri P.K. Kaurav, Additional Advocate General with Shri Amit Seth, Government Advocate

The definition of "works contract" as defined under Section 2(I) of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 is wide enough to include the concession agreement if it fulfils the necessary ingredients of a works contract.

Headnote:

Whether, any agreement by whatever name called, if it falls within the meaning and definition of work contract as defined under Section 2(I) of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 has to be referred for adjudication before the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym? Whether, in view of statutory provisions of Section 7 of the Adhiniyam of 1983, the matter has to be referred to the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym, even in cases where the parties have incorporated a clause in agreement regarding resolution of dispute by some other forum or under the Arbitration and Conciliation Act, 1996? Which of the views taken by the Division Bench of Ashoka Infraways Ltd. is correct relying on Jabalpur Corridor (India) Pvt. Ltd. ? Whether, the substituted definition of work contract in the M.P. Madhyastham Adhikaran Adhiniyam, 1983 by Act No.7 of 2017 is clarifactory and is applicable to the pending or future contracts? Any other ancillary issues arising out of the reference order.

Fact of the Case:

The order of reference dated 31.1.2017 which occasioned the constitution of this Full Bench has been passed by a Division Bench in AC No.27/2013 (M/s ESSEL Infra Projects Ltd. v. State of M.P.). The relevant facts giving rise to the reference are that the aforesaid arbitration case filed under Section 11(6) of Arbitration and Conciliation Act, 1996 (for short 'Act of 1996') was listed before the learned Single Judge wherein it is prayed that an appropriate Arbitrator may be appointed as per the relevant dispute resolution clause in the agreement. During the course of hearing of the said matter before the learned Single Judge, the respondents have raised an objection as to maintainability of the application under Section 11(6) of the Act of 1996 on the ground that the provisions of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 (Adhiniyam of 1983) are applicable for the dispute between the parties and; therefore, matter has to be referred to the Tribunal constituted under the Adhiniyam of 1983.

Finding of the Court:

Any agreement by whatever name called, if it falls within the meaning and definition of "works contract" as defined under Section 2(I) of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 has to be referred for adjudication before the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym. In view of statutory provisions of Section 7 of the Adhiniyam of 1983, the matter has to be referred to the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym, even in cases where the parties have incorporated a clause in agreement regarding resolution of dispute by some other forum or under the Arbitration and Conciliation Act, 1996. The view taken by the Division Bench in Ashoka Infraways Ltd. relying on Jabalpur Corridor (India) Pvt. Ltd. is correct. The substituted definition of work contract in the M.P. Madhyastham Adhikaran Adhiniyam, 1983 by Act No.7 of 2017 is clarifactory and is applicable to the pending or future contracts. The words "claim of ascertained money" have a definite connotation and therefore only such difference arising out of execution or non-execution of a 'works contract' which are related with claims of above nature will be covered under Section 2(d) of the Adhiniyam of 1983.

Issues: Whether, any agreement by whatever name called, if it falls within the meaning and definition of work contract as defined under Section 2(I) of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 has to be referred for adjudication before the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym? Whether, in view of statutory provisions of Section 7 of the Adhiniyam of 1983, the matter has to be referred to the M.P. Arbitration Tribunal constituted under Section 3 of the 1983 Adhiniym, even in cases where the parties have incorporated a clause in agreement regarding resolution of dispute by some other forum or under the Arbitration and Conciliation Act, 1996? Which of the views taken by the Division Bench of Ashoka Infraways Ltd. is correct relying on Jabalpur Corridor (India) Pvt. Ltd. ? Whether, the substituted definition of work contract in the M.P. Madhyastham Adhikaran Adhiniyam, 1983 by Act No.7 of 2017 is clarifactory and is applicable to the pending or future contracts? Any other ancillary issues arising out of the reference order.

Ratio Decidendi: The definition of "works contract" as defined under Section 2(I) of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 is wide enough to include the concession agreement if it fulfils the necessary ingredients of a works contract. The amendment in the definition of "works contract" is clarificatory in nature and is applicable to pending and future contracts. The words "claim of ascertained money" have a definite connotation and therefore only such difference arising out of execution or non-execution of a 'works contract' which are related with claims of above nature will be covered under Section 2(d) of the Adhiniyam of 1983.

Final Decision: The reference is decided accordingly.

JUDGMENT :

Sujoy Paul, J.

1. The order of reference dated 31.1.2017 which has occasioned the constitution of this Full Bench has been passed by a Division Bench in AC No.27/2013 (M/s ESSEL Infra Projects Ltd. v. State of M.P.).

2. The relevant facts giving rise to the reference are that the aforesaid arbitration case filed under Section 11(6) of Arbitration and Conciliation Act, 1996 (for short 'Act of 1996') was listed before the learned Single Judge wherein it is prayed that an appropriate Arbitrator may be appointed as per the relevant dispute resolution clause in the agreement. During the course of hearing of the said matter before the learned Single Judge, the respondents have raised an objection as to maintainability of the application under Section 11(6) of the Act of 1996 on the ground that the provisions of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983 (Adhiniyam of 1983) are applicable for the dispute between the parties and; therefore, matter has to be referred to the Tribunal constituted under the Adhiniyam of 1983.

3. During the course of hearing before the learned Single Judge, the parties cited single bench decision of this court rendered in the case of Jabalpur Corridor (India) Pvt. Ltd. v. M.P. Road Development Corporation, 2014 (2) MPLJ 276 and judgment of another Single Bench in the case of Mrs. Kamini Malhotra v. State of M.P., AIR 2003 MP 13. The learned single judge opined that there is a conflict between the aforesaid two decisions and therefore ordered that the matter be placed before Hon'ble the Chief Justice for constituting a larger bench.

4. In view of aforesaid order of learned Single Judge, the matter was placed before the Division Bench. Before the Division Bench, it was fairly admitted by the parties that earlier decision in the case of Mrs. Kamini Malhotra(Supra) was not brought to the notice of the subsequent bench which decided the case of Jabalpur Corridor(Supra). Before the Division Bench, two Division Bench decisions were placed i.e. in the case of Ashok Infraways Ltd. And another v. State of M.P. and another, 2016 (2) MPLJ 685 and State of M.P. and another v. M/s K.T. Construction (India) Ltd. and another (A.A. No.5/2009 decided on 27.4.2016). It was argued before the Division Bench that in aforesaid two Division Bench decisions, the judgment in the case of Jabalpur Corridor(Supra) has been affirmed and confirmed. Since the Single Bench judgment of Jabalpur Corridor was applied and affirmed in aforesaid two Division Bench judgments, the question of any conflict between Jabalpur Corridor and Mrs. Kamini Malhotra does not arise.

5. The Division Bench during the course of hearing noticed that between the same parties who were involved in Division Bench decision rendered in the case of Ashok Infraways Ltd.(Supra) previously WP No.1122/2015 was filed wherein challenge was made to the order of District Judge, Dewas passed while deciding an application under Section 9 of the Act of 1996. The said WP was initially dismissed as not maintainable but subsequently taken up in Review Petition No.191/2015. The Division Bench in said RP passed an order dated 31.7.2015 holding that contract between the parties i.e. Ashoka Infraways Ltd. and another v. State of Madhya Pradesh and another was in the nature of a "works contract" and; therefore, the provisions of Adhiniyam of 1983 would apply. It was noticed by Division Bench that the aforesaid order passed in writ petition as well as review petition was challenged before the Supreme Court in SLP(Civil) No.22890-22891/2015. The Supreme Court disposed of the aforesaid SLPs by quoting findings recorded by Division Bench of this Court to the effect that the dispute between the parties pertains to a works contract and shall be referred to the Tribunal under the provisions of Adhiniyam, 1983. Thereafter, taking note of the fact that an arbitration appeal under Section 17 of the Act of 1996 was pending before this court, disposed of the SLP by observing that






















































































































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top